Home / Browse projects / Bengaluru Urban, Karnataka / ELV Kingsland

Registration approved Residential/Group Housing project

ELV Kingsland

By ELV Projects Pvt Ltd

RG-KA-00400 · RERA PRM/KA/RERA/1251/446/PR/181122/002144

Source: official RERA Karnataka filing

Red flags

  • 49 complaints at RERA Karnataka
  • Completion date moved by 32 months
  • 3 extensions taken

Clear

  • Separate project account declared
Aug 2024Possession promisedmoved 32 months from the original
49Complaints at RERA Karnatakaon this registration
Jump to the 22 documents Report an error

ELV Kingsland is a Residential/Group Housing project by ELV Projects Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/181122/002144 on 22 Nov 2018. Possession is promised by 30 Aug 2024. The completion date has moved by 32 months from the original filing. 49 complaints are on record with the regulator.

At a glance

Project

  • NameELV Kingsland
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/181122/002144
  • ReraGenie IDRG-KA-00400

Builder

  • NameELV Projects Pvt Ltd
  • Entity typeCompany
  • CINU45203KA2015PTC084790
  • Authorized SignatoryMr.E.Bhaskar

Key dates

this monthRegisteredNov 2018First promiseDec 2021Revised toAug 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on22 Nov 2018
  • Promised completion30 Aug 2024
  • Revised completionRevised to 30 Aug 2024 (originally 31 Dec 2021)
  • Buildings2 building records
  • Documents filed22 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A & B BLOCK---1070107
C BLOCK---54054

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalNoNot applicable
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,105 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 43.53 cr

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2021 → Sep 2022

No reason recorded in the filing

EX/PRM/KA/RERA/1251/446/PR/221109/002144Sep 2022 → Sep 2023

Reason as filed by the promoterForce Majeure

ExtensionSep 2023 → Aug 2024

No reason recorded in the filing

Complaints filed with RERA Karnataka49

Case no.ComplainantRespondentFiled
CMP/190611/0003276-ELV Projects Pvt Ltd11/06/2019
CMP/221010/0010082-ELV Projects Pvt Ltd10/10/2022
CMP/221114/0010276-ELV Projects Pvt Ltd14/11/2022
CMP/221114/0010278-ELV Projects Pvt Ltd14/11/2022
CMP/221114/0010283-ELV Projects Pvt Ltd14/11/2022
CMP/221114/0010285-ELV Projects Pvt Ltd14/11/2022
CMP/221114/0010286-ELV Projects Pvt Ltd14/11/2022
CMP/221114/0010288-ELV Projects Pvt Ltd14/11/2022
CMP/221114/0010291-ELV Projects Pvt Ltd14/11/2022
CMP/221114/0010292-ELV Projects Pvt Ltd14/11/2022
CMP/221114/0010293-ELV Projects Pvt Ltd14/11/2022
CMP/221114/0010313-ELV Projects Pvt Ltd14/11/2022
CMP/221114/0010316-ELV Projects Pvt Ltd14/11/2022
CMP/221114/0010317-ELV Projects Pvt Ltd14/11/2022
CMP/221114/0010318-ELV Projects Pvt Ltd14/11/2022
CMP/221114/0010319-ELV Projects Pvt Ltd14/11/2022
CMP/221114/0010320-ELV Projects Pvt Ltd14/11/2022
CMP/221114/0010321-ELV Projects Pvt Ltd14/11/2022
CMP/221114/0010322-ELV Projects Pvt Ltd14/11/2022
CMP/221114/0010323-ELV Projects Pvt Ltd14/11/2022
CMP/221114/0010324-ELV Projects Pvt Ltd14/11/2022
CMP/221125/0010398-ELV Projects Pvt Ltd25/11/2022
CMP/221125/0010399-ELV Projects Pvt Ltd25/11/2022
00253/2023-ELV Projects Pvt Ltd27/02/2023
00259/2023-ELV Projects Pvt Ltd27/02/2023
00260/2023-ELV Projects Pvt Ltd27/02/2023
00261/2023-ELV Projects Pvt Ltd27/02/2023
00262/2023-ELV Projects Pvt Ltd27/02/2023
00263/2023-ELV Projects Pvt Ltd27/02/2023
00320/2023-ELV Projects Pvt Ltd13/03/2023
00321/2023-ELV Projects Pvt Ltd13/03/2023
00357/2023-ELV Projects Pvt Ltd23/03/2023
00358/2023-ELV Projects Pvt Ltd23/03/2023
00429/2023-ELV Projects Pvt Ltd03/04/2023
00430/2023-ELV Projects Pvt Ltd03/04/2023
00673/2023-ELV Projects Pvt Ltd05/05/2023
00080/2024-ELV Projects Pvt Ltd18/01/2024
00081/2024-ELV Projects Pvt Ltd18/01/2024
00082/2024-ELV Projects Pvt Ltd18/01/2024
00083/2024-ELV Projects Pvt Ltd18/01/2024
00096/2024-ELV Projects Pvt Ltd20/01/2024
00097/2024-ELV Projects Pvt Ltd20/01/2024
00212/2024-ELV Projects Pvt Ltd21/02/2024
00347/2025-ELV Projects Pvt Ltd28/02/2025
00387/2025-ELV Projects Pvt Ltd06/03/2025
00673/2025-ELV Projects Pvt Ltd26/04/2025
00674/2025-ELV Projects Pvt Ltd26/04/2025
00675/2025-ELV Projects Pvt Ltd26/04/2025
00709/2025-ELV Projects Pvt Ltd05/05/2025

Documents filed22

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/181122/002144 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: 00009-Certificate of Incorporation 171.pdf-
Project Details-
Architect Certificate for Work Completion Schedule till DateFile: Architect_Work Completed.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer_Work Completed.pdf-
CA Certificate for Funds UtilizationFile: CA_Utilization.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Architect_Pending Work.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer_Pending Work.pdf-
CA Certificate for Funds required for Project CompletionFile: CA_Fund Requirement.pdf-
AffidavitFile: FORM-EX 7.pdf-
Latest Encumbrance CertificateFile: EC.jpeg-
Details Of Sold/ Un-sold UnitsFile: Sold Unsold units.xlsx-
NOC DetailsFile: NOC_BESCOM.pdf-
Document 1File: FORM-EX 7.pdf-
Document 2File: FORM-B.pdf-
Document 3File: RERA Extension_Application.pdf-
Plan-ELV-
EC Kings-
JD ELV-
Conversion-ELV-
Prospectus/Brochure-
Advertisement Copy 1File: KINGSLAND ADVT COPY.pdf-
Tower Excel SheetFile: RERA FLATS ANNEXURE.xlsx-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 32 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep ELV Kingsland on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: ELV Projects Pvt Ltd

ELV Projects Pvt Ltd has 1 registration on RERA Karnataka, including ELV Kingsland. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if ELV Kingsland is delayed beyond 30 Aug 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ELV Kingsland?

The registered promoter entity is ELV Projects Pvt Ltd, a company as per the filing. Its CIN U45203KA2015PTC084790 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ELV Kingsland?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ELV Kingsland?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

What should I check before booking in ELV Kingsland?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ELV Kingsland. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ELV Kingsland to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.