Home / Browse projects / Bengaluru Urban, Karnataka / ELEGANT EXOTICA
ELEGANT EXOTICA
By Elegant Builders and Developers
RG-KA-43933 · RERA PRM/KA/RERA/1251/309/PR/190301/002457
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 12 months
- 2 extensions taken
Clear
- No complaints on record
- Separate project account declared
Saved.
ELEGANT EXOTICA is a Residential/Group Housing project by Elegant Builders and Developers in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/190301/002457 on 1 Mar 2019. Possession is promised by 31 Mar 2021. The completion date has moved by 12 months from the original filing.
At a glance
Project
- NameELEGANT EXOTICA
- TypeResidential/Group Housing
- Location
- Bengaluru North
- Bengaluru Urban
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/309/PR/190301/002457
- ReraGenie IDRG-KA-43933
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on1 Mar 2019
- Promised completion31 Mar 2021
- Revised completionRevised to 31 Mar 2021 (originally 31 Mar 2020)
- Buildings1 building record
- Documents filed86 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| ELEGANT EXOTICA | - | - | - | 87 | 0 | 87 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Painting | - |
| Elevation work | Not applicable |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation | No | Not applicable |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Reason as filed by the promoterShortage of Labour
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed86
As listed on the registration, under the names the promoter filed them with; the newest 80 of 86 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/190301/002457 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: Deed of partnership_1.pdf | - |
| Architect Certificate for Work Completion Schedule till DateFile: PE Work Done Arct.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: RK MAKHIJA ENG VALUATION.pdf | - |
| CA Certificate for Funds UtilizationFile: CA fund utilization certificate P E.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: PE RERA Arct Pending work.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: PE ENG RK PENDING WORK.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: CA PE FUNDS REQUIRED.pdf | - |
| AffidavitFile: PE Affidavit.pdf | - |
| Latest Encumbrance CertificateFile: Exotica EC 1989-2020_4.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx | - |
| Document 1File: clarification on the project elegant exotica_1.pdf | - |
| Document 2File: Form B affidavit cum declaration.pdf | - |
| Document 3File: Templet no. 6_1.pdf | - |
| Document 4File: Statement of Accounts sbi.pdf | - |
| Document 5File: KVB Account Statement August 19.pdf | - |
| CC | - |
| INSIGHTS NA | - |
| plan Combined | - |
| ELEGANT EXOTICA SALE DEED DRAFT | - |
| ELEGANT EXOTICA SALE AGREEMENT DRAFT | - |
| Absolute Sale Deed | - |
| section-ilovepdf-compressed | - |
| INSIGHTS NA | - |
| INSIGHTS NA | - |
| Exotica-Brochure (1) | - |
| specifications (1) | - |
| EC | - |
| katha | - |
| INSIGHTS NA | - |
| INSIGHTS NA | - |
| INSIGHTS NA | - |
| INSIGHTS NA | - |
| INSIGHTS NA | - |
| INSIGHTS NA | - |
| INSIGHTS NA | - |
| FIRE NOC | - |
| Airport NOC | - |
| BESCOM NOC | - |
| BWSSB NOC | - |
| Pollution CB NOC-ilovepdf-compressed | - |
| INSIGHTS NA | - |
| BSNL NOC | - |
| INSIGHTS NA | - |
| Unnamed document | - |
| INSIGHTS NA | - |
| INSIGHTS NA | - |
| INSIGHTS NA | - |
| INSIGHTS NA | - |
| INSIGHTS NA | - |
| INSIGHTS NA | - |
| section | - |
| INSIGHTS NA | - |
| INSIGHTS NA | - |
| INSIGHTS NA | - |
| INSIGHTS NA | - |
| Balance Sheet 2016 - 2017File: balance sheet 2017.pdf | - |
| Balance Sheet 2015 - 2016File: balance sheet 2016.pdf | - |
| Balance Sheet 2014 - 2015File: balance sheet 2015.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: P&L 2017.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: P&L 2016.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: P&L 2015.pdf | - |
| Director's Report 2016 - 2017File: INSIGHTS NA.jpg | - |
| Director's Report 2015 - 2016File: INSIGHTS NA.jpg | - |
| Director's Report 2014 - 2015File: INSIGHTS NA.jpg | - |
| Cash Flow Statement 2016 - 2017File: INSIGHTS NA.jpg | - |
| Cash Flow Statement 2015 - 2016File: INSIGHTS NA.jpg | - |
| Auditor's Report 2016 - 2017File: INSIGHTS NA.jpg | - |
| Auditor's Report 2015 - 2016File: INSIGHTS NA.jpg | - |
| Auditor's Report 2014 - 2015File: INSIGHTS NA.jpg | - |
| Income Tax Return Acknowledgement 2016 - 2017File: IT returns acknowledgement 2017.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: IT returns acknowledgement 2016.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: IT returns acknowledgement 2015.pdf | - |
| Form B | - |
| Prospectus/BrochureFile: RERA Exotica Brochure.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1251_309_PR_190301_002457.xlsx | - |
| Stability CertificateFile: Archtect - Certificate - Oct 2020 - Dec 2020.pdf | - |
| Road cutting permission letter issued by the planning Authority for laying Water supply line, sanitary line, UFile: exotica road cutting.pdf | - |
| NOC issued by the Fire Force department after completion of workFile: BESCOM.pdf | - |
| Occupancy CertificateFile: Archtect - Certificate - Oct 2020 - Dec 2020.pdf | - |
| Consent for operation issued by KSPCBFile: KSPC.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep ELEGANT EXOTICA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 27 registered projects within 2 km.
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: Elegant Builders and Developers
ELEGANT BUILDERS AND DEVELOPERS has 8 registrations on RERA Karnataka, including ELEGANT AURA and ELEGANT EXOTICA. Its filings declare 7 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if ELEGANT EXOTICA is delayed beyond 31 Mar 2021?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of ELEGANT EXOTICA?
The registered promoter entity is Elegant Builders and Developers, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in ELEGANT EXOTICA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
What should I check before booking in ELEGANT EXOTICA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.