Registration approved Mixed Development project

Eden at Brigade Cornerstone Utopia

By Mysore Projects Private Limited

RG-KA-08357 · RERA PRM/KA/RERA/1251/446/PR/181219/002236

Source: official RERA Karnataka filing

Red flags

  • 4 complaints at RERA Karnataka
  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • Separate project account declared
Mar 2024Possession promisedmoved 9 months from the original
4Complaints at RERA Karnatakaon this registration
Jump to the 57 documents Report an error

Eden at Brigade Cornerstone Utopia is a Mixed Development project by Mysore Projects Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/181219/002236 on 19 Dec 2018. Possession is promised by 30 Mar 2024. The completion date has moved by 9 months from the original filing. 4 complaints are on record with the regulator.

At a glance

Project

  • NameEden at Brigade Cornerstone Utopia
  • TypeMixed Development
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/181219/002236
  • ReraGenie IDRG-KA-08357

Builder

  • NameMysore Projects Private Limited
  • Entity typeCompany
  • CINU70102KA2010PTC054771
  • Authorized SignatoryViswa Prathap Desu
  • Other registrations6 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredDec 2018First promiseJun 2023Revised toMar 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on19 Dec 2018
  • Promised completion30 Mar 2024
  • Revised completionRevised to 30 Mar 2024 (originally 30 Jun 2023)
  • Buildings5 building records
  • Documents filed57 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---2730273
B-----67
C---2150215
D-----87
E---2260226

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etcNot applicable
Plastering inside , outside & CeilingNot applicable
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallNoNot applicable
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area28,112 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 280.00 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJun 2023 → Mar 2024

No reason recorded in the filing

Complaints filed with RERA Karnataka4

Case no.ComplainantRespondentFiled
CMP/220420/0009372-Mysore Projects Private Limited20/04/2022
00413/2023-Mysore Projects Private Limited01/04/2023
00433/2023-Mysore Projects Private Limited03/04/2023
00453/2024-Mysore Projects Private Limited23/05/2024

Documents filed57

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/181219/002236 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: MPPL Certificate of Incorporation.pdf-
Plan Sanction Ltr compressed-
Site Plan Eden-
Site Plan Blown Plan and Development Plan Eden-
Awaiting Sale Deed Draft-
Agreement to Sell -Eden-
Consolidated Sale Deed & RTC (1)-
Utopia_Eden Site Plan_1-
Blown Up Plan Eden-
Pro forma Eden at Brigade Cornerstone Utopia-
Eden At Brigade Cornerstone Utopia_RERA Brochure_16Oct18-
Eden Schedule H-
Consolidated EC-
Khata Certificate & Extract-
GPA & JDA-
Consolidated Conversion Order-
AAI NOC-
BSNL NOC-
Utopia_Eden Site Plan_1-
Eden Section Elevation and specification-compressed-
Balance Sheet 2017 - 2018File: Balance Sheet - 31-03-2017.pdf-
Balance Sheet 2016 - 2017File: Balance Sheet - 31-03-2016.pdf-
Balance Sheet 2015 - 2016File: Balance Sheet - 31-03-2015.pdf-
Audited Profit and Loss Statement 2017 - 2018File: P&L Account - 31-03-2017.pdf-
Audited Profit and Loss Statement 2016 - 2017File: P&L Account - 31-03-2016.pdf-
Audited Profit and Loss Statement 2015 - 2016File: P&L Account - 31-03-2015.pdf-
Director's Report 2017 - 2018File: Board's Report - 31-03-2017.pdf-
Director's Report 2016 - 2017File: Board's Report - 31-03-2016.pdf-
Director's Report 2015 - 2016File: Board's Report - 31-03-2015.pdf-
Cash Flow Statement 2017 - 2018File: Cash Flow Statement - 31-03-2017.pdf-
Cash Flow Statement 2016 - 2017File: Cash Flow Statement - 31-03-2015 and 2016.pdf-
Auditor's Report 2017 - 2018File: Auditors Report - 31-03-2017.pdf-
Auditor's Report 2016 - 2017File: Auditors Report - 31-03-2016.pdf-
Auditor's Report 2015 - 2016File: Auditors Report - 31-03-2015.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: ITR 2017.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: ITR 2016.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR 2015.pdf-
Form B (Eden)-
Prospectus/BrochureFile: Brigade Cornerstone Utopia - Eden Unit Plan.pdf-
Advertisement Copy 1File: Marketing - No Ad.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_446_PR_181219_002236.xlsx-
Stability CertificateFile: Strl Stability Certificate - Eden.pdf-
Road cutting permission letter issued by the planning Authority for laying Water supply line, sanitary line, UFile: ROAD CUTTING PERMISSION.pdf-
NOC issued by the Fire Force department after completion of workFile: Eden - Fire CC.pdf-
Occupancy CertificateFile: Brigade Cornerstone Utopia - Eden - Occupancy Certificate.pdf-
Consent for operation issued by KSPCBFile: CFO - Eden.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: Lift Approval - Eden.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: Eden - Power Sanction Letter1.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: Permanent Water Connection Payment Receipt - Eden.pdf-
Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: Details of Infrastructure Works.pdf-
Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: Aminities Details.pdf-
Details of undivided share of land handed over to the association of allotteesFile: Eden - DOD & AOP.pdf-
Architect certificate for having completed the work(in format no 5)File: Eden - Form 5 - Completion Certificate.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: Eden - Form 4 - Completion Certificate.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Eden - Affidavit Cum Declaration.pdf-
Handover Details 1File: Eden - Hand Over Details 1.pdf-
Handover Details 2File: Eden - Hand Over Details 2.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Eden at Brigade Cornerstone Utopia on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmEden at Brigade CornerstOther 37Dot size: filed unitsN

Filed coordinates, straight-line distance. 37 registered projects within 2 km.

Builder: Mysore Projects Private Limited

Mysore Projects Private Limited has 7 registrations on RERA Karnataka, including Elysium at Brigade Cornerstone Utopia and Serene at Brigade Cornerstone Utopia. Its filings declare 4 earlier projects, none of them declared completed. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Eden at Brigade Cornerstone Utopia is delayed beyond 30 Mar 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Eden at Brigade Cornerstone Utopia?

The registered promoter entity is Mysore Projects Private Limited, a company as per the filing. Its CIN U70102KA2010PTC054771 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Eden at Brigade Cornerstone Utopia?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Eden at Brigade Cornerstone Utopia?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

What should I check before booking in Eden at Brigade Cornerstone Utopia?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Eden at Brigade Cornerstone Utopia. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Eden at Brigade Cornerstone Utopia to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.