ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / E Golden Heights

Registration approved No litigation declared Residential/Group Housing project

E Golden Heights

By SHREE KRISHNA BUILDERS AND DEVELOPERS

RG-KA-08997 · RERA PRM/KA/RERA/1251/310/PR/210524/006913

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Jump to the 29 documents Report an error

E Golden Heights is a Residential/Group Housing project by SHREE KRISHNA BUILDERS AND DEVELOPERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/210524/006913 on 21 May 2024. Possession is promised by 25 Jun 2025.

At a glance

Project

  • NameE Golden Heights
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/310/PR/210524/006913
  • ReraGenie IDRG-KA-08997

Builder

  • NameSHREE KRISHNA BUILDERS AND DEVELOPERS
  • Entity typeProprietorship
  • GSTIN29AJJPB8379F1ZU
  • Authorized SignatoryEshwara Reddy B K

Key dates

this monthRegisteredMay 2024PromisedJun 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on21 May 2024
  • Promised completion25 Jun 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed29 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER 1---48048

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes-
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingNoNot applicable
Street LightingYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners1
LandownerVillageDistrict
G Ramareddy--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 10.85 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 10.85 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectT N S Chankravarthi
EngineerDakka Gurappa
Chartered AccountantBhaskar Reddy V

Documents filed29

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/210524/006913 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
RTC, survey 48/7-
Mutation, survey 48/7-
Encumbrance Certificate, survey 48/7-
Conversion/Alienation Order, survey 48/7-
Sale/Title/Gift Deed, survey 48/7-
JDA, survey 48/7-
Khatha, survey 48/7-
Registration CertificateFile: GST Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
Income Tax Return Acknowledgement 2020 - 2021File: IT 2021-22.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: IT 2020-21.pdf-
Work Order-
BESCOM Fees Receipt-
Water NOC-
Ground Floor to Terrece-
Site Plan-
Legal Opinion-
Jiont Development Agreement-
Water NOC-
KSPCB-
CDP Map-
Aakharband-
Genaral Power Of Attorney-
Hiss Phody-
Sketh-
Village Map-
House Constraction Permit-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep E Golden Heights on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: SHREE KRISHNA BUILDERS AND DEVELOPERS

SHREE KRISHNA BUILDERS AND DEVELOPERS has 1 registration on RERA Karnataka, including E Golden Heights. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if E Golden Heights is delayed beyond 25 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of E Golden Heights?

The registered promoter entity is SHREE KRISHNA BUILDERS AND DEVELOPERS, a proprietorship as per the filing. Its GSTIN 29AJJPB8379F1ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in E Golden Heights?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at E Golden Heights?

The professionals named in the filing: Architect: T N S Chankravarthi; Engineer: Dakka Gurappa; Chartered Accountant: Bhaskar Reddy V. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in E Golden Heights?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About E Golden Heights. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save E Golden Heights to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.