Home / Browse projects / Bengaluru Urban, Karnataka / DS MAX Silver Oak

Registration approved Residential/Group Housing project

DS MAX Silver Oak

By Ds Max Properties Private Limited

RG-KA-92665 · RERA PRM/KA/RERA/1251/308/PR/180516/001704

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2018Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 48 documents Report an error

DS MAX Silver Oak is a Residential/Group Housing project by Ds Max Properties Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/180516/001704 on 16 May 2018. Possession is promised by 11 Dec 2018.

At a glance

Project

  • NameDS MAX Silver Oak
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/180516/001704
  • ReraGenie IDRG-KA-92665

Builder

  • NameDs Max Properties Private Limited
  • Entity typeCompany
  • CINU70102KA2007PTC041508
  • Authorized SignatoryK V SATISH
  • Other registrations38 more →
  • Declared earlier projects31 →

Key dates

this monthRegisteredMay 2018PromisedDec 2018

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on16 May 2018
  • Promised completion11 Dec 2018
  • Revised completionNone
  • Buildings1 building record
  • Documents filed48 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DSMAX SILVEROAK---1120112

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)Not applicable
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities45

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityYes-
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionYes-
vetrified flooringYes-
Boundary PlantationYes-
Lift FacilityYes-
charging Point for electric vehicalNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallNoNot applicable
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,149 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 17.28 cr

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed48

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/180516/001704 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Certificate of Incorporation.pdf-
commancement copy-
Silveroak plan-
Silveroak plan-
SILVER OAK SALE DEED DRAFT-
SILVER OAK SALE CUM CONSTRUCTION AGREEMENT DRAFT - Copy-
RTC-
Silver Oak Project Plan-
Silveroak plan-
ALLOTMENT LETTER-
silveroak-brochure-
Silver OakProject Specifiation-
EC FROM-26-10-2015 TO 03-10-2016--
E-KATHA & TAX PAID-14-15-
JDA_SILVER OAK-
Silver Oak Partition Deed-
BESCOM - NOC - Siver Oak-
KPCB NOC-
Silver Oak Project Plan-
Silver Oak Project Plan-
CONVERSION ORDER-
Silver Oak Partition Deed-
Balance Sheet 2016 - 2017File: DSMPPL Scanned Financials FY 2015-16 BS pl cf itr.pdf-
Balance Sheet 2015 - 2016File: Balance sheet 2014-15-BS PL CF.pdf-
Balance Sheet 2014 - 2015File: DS Max Properties Pvt Ltd - 2013-2014-BS PL CF ITR.pdf-
Audited Profit and Loss Statement 2016 - 2017File: DSMPPL Scanned Financials FY 2015-16 BS pl cf itr.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Balance sheet 2014-15-BS PL CF.pdf-
Audited Profit and Loss Statement 2014 - 2015File: DS Max Properties Pvt Ltd - 2013-2014-BS PL CF ITR.pdf-
Director's Report 2016 - 2017File: BOARD REPORT 15-16.pdf-
Director's Report 2015 - 2016File: Directors report Balance sheet- 14-15.pdf-
Director's Report 2014 - 2015File: Director's Report-13-14.pdf-
Cash Flow Statement 2016 - 2017File: DSMPPL Scanned Financials FY 2015-16 BS pl cf itr.pdf-
Cash Flow Statement 2015 - 2016File: Balance sheet 2014-15-BS PL CF.pdf-
Auditor's Report 2016 - 2017File: PROPERTIES Auditor's Report-2015-16.pdf-
Auditor's Report 2015 - 2016File: Auditors report - 2014-15-.pdf-
Auditor's Report 2014 - 2015File: Auditors Report-properties-13-14.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: DSMPPL Scanned Financials FY 2015-16 BS pl cf itr.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: DSMAXPPL ITR scanned FY 2014-15.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: DS Max Properties Pvt Ltd - 2013-2014-BS PL CF ITR.pdf-
declaration-supported-by-an-affidavit-which-shall-be-signed-by-the-promoter-or-any-person--
Prospectus/BrochureFile: silveroak-brochure.pdf-
Advertisement Copy 1File: Advertisment Copy.jpg-
Tower Excel SheetFile: PRM_KA_RERA_1251_308_PR_180516_001704.xlsx-
Loan raised documentFile: loanDetails.xlsx-
Occupancy CertificateFile: OC-Silveroak.pdf-
Consent for operation issued by KSPCBFile: SILVER OAK CFO.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: BESCOM.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Silveroak_0001.pdf-

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

5 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
DSMax Sheldons-Completed-No date filed
DS-Max Stonehill-Completed-No date filed
DS-Max Sterling-Completed-No date filed
DS-Max Sherwood-Completed-No date filed
DS-Max Sandalwood-Completed-No date filed

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep DS MAX Silver Oak on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmDS MAX Silver OakOther 17Dot size: filed unitsN

Filed coordinates, straight-line distance. 17 registered projects within 2 km.

Builder: Ds Max Properties Private Limited

DS Max Properties Private Limited has 39 registrations on RERA Karnataka, including DS MAX SKY SISIRA and DS MAX SKY SAMURAI. Its filings declare 31 earlier projects, 18 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if DS MAX Silver Oak is delayed beyond 11 Dec 2018?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of DS MAX Silver Oak?

The registered promoter entity is Ds Max Properties Private Limited, a company as per the filing. Its CIN U70102KA2007PTC041508 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in DS MAX Silver Oak?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in DS MAX Silver Oak?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DS MAX Silver Oak. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DS MAX Silver Oak to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.