Registration approved No litigation declared Residential/Group Housing project

DNR HIGHLINE

By DNR CORPORATION PRIVATE LIMITED

RG-KA-73883 · RERA PRM/KA/RERA/1251/309/PR/220118/004647 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Oct 2027Possession promisedmoved 12 months from the original
4 of 17Construction stages donefurthest along: Sub-structure flooring (Parking Floor, 99%
49 of 218Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 189 documents Report an error

DNR HIGHLINE is a Residential/Group Housing project by DNR CORPORATION PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/220118/004647 on 18 Jan 2022. Possession is promised by 1 Oct 2027. The completion date has moved by 12 months from the original filing. 169 of the 218 units on this registration are recorded sold or booked, and 4 of 17 construction stages are filed complete.

At a glance

Project

  • NameDNR HIGHLINE
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/220118/004647
  • ReraGenie IDRG-KA-73883

Builder

  • NameDNR CORPORATION PRIVATE LIMITED
  • Entity typeCompany
  • Authorized SignatoryVIPUL KUMAT
  • Board MemberRITESH KUMAT
  • Other registrations2 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredJan 2022First promiseOct 2026Revised toOct 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on18 Jan 2022
  • Promised completion1 Oct 2027
  • Revised completionRevised to 1 Oct 2027 (originally 1 Oct 2026)
  • Buildings2 building records
  • Documents filed189 files

Current status

78%169 of 218 units booked
2.0%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---90090
B---1280128

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 17 construction stages are filed complete. The stage furthest along is Sub-structure flooring (Parking Floor, at 99%.

Building: 90% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)99%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc99%
Plastering inside , outside & Ceiling99%
Joinery: Doors, Windows, Ventilators etc90%
Basic work of Water supply, Sanitary and Electrification90%
Dadoing, Skirting, Flooring, Tiles work (All types)95%
Railing and Grill fixing70%
Electrification, Water supply and Sanitary Finishing85%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network85%
Weather Proof work(tile,concrete)95%
Painting85%
Elevation work85%
Internal and External work including landscapes as per santioned drawings60%

Progress on shared amenities41

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes80%
Internal Roads & FootpathsYes0%
Sewage and Drainage SystemYes80%
Parks & Tree plantingYes0%
Street LightingYes0%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes85%
Solid waste management and disposalYes30%
Water conservationYes20%
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes0%
Electricity supply transformer and substationYes0%
Emergency Evacuation servicesYes0%
Storm water drainsYes50%
Use of renewable energyYes0%
Water conservation/rain water harvesting/recharge of ground waterYes60%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes50%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes50%
GymYes0%
ParksYes0%
Power BackupYes0%
GasNoNot applicable
Water and SanitationYes0%
Air Conditioning And incerntionNoNot applicable
StaircasesYes92%
LiftsYes90%
Staircases and Lift lobbies, corridor,lobbies, corridorYes90%
Fire escapesYes90%
Common entrance and exit for the building / common portico/foyer/verandahYes50%
BasementYes90%
TerraceYes95%
Outer WallYes30%
Open parking areas and common storage spacesYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,262 sq m
Named landowners2
LandownerVillageDistrict
ANUSHKA CONSTRUCTIONS PRIVATE LIMITED--
DAVANAM CONSTRUCTIONS PRIVATE LIMITED--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 252.16 cr
Cost incurredRs 4.98 cr
Spent of the estimate1.98%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 132.19 crRs 3.52 cr
On-site expenditure-Consultants FeesRs 44.11 crRs 7.72 lakh
Payment of taxesRs 33.40 crRs 67.24 lakh
Principal sum and interest payable to financial institutions-Scheduled BanksRs 33.21 crRs 57.65 lakh
On-site expenditure-Site OverheadRs 6.00 crRs 7.35 lakh
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 3.25 crRs 6.83 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectURBAN FRAME PRIVATE LIMITED
EngineerPRASAD CONSULTANTS

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/309/PR/261006/004647Oct 2026 → Oct 2027

Reason as filed by the promoterForce Majeure

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed189

As listed on the registration, under the names the promoter filed them with; the newest 80 of 189 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/220118/004647 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4, Q2 Uploaded.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: FORM -5 ARCHITECT CERTIFICATE.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM - 6 ENGINEER CERTIFICATE.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
BUILDING LICENCEFile: Building Licence 2025.pdf28 Sep 2026
PLANFile: PLAN.pdf28 Sep 2026
EX-5 ENGINEER LICENCEFile: Ex5 ENGINEER CERTIFICATE.pdf28 Sep 2026
EX-6 ENGINEER LICENCEFile: Ex6 ENGINEER CERTIFICATE.pdf28 Sep 2026
KSPCB ACKFile: KSPCB Ack.pdf28 Sep 2026
SOLD AND UNSOLDFile: SOLD AND UNSOLD.pdf28 Sep 2026
AFFIDAVIT FOR NOCFile: Affidavit.pdf28 Sep 2026
CIVIL ENGINEER LICENCEFile: CIVIL ENGINEER LICENCE.pdf28 Sep 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4, CA (QU) - Highline_compressed.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: FORM 5 ARCHITECT CERTIFICATE HIGHLINE.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM 6 ENGINEER CERTIFICATE HIGHLINE.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department15 Jul 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA QU Highline.pdf15 Apr 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 - Architect certificate.pdf15 Apr 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form - 6 Engineer Certificate.pdf15 Apr 2026
Q3 2025-26 Water supply and sewage board15 Apr 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q3 2025-26 KPTCL- BESCOM15 Apr 2026
Q3 2025-26 Fire and Safety15 Apr 2026
Q3 2025-26 Airport Authority of India15 Apr 2026
Q3 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CHARTED ACCOUNTANT CERTIFICATE FORM 4_compressed.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: ARCHITECT CERTIFICATE FORM 5.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: ENGINEER CERTIFICATE FORM 6.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
AGREEMENT OF SALE INCORPORATION SCHEDULE C PAYMENT PLANFile: AOS Oakalipuram RERA.pdf14 Jan 2022
BWSSB NOCFile: BWSSB NOC.pdf12 Jan 2022
AGREEMENT OF SALE DRAFT AS PER GOK PROVISIONSFile: AOS_Oakalipuram_RERA.pdf23 Dec 2021
BWSSB-NOC-ACKNOWLEDGEMENTFile: BWSSB-NOC-ACKNOWLEDGEMENT.jpeg23 Dec 2021
REVENUE RELATED CLAUSE IS HIGHLIGHTED IN JDA CLAUSE NO 7File: REPLY FOR THE QUERY WITH regard to revenue sharing.pdf23 Dec 2021
ECFile: EC-01-04-2005 TO 03-10-2021.pdf6 Dec 2021
AOS DRAFT AS PER NOTIFIED GOKFile: AOS_Oakalipuram_RERA.pdf29 Nov 2021
SALE DEED DRAFT AS PER NOTIFIED GOKFile: PROFORMA OF SALE DEED.pdf29 Nov 2021
STATUS OF THE PROJECTS OF DEVELOPER AND THEIR TRACK RECORDFile: TRACK RECORD OF DEVELOPER PROJECTS.pdf29 Nov 2021
TITLE OPINIONFile: TITLE OPINION-OKALIPURAM.pdf29 Nov 2021
DEED OF DISCHARGE FROM UNION BANKFile: Deed of Discharge-union bank.pdf29 Nov 2021
RELEASE LETTER FROM UNION BANKFile: release letter-UNION BANK TO DAVANAM JWELLERS.pdf29 Nov 2021
BSNL NOCFile: NOC-BSNL.pdf27 Oct 2021
BWSSB NOCFile: NOC-BWSSB.pdf27 Oct 2021
SITE PLANFile: Site Plan.pdf21 Oct 2021
GROUND FLOOR PLANFile: Ground Floor Plan.pdf21 Oct 2021
Elevation Section PlanFile: Elevation Section Plan.pdf21 Oct 2021
1ST BASEMENT FLOOR PLANFile: 1st Basement Floor Plan.pdf21 Oct 2021
2ND BASEMENT FLOOR PLANFile: 2nd Basement Floor Plan.pdf21 Oct 2021
3RD BASEMENT FLOOR PLANFile: 3rd Basement Floor Plan.pdf21 Oct 2021
1st to 17th Floor PlanFile: 1st to 17th Floor Plan.pdf21 Oct 2021
18th 19th & 21st Floor PlanFile: 18th 19th & 21st Floor Plan.pdf21 Oct 2021
20th 23rd & 24th Floor PlanFile: 20th 23rd & 24th Floor Plan.pdf21 Oct 2021
24th & 25th Floor PlanFile: 24th & 25th Floor Plan.pdf21 Oct 2021
26th & 27th Floor PlanFile: 26th & 27th Floor Plan.pdf21 Oct 2021
28th & Terrace Floor PlanFile: 28th & Terrace Floor Plan.pdf21 Oct 2021
RENEWED KSPCB NOCFile: KSPCB-2021.pdf21 Oct 2021
BWSSB -APPLIED ONLINE APPLICATION ACKNOWLEDGMENTFile: BWSSB-APPLICATION SUBMISSION.pdf21 Oct 2021
CANCELLATION JDA WITH PACIFIC HEIGHTS BY DAVANAMFile: DEED OF CANCELLATION-JDA.pdf21 Oct 2021
REVOCATION OF POWER OF ATTORNEY WITH PACIFIC HEIGHTS BY DAVANAMFile: DEED OF REVOCATION-1.pdf21 Oct 2021
Break up development details with type of flat/houseFile: DNR Highline_Unit Details-breakup devlopment details.pdf21 Oct 2021
ENCUMBRANCE CERTIFICATE FROM 01-04-2005 TO 03-10-2021File: EC-01-04-2005 TO 03-10-2021.pdf5 Oct 2021
BUILDING LICENSE WITH CONDITIONSFile: SANCTION & LICENCE & Condition for Highline Project.pdf5 Oct 2021
STP DETAILSFile: STP details-DNR HIGHLINE.pdf5 Oct 2021
STP LOCATION CAPACITY WITH SECTION DETAILSFile: DNR HIGHLINE_STP LOCATION CAPACITY WITH SECTION DETAILS.PDF5 Oct 2021
PROJECT SPECIFICATION WITH AUTHORISED SIGNEDFile: PROJECT SPECIFICATION-AUTHORISED SIGNED.pdf5 Oct 2021

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 not delivered by the promised date2 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
DNR SPRINGLEAF-OngoingSep 2023Not delivered
DNR CASABLANCA-OngoingJun 2022Not delivered
DNR REFLECTION-Completed-No date filed
DNR ATMOSPHERE-Completed-No date filed

How this compares with Bengaluru Urban

78%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep DNR HIGHLINE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmDNR HIGHLINEOther 13Dot size: filed unitsN

Filed coordinates, straight-line distance. 13 registered projects within 2 km.

Builder: DNR CORPORATION PRIVATE LIMITED

DNR Corporation Private Limited has 3 registrations on RERA Karnataka, including DNR SOLACE and DNR HIGHLINE. Its filings declare 4 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if DNR HIGHLINE is delayed beyond 1 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of DNR HIGHLINE?

The registered promoter entity is DNR CORPORATION PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in DNR HIGHLINE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at DNR HIGHLINE?

The professionals named in the filing: Architect: URBAN FRAME PRIVATE LIMITED; Engineer: PRASAD CONSULTANTS. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DNR HIGHLINE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DNR HIGHLINE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DNR HIGHLINE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.