Home / Browse projects / Bengaluru Urban, Karnataka / DNR Arista Phase 2

Registration approved No litigation declared Residential/Group Housing project

DNR Arista Phase 2

By INESA VENTURES LLP

RG-KA-35567 · RERA PRM/KA/RERA/1251/446/PR/240306/006662 · Last updated on RERA Karnataka portal: 28 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 7 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Jul 2026Possession promisedmoved 7 months from the original
8 of 18Construction stages donefurthest along: Weather Proof work(tile, 90%
54 of 168Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 171 documents Report an error

DNR Arista Phase 2 is a Residential/Group Housing project by INESA VENTURES LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/240306/006662 on 6 Mar 2024. Possession is promised by 15 Jul 2026. The completion date has moved by 7 months from the original filing. 114 of the 168 units on this registration are recorded sold or booked, and 8 of 18 construction stages are filed complete.

At a glance

Project

  • NameDNR Arista Phase 2
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/240306/006662
  • ReraGenie IDRG-KA-35567

Builder

  • NameINESA VENTURES LLP
  • Entity typePartnership Firm
  • Authorized SignatoryBN Venugopal
  • OthersVenugopal B N
  • Other registrations1 more →

Key dates

this monthRegisteredMar 2024First promiseDec 2025Revised toJul 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on6 Mar 2024
  • Promised completion15 Jul 2026
  • Revised completionRevised to 15 Jul 2026 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed171 files

Current status

68%114 of 168 units booked
10.8%Of the estimated cost spent so far

Figures as on 28 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 3---1680168

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 28 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 18 construction stages are filed complete. The stage furthest along is Weather Proof work(tile, at 90%.

Building: 89% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc80%
Basic work of Water supply, Sanitary and Electrification80%
Dadoing, Skirting, Flooring, Tiles work (All types)86%
Railing and Grill fixing87%
Electrification, Water supply and Sanitary Finishing72%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network86%
Weather Proof work(tile,concrete)90%
Painting70%
Elevation work88%
Internal and External work including landscapes as per santioned drawings70%

Progress on shared amenities41

As on 28 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Internal Roads & FootpathsYes85%
Sewage and Drainage SystemYes100%
Parks & Tree plantingYes5%
Street LightingYes50%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservationNoNot applicable
Energy managementYes0%
Fire protection and fire safety requirementsYes100%
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationNoNot applicable
Emergency Evacuation servicesYes0%
Storm water drainsYes86%
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes100%
ElectricityYes95%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes100%
Community HallNoNot applicable
Outdoor Sports facilityYes15%
Indoor Sports facilityYes100%
Swimming PoolYes100%
GymYes100%
ParksYes15%
Power BackupYes25%
GasNoNot applicable
Water and SanitationYes100%
Air Conditioning And incerntionNoNot applicable
StaircasesYes92%
LiftsYes88%
Staircases and Lift lobbies, corridor,lobbies, corridorYes80%
Fire escapesYes86%
Common entrance and exit for the building / common portico/foyer/verandahYes85%
BasementYes88%
TerraceYes88%
Outer WallYes0%
Open parking areas and common storage spacesYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes100%

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area17,705 sq m
Named landowners1
LandownerVillageDistrict
Venugopal B N--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 104.00 cr
Cost incurredRs 11.27 cr
Spent of the estimate10.84%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 75.00 crRs 8.27 cr
Payment of taxesRs 14.50 crRs 1.87 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 8.00 cr-
On-site expenditure-Site OverheadRs 6.50 crRs 1.13 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVishal Pujar
EngineerDhruvaraj

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/446/PR/260120/006662Dec 2025 → Jul 2026

Reason as filed by the promoterShortage of Labour

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed171

As listed on the registration, under the names the promoter filed them with; the newest 80 of 171 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/240306/006662 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 - DNR Arista Phase 2 - Q1.pdf28 Oct 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: DNR Arista P2 - Architect Certificate - Q1.pdf28 Oct 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: DNR Arista P2 - Engineer Certificate - Q1.pdf28 Oct 2026
Q1 2026-27 Water supply and sewage board28 Oct 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)28 Oct 2026
Q1 2026-27 KPTCL- BESCOM28 Oct 2026
Q1 2026-27 Fire and Safety28 Oct 2026
Q1 2026-27 Airport Authority of India28 Oct 2026
Q1 2026-27 BSNL/Telecommunication Department28 Oct 2026
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 - DNR Arista Phase 2 - Q2.pdf28 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 - Architect Certificate - DNR P 2 - Q2.pdf28 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 - Engineer Certificate - DNR P2 - Q2.pdf28 Oct 2026
Q2 2026-27 Water supply and sewage board28 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)28 Oct 2026
Q2 2026-27 KPTCL- BESCOM28 Oct 2026
Q2 2026-27 Fire and Safety28 Oct 2026
Q2 2026-27 Airport Authority of India28 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department28 Oct 2026
KSPCB NOCFile: KSPCB - DNR Arista P2.pdf7 Aug 2026
Project brochureFile: Brochure - DNR Arista P2.pdf7 Aug 2026
Sold and unsold units detailsFile: Clarification- Sold and Unsold Units.pdf7 Aug 2026
Form 6 - Engineer CertificateFile: Form 6 - Engineer Certificate - DNR Arista P2.pdf7 Aug 2026
Stability CertificateFile: Structure Stability Certificate - DNR Arista P2.pdf7 Aug 2026
Notarised affidavit for modificationFile: Modification- Affidivit.pdf7 Aug 2026
Inventories details as per modified planFile: Clarification - Inventory.pdf7 Aug 2026
Clarification - NOC for increased load and for increasing in heightFile: Clarification- Increase In height.pdf7 Aug 2026
Updated ECFile: EC.pdf8 Jan 2026
Affidavit - Form Ex 7File: Form-Ex7.pdf8 Jan 2026
Sold and Unsold unitsFile: Sold and Unsold Units.pdf8 Jan 2026
Clarification on BESCOM NOCFile: Clarification BESCOM NOC.pdf8 Jan 2026
Clarification on BWSSB NOCFile: Clarification BWSSB NOC.pdf8 Jan 2026
Clarification on SEIAA NOCFile: Clarification SEIAA NOC.pdf8 Jan 2026
Update24 Dec 2025
TerraceFile: Terrace.pdf29 Feb 2024
Site planFile: Site plan.pdf29 Feb 2024
sectionsFile: sections.pdf29 Feb 2024
level 7File: level 7.pdf29 Feb 2024
level 6File: level 6.pdf29 Feb 2024
level 2File: level 2.jpg29 Feb 2024
elevationFile: elevation.pdf29 Feb 2024
elevation 2File: elevation 2.pdf29 Feb 2024
BasementFile: Basement.pdf29 Feb 2024
Basement 2File: Basement 2.pdf29 Feb 2024
Balance sheet and Profit Loss 22_23File: Balance sheet and Profit Loss 22_23.pdf29 Feb 2024
Balance sheet and Profit loss 21_22File: Balance sheet and Profit loss 21_22.pdf29 Feb 2024
ABFL Loan Sanction letterFile: ABFL Loan Sanction letter.jpeg29 Feb 2024
floorFile: 13 floor.pdf29 Feb 2024
6 7 8 10 11 & 12File: 5 6 7 8 10 11 & 12.pdf29 Feb 2024
of 14 level 1File: 4 of 14 level 1.pdf29 Feb 2024
of 14 grd flrFile: 3 of 14 grd flr.pdf29 Feb 2024
RERA master collection accountFile: DNR Arista Phase 2 master collection account.pdf9 Feb 2024
RERA Designated accountFile: DNR Arista Phase 2 RERA designated account.pdf9 Feb 2024
RERA 30% accountFile: DNR Arista Pahse 2- 30% account.pdf9 Feb 2024
CA CertificateFile: CA_Certificate_-_DNR_Arista-Phase_2_registration (1).pdf9 Feb 2024
Loan Sanction LatterFile: ABFL Sanction Letter.pdf9 Feb 2024
Inesa venture Bank account statementFile: DNR Arista Bank Account statement.pdf9 Feb 2024
HOA Order full copyFile: HOA Order-Full copy.pdf9 Feb 2024
Section drawing with seal and signaturesFile: Section Drawings.pdf9 Feb 2024
Balance sheet Inesa Ventures 2022File: Financial as on March 2022.pdf9 Feb 2024
Profit and loss account March 2022File: P and L as on macrh 2022.pdf9 Feb 2024
Financial Statements March 2022File: Financial statement as on march 2022.pdf9 Feb 2024
Clarification Affidavit and declarationFile: Affidavit Declaration clarifications.pdf9 Feb 2024
Performa Agreement to saleFile: DNR Arista Phase 2-Agreement to Sale-Final Rera.pdf9 Feb 2024
STP PicsFile: STP Pics.pdf9 Feb 2024
BESCOM Sanction Certificate with payment detailsFile: BESCOM Sanction Certificate.pdf9 Feb 2024
Section planFile: BBMPRemdifiedlatest_ DWG-3 - Section Plan.pdf24 Nov 2023
Development Construction AgreementFile: Develoment Construction Agreement-Inesa.pdf24 Nov 2023
Agreement to SaleFile: DNR Arista Phase 2-Agreement to Sale-Final Rera - 19-11-23.pdf24 Nov 2023
KSPCB notificationFile: KSPCB Notification.pdf24 Nov 2023
Affidavit 3(1)File: Affidavit 3(1).pdf7 Jul 2023
Form BFile: Affidavit cum Declaration - Form B.pdf7 Jul 2023
DeclarationFile: Declaration.pdf7 Jul 2023
JD Affidavit cum DeclarationFile: JD Adffidavit cum Declaration.pdf7 Jul 2023
Non litigation AffidavitFile: Non litigation Affidavit.pdf7 Jul 2023
STP - Supporting Document - DrawingsFile: A-CO-1208_STP.pdf7 Jul 2023
BBMP Approval PlanFile: BBMPRemdifiedlatest_ DWG_compressed.pdf7 Jul 2023
Project SpecificationFile: Project Spec.pdf7 Jul 2023
Proforma of AOSFile: Proforma of AOS.pdf7 Jul 2023
JDA/MOUFile: JDA-MOU.pdf7 Jul 2023
Rs.176260/- ReceiptFile: RECEIPT.pdf8 Sep 2021

How this compares with Bengaluru Urban

68%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 7 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep DNR Arista Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: INESA VENTURES LLP

INESA VENTURES LLP has 2 registrations on RERA Karnataka, including DNR Arista Phase 2 and DNR Arista Phase 1. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if DNR Arista Phase 2 is delayed beyond 15 Jul 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of DNR Arista Phase 2?

The registered promoter entity is INESA VENTURES LLP, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in DNR Arista Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at DNR Arista Phase 2?

The professionals named in the filing: Architect: Vishal Pujar; Engineer: Dhruvaraj. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DNR Arista Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DNR Arista Phase 2. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DNR Arista Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.