Home / Browse projects / Bengaluru Urban, Karnataka / Dhiraan Northbrook

Registration approved Residential/Group Housing project

Dhiraan Northbrook

By dhiraan infrastructure pvt.ltd

RG-KA-79077 · RERA PRM/KA/RERA/1251/309/PR/200604/003434 · Last updated on RERA Karnataka portal: 26 May 2020

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • No complaints on record
  • Separate project account declared
Dec 2024Possession promisedmoved 21 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 97 documents Report an error

Dhiraan Northbrook is a Residential/Group Housing project by dhiraan infrastructure pvt.ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/200604/003434 on 4 Jun 2020. Possession is promised by 30 Dec 2024. The completion date has moved by 21 months from the original filing.

At a glance

Project

  • NameDhiraan Northbrook
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/200604/003434
  • ReraGenie IDRG-KA-79077

Builder

  • Namedhiraan infrastructure pvt.ltd
  • Entity typeCompany
  • Authorized SignatorySuresh B. S
  • DirectorSURESH B S
  • Board MemberREKHA B G
  • Other registrations3 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredJun 2020First promiseMar 2023Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on4 Jun 2020
  • Promised completion30 Dec 2024
  • Revised completionRevised to 30 Dec 2024 (originally 31 Mar 2023)
  • Buildings1 building record
  • Documents filed97 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DHIRAAN NORTHBROOK---1440144

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 26 May 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)Not applicable
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 26 May 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyNoNot applicable

Land and ownership4

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,945 sq m
Named landowners4
LandownerVillageDistrict
M/s Cerrtainant Private Limited Rep by Deepti R Kakade--
B.N.Ravindrachar--
T.K.Ambujakshi--
Mohammed Fazal Ahmed--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 20.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRamesha DB, Landmark Architects & Engineers
EngineerG. Praveen Kumar, ECO Consultants

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMar 2023 → Dec 2023

No reason recorded in the filing

EX/PRM/KA/RERA/1251/309/PR/240503/003434Dec 2023 → Dec 2024

Reason as filed by the promoterAwaiting OC

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed97

As listed on the registration, under the names the promoter filed them with; the newest 80 of 97 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/200604/003434 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Clarification regarding IT returns for the year 2018-19File: Declaration for Accounts.pdf26 May 2020
Joint Declaration AffidavitFile: Joint Declration Affidavit.pdf26 May 2020
Form-B AffidavitFile: Form B Affidavit.pdf26 May 2020
sec 3(1) non violation AffidavitFile: Sec 3(1) Non violation Affidavit.pdf26 May 2020
Encumbrance Certificate from 2015File: UPTO DATE EC.pdf26 May 2020
Sale Deed-1File: sale deeds4.pdf26 May 2020
sale DeedFile: Sale Deed 10.5 Guntas (Mohammed fazal)_compressed.pdf26 May 2020
Conversion CertificateFile: CONVERSION ORDER.pdf26 May 2020
khataFile: YELHANKA KHATHA_organized.pdf26 May 2020
JDAFile: JDA.pdf26 May 2020
GPAFile: GPA.pdf26 May 2020
KSPCB NOCFile: Karnataka state Pollution Control Board -1-converted_compressed.pdf26 May 2020
Commencement CertificateFile: Commencement Certifiate.pdf26 May 2020
Renewed PlanFile: NORTH BROOK APPROVAL PLAN - PG 1.pdf26 May 2020
specificationFile: ANNEXURE Specification.pdf26 May 2020
Approved planFile: 8830SCAN_20200317_0001.JPG17 Mar 2020
approved planFile: 8830SCAN_20200317_0002.JPG17 Mar 2020
Auditor Report 18-19File: Audited report 18.pdf14 Jan 2020
Balance Sheet 18-19File: Balance sheet 18.pdf14 Jan 2020
Director Report 18-19File: director report 18.pdf14 Jan 2020
P&L 18-19File: pl 18.pdf14 Jan 2020
Pollution board NOCFile: Pollution Board NOC.docx14 Jan 2020
Industrial NOCFile: industrial NOC.docx14 Jan 2020
Airport NoCFile: Airport NOC.docx14 Jan 2020
Sale deedFile: Saledeed 1.docx14 Jan 2020
Sale deedFile: saledeed lakshmamma.docx14 Jan 2020
Sale deedFile: saledeed-1034-2013-13.docx14 Jan 2020
Sale deedFile: saledeed-1035.docx14 Jan 2020
Sale deedFile: saledeed-2029-2012-2013.docx14 Jan 2020
sale deedFile: saledeed-2030.docx14 Jan 2020
sale deedFile: saledeed-3489-2002-03.docx14 Jan 2020
sale deedFile: saledeed-3489-2002-03.docx14 Jan 2020
sale deedFile: saledeed-26283.docx14 Jan 2020
sale deedFile: saledeed-3279109-10.docx14 Jan 2020
nocFile: NOC.docx14 Jan 2020
Form-BFile: 001.jpg6 Jan 2020
Form-BFile: 002.jpg6 Jan 2020
ECFile: EC - MODIFIED.docx6 Jan 2020
Approved planFile: Celestia Building Plan Approval page1 (1).pdf6 Jan 2020
Approved PlanFile: Celestia Building Plan Approval page2.pdf6 Jan 2020
Approved PlanFile: Celestia Building Plan Approval page2 (3).pdf6 Jan 2020
Approved PlanFile: Celestia Building Plan Approval page2 (1).pdf6 Jan 2020
Auditors report 16File: audited report 16 28.pdf6 Jan 2020
Balance Sheet 18File: Balance sheet 18 c.pdf6 Jan 2020
P&l 18File: pl 18.pdf6 Jan 2020
Auditor ReportFile: Audited report 18 (1).pdf6 Jan 2020
Director ReportsFile: director report 18.pdf6 Jan 2020
CCFile: CC.pdf6 Jan 2020
Conversion orderFile: land Conversion order.docx6 Jan 2020
kathaFile: 001 (1).jpg6 Jan 2020
kathaFile: 002 (1).jpg6 Jan 2020
kathaFile: 003.jpg6 Jan 2020
CertificateFile: regestration.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer Certificate Completed Work.pdf-
CA Certificate for Funds UtilizationFile: CA certificate - fund utilized DP NBK.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer Certificate Completed Work.pdf-
CA Certificate for Funds required for Project CompletionFile: CA certificate - funds required DP NBK.pdf-
AffidavitFile: Form B Affidavit.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
CC-
Celestia Building Plan Approval page2-
Celestia Building Plan Approval page1 (1)-
sale Deed-
DRFT-
RTC-
Celestia Building Plan Approval page2-
AJAY CHIKKAJALA SANCTION PLAN _FINAL_18-5-15-
Draft 2-
Typical Floor Plan-
ANNEXURE Specification-
EC - CHIKKAJALA-
aff-
n aff-
katha-
JDA-
160501_excvation-
AJAY CHIKKAJALA SANCTION PLAN _FINAL_18-5-15-
DC-
Balance Sheet 2017 - 2018File: Balance sheet 18 c.pdf-
Balance Sheet 2016 - 2017File: Balance sheet 17 (1).pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 21 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Dhiraan Northbrook on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmDhiraan NorthbrookOther 8Dot size: filed unitsN

Filed coordinates, straight-line distance. 8 registered projects within 2 km.

Builder: dhiraan infrastructure pvt.ltd

DHIRAAN INFRASTRUCTURE PVT LTD has 4 registrations on RERA Karnataka, including DHIRAAN URBAN FOREST and Dhiraan Northbrook. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Dhiraan Northbrook is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Dhiraan Northbrook?

The registered promoter entity is dhiraan infrastructure pvt.ltd, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Dhiraan Northbrook?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Dhiraan Northbrook?

The professionals named in the filing: Architect: Ramesha DB, Landmark Architects & Engineers; Engineer: G. Praveen Kumar, ECO Consultants. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Dhiraan Northbrook?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Dhiraan Northbrook. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Dhiraan Northbrook to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.