ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / DEV ASHOKA

Registration lapsed No litigation declared Others project

DEV ASHOKA

By DEV LAND & HOUSING PVT LTD

RG-MH-21196 · RERA P51700003374 · Last updated on MahaRERA portal: 23 Jan 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 71 months past the filed date
  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Nov 2020Possession promised71 months past this date
22 of 33Construction stages doneacross 3 buildings; furthest along: Installation of Lifts, 95%
0Complaints at MahaRERAon this registration
Jump to the 88 documents Report an error

DEV ASHOKA is a Others project by DEV LAND & HOUSING PVT LTD in Thane, Maharashtra, registered with MahaRERA as P51700003374 on 5 Aug 2017. Possession was promised by 30 Nov 2020 and is now 71 months past that date. The completion date has moved by 18 months from the original filing.

At a glance

Project

  • NameDEV ASHOKA
  • TypeOthers
  • Location
    • ESIC Hospital Road
    • Near Nitin Company Junction
    • Thane (M Corp.)
    • Thane
    • 400604
  • Pincode400604
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700003374
  • ReraGenie IDRG-MH-21196

Builder

  • NameDEV LAND & HOUSING PVT LTD
  • Entity typeCompany
  • Other registrations3 more →
  • Completed2 of 4
  • No longer live1 lapsed, de-registered or revoked

Key dates

71 months past promisethis monthRegisteredAug 2017First promiseMay 2019Revised toNov 2020

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Aug 2017
  • Promised completion30 Nov 2020
  • Revised completionRevised to 30 Nov 2020 (originally 31 May 2019)
  • Buildings3 building records
  • Documents filed88 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DEV ASHOKA S1NA260000
DEV ASHOKA S2NA250000
DEV ASHOKA S3NA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 23 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Installation of Lifts, at 95%.

DEV ASHOKA S181%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
DEV ASHOKA S281%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
DEV ASHOKA S363%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities18

As on 23 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes95%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%
Fitness Centre and Swimming PoolYes100%
Common Podium 1 basement and 3 levelsYes100%
0NoNot applicable

Parking filed361

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots361
Closed/Covered351
Open Space10
BuildingClosed/CoveredOpen SpaceTotal
DEV ASHOKA S11504154
DEV ASHOKA S21504154
DEV ASHOKA S351253

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,910 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
SHREE MANGALMURTI ENTERPRISESThane (M Corp.)Thane

Approvals and building plan

Permissible FSI32983.0
Proposed, not sanctioned32,983 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNAUPADA, THANE WEST

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectYOGESH N KELKAR AND ASSOCIATES
EngineerAJAY MAHALE
PartnerRole in project
DEV LAND & HOUSING PVT LTD-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700001825May 2019 → May 2020

Reason as filed by the promoterThe Project is a slum rehabilitation scheme wherein apart from the rehab component, 3 sale buildings viz. ‘S1, S2 and S3 are being constructed by us. We have already committed sale/allotment of 41 units in S1 and 39 units in S2, however have not committed sale/allotment in S3. The application for OC for S1 is already applied on 20th May 2019. For S2, the entire RCC work upto 20th floor is already completed. Till date, we have committed sale of 7 units in S2; and 6 out of 7 units in S2 have confirmed in writing that they have no objection to the extension of the Project. We are in process of ap

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 May 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 May 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 23 Jan 2025

Documents filed88

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: CA CERTIFICATE.pdf23 Jan 2025
Certificates of CA (Form 5)File: CA CERTIFICATE.pdf23 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: S3 PART OC _29-04-2022.pdf23 Jan 2025
Architect’s Certificate on Completion of Project (Form 4)File: 45 RERA Certificate .pdf22 Jan 2025
OtherFile: Reply to Rera Noticepdf.pdf22 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Louiswadi (Thane) FY 22-23.pdf17 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: THANE ASHOKA 21-22.pdf25 Jan 2023
Certificates of CA (Form 5)File: THANE ASHOKA 21-22.pdf25 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: THANE ASHOKA 20-21.pdf25 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERTIFICATE DLH DEV ASHOKA.pdf13 Aug 2021
Certificates of CA (Form 3)File: THANE ASHOKA.pdf13 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: ANNUAL REPORT 2019.pdf13 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: ANNUAL REPORT 2020.pdf13 Aug 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC THANE S1 JULY 19 2019.pdf13 Aug 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Full OC - S2.pdf13 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20200120123549.pdf20 Jan 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20200120123449.pdf20 Jan 2020
Certificates of CA (Form 3)File: rera certificate-1.pdf20 Jan 2020
Certificates of CA (Form 5)File: thane - form 5.pdf16 Dec 2019
Building plan approvalFile: S1.pdf22 May 2019
Building plan approvalFile: S2.pdf22 May 2019
Building plan approvalFile: s3.pdf22 May 2019
Building plan approvalFile: r1.pdf22 May 2019
Building plan approvalFile: r2.pdf22 May 2019
Building plan approvalFile: cfo.pdf22 May 2019
Building Plan Approval (IOD)File: S1.pdf22 May 2019
Building Plan Approval (IOD)File: S2.pdf22 May 2019
Building Plan Approval (IOD)File: s3.pdf22 May 2019
Building Plan Approval (IOD)File: r1.pdf22 May 2019
Building Plan Approval (IOD)File: r2.pdf22 May 2019
Building Plan Approval (IOD)File: cfo.pdf22 May 2019
Building plan approvalFile: IOD S2 - 27012018.pdf20 May 2019
Building plan approvalFile: Amended IOD S129012019 .pdf20 May 2019
Building plan approvalFile: Amended IOD S2 29012019.pdf20 May 2019
Building plan approvalFile: Amended IOD S3 29012019.pdf20 May 2019
Building Plan Approval (IOD)File: Amended IOD S129012019 .pdf20 May 2019
Building Plan Approval (IOD)File: Amended IOD S2 29012019.pdf20 May 2019
Building Plan Approval (IOD)File: Amended IOD S3 29012019.pdf20 May 2019
Building Plan Approval (IOD)File: IOD S2 - 27012018.pdf20 May 2019
Commencement Certificates / NA Order for plotted developmentFile: updated CC for S1 S2_compressed (1).pdf20 May 2019
OtherFile: BOM No dues letter.pdf20 May 2019
OtherFile: CFO NOC 8-05-2018_compressed.pdf20 May 2019
OtherFile: Fire NOC 28082018_compressed.pdf20 May 2019
OtherFile: MOEF NOC 16012019.pdf20 May 2019
OtherFile: OC - R2.pdf20 May 2019
OtherFile: possession Receipt 15-nov 2017.pdf20 May 2019
OtherFile: oc application thane_20190520172754.pdf20 May 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect thane dev ashoka.pdf15 May 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: amol kerkar dev ashoka.pdf15 May 2019
Certificates of CA (Form 3)File: c a thane dev ashoka.pdf15 May 2019
Certificates of CA (Form 5)File: form 5 - ashoka.pdf1 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: yogesh certificate.pdf27 Jul 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: amol certificate.pdf27 Jul 2018
Certificates of CA (Form 3)File: paresh.pdf27 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch yogesh kelkar.pdf30 Jan 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate ashoka.pdf30 Jan 2018
Certificates of CA (Form 3)File: CA Paresh Jain.pdf30 Jan 2018
Proforma of Allotment letterFile: DLH Ashoka-RERA FINAL.pdf30 Jan 2018
Building plan approvalFile: IOD ASHOKA Compressed.pdf28 Jul 2017
Layout approvalFile: LAYOUT LATTER.pdf28 Jul 2017
Layout approvalFile: IOD.pdf28 Jul 2017
Details of encumbrancesFile: MORT 1-10.pdf28 Jul 2017
Details of encumbrancesFile: MORT 11-20.pdf28 Jul 2017
Details of encumbrancesFile: MORT 31-40.pdf28 Jul 2017
Details of encumbrancesFile: MORT 41-50.pdf28 Jul 2017
Details of encumbrancesFile: MORT 61-70.pdf28 Jul 2017
Details of encumbrancesFile: MORT 71 80.pdf28 Jul 2017
Details of encumbrancesFile: MORT 80 96.pdf28 Jul 2017
Details of encumbrancesFile: last page.pdf28 Jul 2017
Details of encumbrancesFile: ENC ASHOKA LETTER.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: IOD.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT LATTER.pdf28 Jul 2017
Building Plan Approval (IOD)File: IOD ASHOKA Compressed.pdf28 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: IOD 03032014.pdf28 Jul 2017
Declaration in FORM BFile: FORM B ASHOKA-ilovepdf-compressed.pdf28 Jul 2017
Declaration in FORM BFile: JV-Ag-1-20.pdf28 Jul 2017
Declaration in FORM BFile: JV-Ag-21-42.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH ASHOKA.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CERT ASHOKA.pdf28 Jul 2017
Certificates of CA (Form 3)File: CA.pdf28 Jul 2017

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 18 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DEV ASHOKA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near Nitin Company Junction7,600+ in Thane

2 kmDEV ASHOKACompleted 116Lapsed / revoked 68Other 156Dot size: filed unitsN

Filed coordinates, straight-line distance. 340 registered projects within 2 km.

Builder: DEV LAND & HOUSING PVT LTD

DEV LAND & HOUSING PVT LTD has 4 registrations on MahaRERA, including DLH DREAM TOWER and DLH ORNATE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that DEV ASHOKA shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if DEV ASHOKA is delayed beyond 30 Nov 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DEV ASHOKA?

The registered promoter entity is DEV LAND & HOUSING PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DEV ASHOKA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for DEV ASHOKA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DEV ASHOKA?

The professionals named in the filing: Architect: YOGESH N KELKAR AND ASSOCIATES; Engineer: AJAY MAHALE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DEV ASHOKA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DEV ASHOKA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DEV ASHOKA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.