Red flags

  • 1 complaint at RERA Karnataka

Clear

  • Completion date never moved
  • Separate project account declared
Dec 2023Possession promisedno revision filed
1Complaints at RERA Karnatakaon this registration
Jump to the 68 documents Report an error

DB LAKVEN GARDENIA is a Residential/Group Housing project by DB INFRA DEVELOPERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/210813/004266 on 13 Aug 2021. Possession is promised by 31 Dec 2023. 1 complaint is on record with the regulator.

At a glance

Project

  • NameDB LAKVEN GARDENIA
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/210813/004266
  • ReraGenie IDRG-KA-93990

Builder

  • NameDB INFRA DEVELOPERS
  • Entity typePartnership Firm
  • Authorized SignatoryT.PRATHEESH KUMAR
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2021PromisedDec 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on13 Aug 2021
  • Promised completion31 Dec 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed68 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DB LAKVEN GARDENIA---96096

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 6 Aug 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 6 Aug 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,047 sq m
Named landowners1
LandownerVillageDistrict
SADANJANA GROUP--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 26.50 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHUBHASHINI.T
EngineerKUMAR.C.G

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
00011/2024-DB INFRA DEVELOPERS04/01/2024

Documents filed68

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/210813/004266 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
AAI NOCFile: AAI NOC.pdf6 Aug 2021
BESCOM NOCFile: BESCOM NOC.pdf6 Aug 2021
BWSSB NOCFile: BWSSB NOC.pdf6 Aug 2021
BBMP Plan - Legible CopyFile: BBMP PLAN - All Floor Plan.pdf7 Jul 2021
BBMP Plan - Legible Copy BasementFile: BBMP PLAN Basement and Stilt.pdf7 Jul 2021
UDIN from CA for the financial year 2019-20 has been mentioned in Page No 8File: 2019-20 Financial Statement CA UDIN No in Page No 8.pdf7 Jul 2021
Financial Statement 2019-20 with CA UDINFile: 2019_2020_Income_Tax_UDIN_compressed.pdf16 Jun 2021
Sanctioned typical floor plansFile: BBMP PLAN - All Floor Plan.pdf16 Jun 2021
Basement and Stilt PlanFile: BBMP PLAN Basement and Stilt.pdf16 Jun 2021
CertificateFile: DB INFRA FIRM Registered Certificate.pdf-
LG_BBMP LICENCE-
BBMP PLAN Basement and Stilt-
LG_SADANJANA SALE DEED-
PROJECT SPECIFICATIONS_compressed-
EC FROM 2004 to Till Date_compressed-
Affidavit-
Joint Affidavit Cum Declaration-
LG_BBMP KATHA CERTIFICATE & EXTRACT-
JDA_compressed-
LG-CONVERTION ORDER-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
KSPCB - NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
BBMP PLAN - All Floor Plan-
BBMP PLAN Basement and Stilt-
Unnamed document-
Balance Sheet 2019 - 2020File: 2020_2021_Income_Tax_Balance Sheet.pdf-
Balance Sheet 2018 - 2019File: 2019_2020_Income_tax_Balance Sheet.pdf-
Balance Sheet 2017 - 2018File: 2018_2019_Income_Tax Balance Sheet.pdf-
Audited Profit and Loss Statement 2019 - 2020File: 2020_2021_Income_Tax_P and L.pdf-
Audited Profit and Loss Statement 2018 - 2019File: 2019_2020_Income_tax_P and L.pdf-
Audited Profit and Loss Statement 2017 - 2018File: 2018_2019 P and L.pdf-
Cash Flow Statement 2019 - 2020File: 2020_2021_Income_Tax_Cash Flow.pdf-
Cash Flow Statement 2018 - 2019File: 2019_2020_Income_tax_Cash Flow.pdf-
Auditor's Report 2019 - 2020File: 2020_2021_Income_Tax_Auditors Report.pdf-
Auditor's Report 2018 - 2019File: 2019_2020_Income_tax_Auditors Report.pdf-
Auditor's Report 2017 - 2018File: 2018_2019_Income_Tax_Auditors Report.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: 2020_2021_Income_Tax_Ack.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: 2019_2020_Income_tax Ack.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: 2018_2019_Income_Tax Ack.pdf-
Form - B-
Prospectus/BrochureFile: Brouchure.pdf-
Advertisement Copy 1File: Brouchure.pdf-
Tower Excel SheetFile: PRMKARERA1251446PR210813004266.xlsx-
Occupancy CertificateFile: OC DOCUMENT_DB LAKVEN GARDENIA.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: BESCOM SANCTION LETTER.pdf-
Architect certificate for having completed the work(in format no 5)File: ARCHITECT REPORT FOR COMPLETION.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: CA REPORT FOR COMPLETION.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: RERA_AFFIDAVIT FOR COMPLETION.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep DB LAKVEN GARDENIA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmDB LAKVEN GARDENIAOther 60Dot size: filed unitsN

Filed coordinates, straight-line distance. 60 registered projects within 2 km.

Builder: DB INFRA DEVELOPERS

DB INFRA DEVELOPERS has 2 registrations on RERA Karnataka, including DB LAKVEN VISISHTA and DB LAKVEN GARDENIA. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if DB LAKVEN GARDENIA is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of DB LAKVEN GARDENIA?

The registered promoter entity is DB INFRA DEVELOPERS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in DB LAKVEN GARDENIA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against DB LAKVEN GARDENIA?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at DB LAKVEN GARDENIA?

The professionals named in the filing: Architect: SHUBHASHINI.T; Engineer: KUMAR.C.G. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DB LAKVEN GARDENIA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DB LAKVEN GARDENIA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DB LAKVEN GARDENIA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.