Home / Browse projects / Buldana, Maharashtra / D SQUARE BULDHANA
D SQUARE BULDHANA
By MANDAKINI RAMESHRAV CHAMBHARE PATIL
RG-MH-63328 · RERA P50000030077 · Last updated on MahaRERA portal: 9 Jan 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Buldana registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
D SQUARE BULDHANA is a Residential / Group Housing project by MANDAKINI RAMESHRAV CHAMBHARE PATIL in Buldana, Maharashtra, registered with MahaRERA as P50000030077 on 29 Jul 2021. Possession was promised by 31 Dec 2025 and is now 10 months past that date.
At a glance
Project
- NameD SQUARE BULDHANA
- TypeResidential / Group Housing
- Location
- NEAR CIRCULAR ROAD
- KESHAV NAGAR
- buldana (MCL)
- Buldana
- 443001
- Pincode443001
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50000030077
- ReraGenie IDRG-MH-63328
Builder
- NameMANDAKINI RAMESHRAV CHAMBHARE PATIL
- Entity typeIndividual
- Declared earlier projects2 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on29 Jul 2021
- Promised completion31 Dec 2025
- Revised completionNone
- Buildings1 building record
- Documents filed43 files
Current status
Figures as on 9 Jan 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| D SQUARE BULDHANA | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 9 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 70%.
D SQUARE BULDHANA: 44% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 35% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 10% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 9 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 80% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 40% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 40% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | Yes | 80% |
| Open Parking | Yes | 100% |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| D SQUARE BULDHANA | NA | Rs 2.04 cr | Rs 2.01 cr |
| - | NA | Rs 2.04 cr | Rs 2.01 cr |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MNY CONSULTING PRIVATE LIMITED |
| Engineer | NEHA RAMESH PATIL |
| Chartered Accountant | ANAND SUREKA |
| Partner | Role in project |
|---|---|
| MNY CONSULTING PRIVATE LIMITED | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 15 Jul 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 4 Jul 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 4 Jul 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 4 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed43
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1 | 9 Jan 2026 |
| Withdrawal Update Form 1 | 9 Jan 2026 |
| Withdrawal Update Form 1 | 9 Jan 2026 |
| Withdrawal Update Form 1 | 9 Jan 2026 |
| Withdrawal Update Form 1 | 9 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 NP.pdf | 9 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 NP.pdf | 9 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 NP.pdf | 9 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 NP.pdf | 9 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 NP.pdf | 9 Jan 2026 |
| Withdrawal Update Form 3File: form 5 ca.pdf | 9 Jan 2026 |
| Withdrawal Update Form 3File: form 5 ca.pdf | 9 Jan 2026 |
| Withdrawal Update Form 3File: form 5 ca.pdf | 9 Jan 2026 |
| Withdrawal Update Form 3File: form 5 ca.pdf | 9 Jan 2026 |
| Withdrawal Update Form 3File: form 5 ca.pdf | 9 Jan 2026 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3-23-24.pdf | 1 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 23 - 24.pdf | 1 Jun 2024 |
| Details of encumbrances concerned to FinanceFile: mom letter for encumbances'1.pdf | 19 Sep 2023 |
| Details of encumbrances concerned to LegalFile: mom letter for encumbances'1.pdf | 19 Sep 2023 |
| CERSAI detailsFile: CEDAI.pdf | 19 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 ca.pdf | 19 Sep 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: napp.pdf | 19 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 ca.pdf | 19 Sep 2023 |
| Deviation Report with respect to Allotment letterFile: napp.pdf | 19 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: CHARTERED ACCOUNTANTS CERTIFICATE FORM 5.pdf | 10 Feb 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: mom pass book.pdf | 10 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CHARTERED ACCOUNTANTS CERTIFICATE 21-22.pdf | 31 Mar 2022 |
| OtherFile: 2122 D SQUARE BULDHANA PHOTOS.pdf | 31 Mar 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.PDF | 24 Jul 2021 |
| Copy of the legal title reportFile: Legal title report .pdf | 15 Jul 2021 |
| Details of encumbrancesFile: mom letter for encumbances'1.pdf | 6 Jul 2021 |
| Details of encumbrancesFile: mom letter for encumbances2.pdf | 6 Jul 2021 |
| Declaration about Commencement CertificateFile: DECLARATION FOR COMMENCEMENT.pdf | 6 Jul 2021 |
| Declaration in FORM BFile: AFFIDAVITRERA.pdf | 5 Jul 2021 |
| Proforma of Allotment letterFile: sale agrrement.pdf | 5 Jul 2021 |
| Building plan approvalFile: bmc sanction plan.pdf | 4 Jul 2021 |
| Layout approvalFile: layout sanction plan less.pdf | 4 Jul 2021 |
| Building plan approvalFile: na order less.pdf | 4 Jul 2021 |
| PAN CardFile: MANDAKINIPAN.pdf | 4 Jul 2021 |
| Copy of Layout Approval (in case of layout)File: layout sanction plan less.pdf | 4 Jul 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: bmc sanction plan.pdf | 4 Jul 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: na order less.pdf | 4 Jul 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: commencement.pdf | 4 Jul 2021 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| D SQUARE MALKAPUR | D SQUARE BANSILAL NAGAR ROAD CHAITANYAWADI MALKAPUR | 10 | Completed | Jan 2014 | Jan 2014 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Buldana
Computed across the 58 Buldana projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 43 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep D SQUARE BULDHANA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KESHAV NAGAR58 in Buldana
Filed coordinates, straight-line distance. 4 registered projects within 2 km.
EKDANT RESIDENCY PHASE 4
EKDANT BUILDERS
Anand Mangal
Sumit Sahebrao Sardar
ANAND SAGAR RESIDENCY
ASHOK SATYANARAYAN VYAS
ANAND TOWER
SUMITKUMAR SAHEBRAO SARDAR
BULDANA PRIDE CONSTRUCTION
BULDANA PRIDE CONSTRUCTION
Construction of 268 EWS 20 MIG and 16 HIG T/s
Amravati Housing And Area Development Boar
See every Buldana project, with the district possession charts
Builder: MANDAKINI RAMESHRAV CHAMBHARE PATIL
MANDAKINI RAMESHRAV CHAMBHARE PATIL has 1 registration on MahaRERA, including D SQUARE BULDHANA. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Buldana district page.
Frequently asked questions
What does it mean that D SQUARE BULDHANA shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if D SQUARE BULDHANA is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of D SQUARE BULDHANA?
The registered promoter entity is MANDAKINI RAMESHRAV CHAMBHARE PATIL, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in D SQUARE BULDHANA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for D SQUARE BULDHANA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at D SQUARE BULDHANA?
The professionals named in the filing: Architect: MNY CONSULTING PRIVATE LIMITED; Engineer: NEHA RAMESH PATIL; Chartered Accountant: ANAND SUREKA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in D SQUARE BULDHANA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.