Home / Browse projects / Bengaluru Urban, Karnataka / D C CAPITOL PHASE - II
D C CAPITOL PHASE - II
RG-KA-91437 · RERA PRM/KA/RERA/1251/446/PR/041024/007120 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
D C CAPITOL PHASE - II is a Residential/Group Housing project by D.C.HI-RISE LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/041024/007120 on 4 Oct 2024. Possession is promised by 31 Dec 2028. 111 of the 164 units on this registration are recorded sold or booked, and 4 of 16 construction stages are filed complete.
At a glance
Project
- NameD C CAPITOL PHASE - II
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/446/PR/041024/007120
- ReraGenie IDRG-KA-91437
Builder
- NameD.C.HI-RISE LLP
- Entity typePartnership Firm
- LLPINAAB-0768
- GSTIN29AAJFD0654Q1ZV
- Authorized SignatoryA LAKSHMAPPA
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on4 Oct 2024
- Promised completion31 Dec 2028
- Revised completionNone
- Buildings1 building record
- Documents filed191 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| B | - | - | - | 164 | 0 | 164 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 16 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 85%.
Building: 68% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | Not applicable |
| RCC or MS Framed structure | 85% |
| Masonry Construction | 75% |
| Plastering inside , outside & Ceiling | 75% |
| Joinery: Doors, Windows, Ventilators etc | 70% |
| Basic work of Water supply, Sanitary and Electrification | 75% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 70% |
| Railing and Grill fixing | 55% |
| Electrification, Water supply and Sanitary Finishing | 60% |
| Painting | 55% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | 35% |
| Elevation work | 35% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 50% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 70% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | 50% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | 50% |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | No | Not applicable |
| Piped Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 90% |
| Lifts | Yes | 90% |
| Corridor/Lobbies | Yes | 90% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | No | Not applicable |
| Basement | Yes | 100% |
| Terrace | Yes | 50% |
| Outer Wall | Yes | 45% |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | 70% |
| Common storage spaces | No | Not applicable |
Land and ownership8
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| D.C.HI-RISE LLP | - | - |
| D.C.HI-RISE LLP | - | - |
| D.C.HI-RISE LLP | - | - |
| D.C.HI-RISE LLP | - | - |
| D.C.HI-RISE LLP | - | - |
| D.C.HI-RISE LLP | - | - |
| D.C.HI-RISE LLP | - | - |
| Manu G | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 98.97 cr | Rs 77.95 cr |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Bhanumathy G |
| Engineer | ARUN KUMAR S R |
| Chartered Accountant | CA RAGHU NADHA MANDADI G |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed191
As listed on the registration, under the names the promoter filed them with; the newest 80 of 191 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/041024/007120 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: From-4 -Signed.PDF | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: D C HI RISE- FORM-5 (2nd Qtr).pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: D C HI RISE- FORM-6 (2nd Qtr).pdf | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4.PDF | 14 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: D C HI-RISE- FORM-5- (1st Qtr).pdf | 14 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: D C HI-RISE- FORM-6-(1st Qtr).pdf | 14 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Signd Form 4.PDF | 15 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: D C HI-RISE-FORM-5 (4th Qtr).pdf | 15 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: D C HI-RISE-FORM-6 (4th Qtr).pdf | 15 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Signed Q3.PDF | 14 Mar 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: D C HI-RISE- FORM-5 (3rd Qtr).pdf | 14 Mar 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: D C HI-RISE -FORM -6 (3rd Qtr).pdf | 14 Mar 2026 |
| DC HIGH RISE Phase 1 & 2 - Area Demarcation PlanFile: 1 DC HIGH RISE Phase 1 & 2 - Area Demarcation Plan.pdf | 25 Sep 2024 |
| Source of Funds with supporting docsFile: 2 Source of Funds with supporting docs.pdf | 25 Sep 2024 |
| EC All Sy No 2008-2024File: 1 EC All Sy No 2008-2024.pdf | 25 Sep 2024 |
| Panchayath Partition 1963 dec sy no 1-1File: 2 Panchayath Partition 1963 dec sy no 1-1.pdf | 25 Sep 2024 |
| Title Deed Sy No 1-3A 1957File: 2 Title Deed Sy No 1-3A 1957.pdf | 25 Sep 2024 |
| Gift Deed 102-4 G ManuFile: 4 Gift Deed 102-4 G Manu.pdf | 25 Sep 2024 |
| Case Status 8320_2015File: 3 Case Status 8320_2015.pdf | 25 Sep 2024 |
| Old Title deed 3699 69-70 Sy no 1-1File: 1 Old Title deed 3699 69-70 Sy no 1-1.pdf | 25 Sep 2024 |
| DC HIGH RISE Phase 1 & 2 - Area DetailsFile: 2 DC HIGH RISE Phase 1 & 2 - Area Details.pdf | 25 Sep 2024 |
| RTC, survey 1/1 | - |
| Mutation, survey 1/1 | - |
| Encumbrance Certificate, survey 1/1 | - |
| Conversion/Alienation Order, survey 1/1 | - |
| Sale/Title/Gift Deed, survey 1/1 | - |
| Khatha, survey 1/1 | - |
| RTC, survey 1/3A | - |
| Mutation, survey 1/3A | - |
| Encumbrance Certificate, survey 1/3A | - |
| Conversion/Alienation Order, survey 1/3A | - |
| Sale/Title/Gift Deed, survey 1/3A | - |
| Khatha, survey 1/3A | - |
| RTC, survey 1/3A | - |
| Mutation, survey 1/3A | - |
| Encumbrance Certificate, survey 1/3A | - |
| Conversion/Alienation Order, survey 1/3A | - |
| Sale/Title/Gift Deed, survey 1/3A | - |
| Khatha, survey 1/3A | - |
| RTC, survey 102/2 | - |
| Mutation, survey 102/2 | - |
| Encumbrance Certificate, survey 102/2 | - |
| Conversion/Alienation Order, survey 102/2 | - |
| Sale/Title/Gift Deed, survey 102/2 | - |
| Khatha, survey 102/2 | - |
| RTC, survey 102-5 | - |
| Mutation, survey 102-5 | - |
| Encumbrance Certificate, survey 102-5 | - |
| Conversion/Alienation Order, survey 102-5 | - |
| Sale/Title/Gift Deed, survey 102-5 | - |
| Khatha, survey 102-5 | - |
| RTC, survey 102/6 | - |
| Mutation, survey 102/6 | - |
| Encumbrance Certificate, survey 102/6 | - |
| Conversion/Alienation Order, survey 102/6 | - |
| Sale/Title/Gift Deed, survey 102/6 | - |
| Khatha, survey 102/6 | - |
| RTC, survey 102/8 | - |
| Mutation, survey 102/8 | - |
| Encumbrance Certificate, survey 102/8 | - |
| Conversion/Alienation Order, survey 102/8 | - |
| Sale/Title/Gift Deed, survey 102/8 | - |
| Khatha, survey 102/8 | - |
| RTC, survey 102/4 | - |
| Mutation, survey 102/4 | - |
| Encumbrance Certificate, survey 102/4 | - |
| Conversion/Alienation Order, survey 102/4 | - |
| JDA, survey 102/4 | - |
| Khatha, survey 102/4 | - |
| Registration CertificateFile: Certificate incorporation.pdf | - |
| Partnership DeedFile: New Partnership LLP Deed.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep D C CAPITOL PHASE - II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: D.C.HI-RISE LLP
D.C.HI-RISE LLP has 2 registrations on RERA Karnataka, including D C CAPITOL PHASE - II and DC CAPITOL. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if D C CAPITOL PHASE - II is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of D C CAPITOL PHASE - II?
The registered promoter entity is D.C.HI-RISE LLP, a partnership firm as per the filing. Its LLPIN AAB-0768 and GSTIN 29AAJFD0654Q1ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in D C CAPITOL PHASE - II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at D C CAPITOL PHASE - II?
The professionals named in the filing: Architect: Bhanumathy G; Engineer: ARUN KUMAR S R; Chartered Accountant: CA RAGHU NADHA MANDADI G. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in D C CAPITOL PHASE - II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback