Home / Browse projects / Bengaluru Urban, Karnataka / CONFIDENT SQUARE

Registration approved Commercial project

CONFIDENT SQUARE

By CONFIDENT PROJECTS INDIA LIMITED

RG-KA-94001 · RERA PRM/KA/RERA/1251/308/PR/211230/004618 · Last updated on RERA Karnataka portal: 17 Dec 2021

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Oct 2024Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 75 documents Report an error

CONFIDENT SQUARE is a Commercial project by CONFIDENT PROJECTS INDIA LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/211230/004618 on 30 Dec 2021. Possession is promised by 31 Oct 2024.

At a glance

Project

  • NameCONFIDENT SQUARE
  • TypeCommercial
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/211230/004618
  • ReraGenie IDRG-KA-94001

Builder

  • NameCONFIDENT PROJECTS INDIA LIMITED
  • Entity typeCompany
  • Authorized SignatoryMR. JOJU KOCHAPPAN
  • OthersMR. JOJU KOCHAPPAN
  • Declared earlier projects4 →

Key dates

this monthRegisteredDec 2021PromisedOct 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on30 Dec 2021
  • Promised completion31 Oct 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed75 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CONFIDENT SQUARE---08080

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 17 Dec 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 17 Dec 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,743 sq m
Named landowners1
LandownerVillageDistrict
CONFIDENT PROJECTS INDIA LIMITED--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 16.58 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUma Nirmala P
EngineerCIVITECH DESIGNS

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed75

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/211230/004618 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Snowflake quaterly updates doneFile: SnowflakeQ2.jpeg17 Dec 2021
Sale agreementFile: Sale agreement .pdf4 Dec 2021
No mortgage affidavitFile: Affidavit No mortgage certificate.pdf4 Dec 2021
Beverly hills Q2 and Q3 completedFile: BeverlyCapture.PNG8 Nov 2021
Meadows Q2 completedFile: meadowsCapture.PNG8 Nov 2021
Cheque leafFile: square cheque leave.pdf23 Oct 2021
Plan approval squareFile: Planapproval square.pdf23 Oct 2021
Conversion OrderFile: Conversion order 25 guntas square.pdf6 Oct 2021
ECFile: EC square 1.pdf6 Oct 2021
Approved PlanFile: Scan 2021-9-13 (16,51,48) (1)-compressed.pdf6 Oct 2021
STP clarification along with DrawingsFile: With STP Location_compressed (1).pdf6 Oct 2021
Water NOCFile: water noc square.pdf6 Oct 2021
BESCOM NocFile: BESCOM NOC.pdf6 Oct 2021
P&L 2018File: Audited Profit loss statement 2018.pdf6 Oct 2021
P&L2019File: Audited Profit loss statement 2019.pdf6 Oct 2021
P&L2020File: Audited Profit Loss Statement 2020.pdf6 Oct 2021
CASH FLOW 2018File: Cash flow statement 2018.pdf6 Oct 2021
CASH FLOW 2019File: Cash Flow Statement2019.pdf6 Oct 2021
CASH FLOW 2020File: Cash Flow Statement2020.pdf6 Oct 2021
BALANCE SHEET 2018File: Balance sheet 2018.pdf6 Oct 2021
BALANCE SHEET 2018File: Balance sheet 2019.pdf6 Oct 2021
Balancesheet2020File: Balance sheet 2020.pdf6 Oct 2021
PassbookFile: PASS BOOK.pdf6 Oct 2021
CertificateFile: Registration Certificate of Confident Projects.pdf-
commencement certificate 1-
Approv plan-
Sale Deed Square1-
SALE agreement-Square-
Sale deed and RTC-
Allotment Letter - SQU G05-
Square Brochure 1-
project specification square-
EC square-
affidavit sqaure-
Affidavit cum JD-
khatha square-
Square collabration agreement-
Noc panchyat-
conversion certificate square-
relinquishment deed square (2)-
NOC PCB square (2)-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Balance Sheet 2019 - 2020File: Balance sheet 2020.pdf-
Balance Sheet 2018 - 2019File: Balance sheet 2019.pdf-
Balance Sheet 2017 - 2018File: Balance sheet 2018.pdf-
Audited Profit and Loss Statement 2019 - 2020File: Audited Profit Loss Statement 2020.pdf-
Audited Profit and Loss Statement 2018 - 2019File: Audited Profit loss statement 2019.pdf-
Audited Profit and Loss Statement 2017 - 2018File: Audited Profit loss statement 2018.pdf-
Director's Report 2019 - 2020File: Directors Report 2020.pdf-
Director's Report 2018 - 2019File: Directors Report 2019.pdf-
Director's Report 2017 - 2018File: Directors Report 2018.pdf-
Cash Flow Statement 2019 - 2020File: Cash Flow Statement2020.pdf-
Cash Flow Statement 2018 - 2019File: Cash Flow Statement2019.pdf-
Auditor's Report 2019 - 2020File: Auditor Report 2020.pdf-
Auditor's Report 2018 - 2019File: Auditor Report 2019.pdf-
Auditor's Report 2017 - 2018File: Auditor Report 2018.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: ITR 2020-2021.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: ITR 2019-2020.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: ITR 2018- 2019.pdf-
declaration square 1-
Prospectus/BrochureFile: Square Brochure with rera (1).pdf-
Advertisement Copy 1File: square advertisment copy.jpeg-
Tower Excel SheetFile: Rera Final Submited on 11 03 2022.xlsx-
Stability CertificateFile: Stability square.pdf-
Occupancy CertificateFile: OC of Confident Square (1).pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: BESCOM NOC SQUARE (1).pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: Water NOC SQUARE 1 1 1.pdf-
Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: Amenities.pdf-
Architect certificate for having completed the work(in format no 5)File: Square Archi certificate.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: square completion certificate (1)_compressed.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Stability square.pdf-

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 not delivered by the promised date2 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
CONFIDENT OXYGEN-OngoingMar 2024Not delivered
CONFIDENT SNOWFLAKES-OngoingOct 2023Not delivered
CONFIDENT PLATINUM PHASE II-Completed-No date filed
BEVERLY HILLS-Completed-No date filed

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep CONFIDENT SQUARE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmCONFIDENT SQUAREOther 70Dot size: filed unitsN

Filed coordinates, straight-line distance. 70 registered projects within 2 km.

Builder: CONFIDENT PROJECTS INDIA LIMITED

CONFIDENT PROJECTS INDIA LIMITED has 1 registration on RERA Karnataka, including CONFIDENT SQUARE. Its filings declare 4 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if CONFIDENT SQUARE is delayed beyond 31 Oct 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of CONFIDENT SQUARE?

The registered promoter entity is CONFIDENT PROJECTS INDIA LIMITED, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in CONFIDENT SQUARE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at CONFIDENT SQUARE?

The professionals named in the filing: Architect: Uma Nirmala P; Engineer: CIVITECH DESIGNS. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CONFIDENT SQUARE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CONFIDENT SQUARE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CONFIDENT SQUARE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.