Registration approved Residential/Group Housing project

CONFIDENT MEADOWS

By D J PROJECTS PRIVATE LIMITED

RG-KA-16520 · RERA PRM/KA/RERA/1251/308/PR/210518/004157 · Last updated on RERA Karnataka portal: 20 Dec 2022

Source: official RERA Karnataka filing

Red flags

  • 4 complaints at RERA Karnataka

Clear

  • Completion date never moved
  • Separate project account declared
Apr 2025Possession promisedno revision filed
4Complaints at RERA Karnatakaon this registration
Jump to the 87 documents Report an error

CONFIDENT MEADOWS is a Residential/Group Housing project by D J PROJECTS PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/210518/004157 on 18 May 2021. Possession is promised by 30 Apr 2025. 4 complaints are on record with the regulator.

At a glance

Project

  • NameCONFIDENT MEADOWS
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/210518/004157
  • ReraGenie IDRG-KA-16520

Builder

  • NameD J PROJECTS PRIVATE LIMITED
  • Entity typeCompany
  • CINU15201DL2005PTC134979
  • Authorized SignatoryMR. JOJU KOCHAPPAN
  • OthersMR. JOJU KOCHAPPAN
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredMay 2021PromisedApr 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on18 May 2021
  • Promised completion30 Apr 2025
  • Revised completionNone
  • Buildings3 building records
  • Documents filed87 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---34034
B---54054
C---60060

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 20 Dec 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 20 Dec 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymYes-
ParksNoNot applicable
Power BackupNoNot applicable
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,790 sq m
Named landowners1
LandownerVillageDistrict
D J PROJECTS PRIVATE LIMITED--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 16.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUma Nirmala. P
EngineerCIVITECH DESIGNS

Complaints filed with RERA Karnataka4

Case no.ComplainantRespondentFiled
01387/2025-D J PROJECTS PRIVATE LIMITED14/11/2025
01388/2025-D J PROJECTS PRIVATE LIMITED14/11/2025
01389/2025-D J PROJECTS PRIVATE LIMITED14/11/2025
01390/2025-D J PROJECTS PRIVATE LIMITED14/11/2025

Documents filed87

As listed on the registration, under the names the promoter filed them with; the newest 80 of 87 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/210518/004157 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Break up details of flat BHK wiseFile: MEADOWS Final Area statement FOR RERA BHK wise (3).pdf20 Dec 2022
Sold and unsold unit detailsFile: Sold and unsold unit meadows modification.pdf20 Dec 2022
Consent letter 1-10File: Meadows modification with sign 1_compressed.pdf20 Dec 2022
Consent letter 11-20File: Meadows modification with sign 2_compressed.pdf20 Dec 2022
Consent letter 21- 30File: Meadows Modification with sign3_compressed.pdf20 Dec 2022
Consent letter 21-40File: Meadows Modification with sign 4_compressed.pdf20 Dec 2022
Consent letter 41- 50File: Meadows modification with sign 5_compressed.pdf20 Dec 2022
Consent letter 51- 60File: Meadows modification with sign 6_compressed.pdf20 Dec 2022
Consent letter 60-70File: Meadows modification with sign 7_compressed.pdf20 Dec 2022
Consent letter 71- 80File: Meadows modification with sign 8_compressed.pdf20 Dec 2022
Terrace Floor PlanFile: Terrace floor plan.pdf6 May 2021
Sale deed for Sy No. 167/3File: Saledeed 167-3.pdf17 Apr 2021
EC for Sy No. 167/3 from 1.04.2005 to till dateFile: EC for 167(3)-1.pdf17 Apr 2021
Building terrace planFile: Scan 2021-3-24 (15,45,52) terrace floor plan.pdf17 Apr 2021
NOC by local Water Supply AuthoritiesFile: grampanchayat noc.pdf17 Apr 2021
CertificateFile: RC.pdf-
Already registered project ongoing detailsFile: Meadows on going Project details.pdf-
Modified plan details site plan, floor plans, Plan Licence LetterFile: Meadows Building License.pdf-
List Of AllotteesFile: Meadows Alotee.pdf-
Consent LetterFile: Meadows modification consent letter.pdf-
Chartered Accountant CertificateFile: Meadows modification form 4 compresed.pdf-
Notarized AffidavitFile: Meadows modification Affidavit.pdf-
Engineer CertificateFile: Meadows modification engineering certificate.pdf-
Architect CertificateFile: Meadows modification Architech.pdf-
Structural Engineer Certificate for stability of structureFile: Meadows stability certificate (1).pdf-
Modification of Plan DetailsFile: Approved building plan.pdf-
Modification of Plan DetailsFile: Meadows modification plan approval.pdf-
Modification of Plan DetailsFile: CC meadows old.pdf-
Modification of Plan DetailsFile: Modified CC_compressed.pdf-
Modification of Plan DetailsFile: Unit details meadows old.pdf-
Modification of Plan DetailsFile: Meadows Unit details for modification sold and unsold (1).pdf-
Consent letter 2File: Consent letter meadows with sign part 2 (1).pdf-
Consent letter 3File: Meadows consent letter 3.pdf-
Meadows site plan floor and licenceFile: Modified site plan, floor plan license new.pdf-
Comencement Certificate-
Approved Layout Plan-
Proforma of sale deed-
Proforma of Sale Agreement-
Sale Deed & RTC-
Approved section of building-
Area Development Plan of project area-
Proforma of allotment letter-
Brochure-
Project specification-
Encumbrance Certificate-
Section 3(1) Notarised Affidavit-
Khatha-
conversion Order-
Relinquishment deed-
KSFES Noc-
Airport authority NOC-
BESCOM NOC-
KSPCB Noc-
BSNL NOC-
Unnamed document-
Sectional Drawing of the Apartments-
Existing Section Plan and specification-
Change of land use-
Balance Sheet 2019 - 2020File: Balance Sheet 2020.pdf-
Balance Sheet 2018 - 2019File: Balance sheet 2019.pdf-
Balance Sheet 2017 - 2018File: Balance sheet 2018.pdf-
Audited Profit and Loss Statement 2019 - 2020File: Audited P&L Statement 2020.pdf-
Audited Profit and Loss Statement 2018 - 2019File: Audited P&L Statement 2019.pdf-
Audited Profit and Loss Statement 2017 - 2018File: Audited P-L Statement 2018.pdf-
Director's Report 2019 - 2020File: Director Report 2020.pdf-
Director's Report 2018 - 2019File: Director Report 2019.pdf-
Director's Report 2017 - 2018File: Director Report 2018.pdf-
Cash Flow Statement 2019 - 2020File: Cashflow 2020.pdf-
Cash Flow Statement 2018 - 2019File: Cashflow 2019.pdf-
Auditor's Report 2019 - 2020File: auditor report 2020.pdf-
Auditor's Report 2018 - 2019File: Auditor Report 2019.pdf-
Auditor's Report 2017 - 2018File: Auditor Report 2018.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: ITR Acknowledgement 2020.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: ITR Acknowledgement 2019.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: ITRV Acknowledgement 2018.pdf-
Declaration (Form B)-
Prospectus/BrochureFile: Meadows brochure 1 (1).pdf-
Advertisement Copy 1File: adv meadows new.pdf-
Tower Excel SheetFile: PRMKARERA1251308PR210518004157 area statement (2).xlsx-
Stability CertificateFile: Stability certificate meadows.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
CONFIDENT PLATINUM PHASE I-Completed-No date filed

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep CONFIDENT MEADOWS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmCONFIDENT MEADOWSOther 75Dot size: filed unitsN

Filed coordinates, straight-line distance. 75 registered projects within 2 km.

Builder: D J PROJECTS PRIVATE LIMITED

D J Projects Private Limited has 2 registrations on RERA Karnataka, including OXYGEN and CONFIDENT MEADOWS. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if CONFIDENT MEADOWS is delayed beyond 30 Apr 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of CONFIDENT MEADOWS?

The registered promoter entity is D J PROJECTS PRIVATE LIMITED, a company as per the filing. Its CIN U15201DL2005PTC134979 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in CONFIDENT MEADOWS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against CONFIDENT MEADOWS?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at CONFIDENT MEADOWS?

The professionals named in the filing: Architect: Uma Nirmala. P; Engineer: CIVITECH DESIGNS. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CONFIDENT MEADOWS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CONFIDENT MEADOWS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CONFIDENT MEADOWS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.