Home / Browse projects / Bengaluru Urban, Karnataka / CONCORDE AURIGA

Registration approved No litigation declared Residential/Group Housing project

CONCORDE AURIGA

By CONCORDE HOUSING CORPORATION PVT LTD

RG-KA-16267 · RERA PRM/KA/RERA/1251/446/PR/190704/002647 · Last updated on RERA Karnataka portal: 14 Jan 2026

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka
  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
Jun 2026Possession promisedmoved 21 months from the original
15 of 15Construction stages doneevery applicable stage filed complete
77 of 501Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 80 documents Report an error

CONCORDE AURIGA is a Residential/Group Housing project by CONCORDE HOUSING CORPORATION PVT LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/190704/002647 on 4 Jul 2019. Possession is promised by 30 Jun 2026. The completion date has moved by 21 months from the original filing. 424 of the 501 units on this registration are recorded sold or booked, and 15 of 15 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameCONCORDE AURIGA
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/190704/002647
  • ReraGenie IDRG-KA-16267

Builder

  • NameCONCORDE HOUSING CORPORATION PVT LTD
  • Entity typeCompany
  • CINU70102KA2008PTC046886
  • Authorized SignatoryR G ANIL
  • DirectorR G ANIL
  • Other registrations10 more →
  • Declared earlier projects12 →

Key dates

this monthRegisteredJul 2019First promiseSep 2024Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on4 Jul 2019
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Sep 2024)
  • Buildings3 building records
  • Documents filed80 files

Current status

85%424 of 501 units booked
0.0%Of the estimated cost spent so far

Figures as on 14 Jan 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---1410141
B---1870187
C---1730173

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 15 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etcNot applicable
Plastering inside , outside & CeilingNot applicable
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Painting100%
Elevation work100%
Internal and External work including landscapes as per santioned drawings100%

Progress on shared amenities41

As on 14 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Internal Roads & FootpathsYes100%
Sewage and Drainage SystemYes100%
Parks & Tree plantingYes100%
Street LightingYes100%
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes100%
Water conservationYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Education/Health/Other public amenitiesYes100%
Electricity supply transformer and substationYes100%
Emergency Evacuation servicesYes100%
Storm water drainsYes100%
Use of renewable energyYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseYes100%
Community HallNoNot applicable
Outdoor Sports facilityYes100%
Indoor Sports facilityYes100%
Swimming PoolYes100%
GymYes100%
ParksNoNot applicable
Power BackupYes100%
GasNoNot applicable
Water and SanitationYes100%
Air Conditioning And incerntionNoNot applicable
StaircasesYes100%
LiftsYes100%
Staircases and Lift lobbies, corridor,lobbies, corridorYes100%
Fire escapesYes100%
Common entrance and exit for the building / common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areas and common storage spacesYes100%
Provision for lodging of management staff and security staffYes100%
Water conservation and renewable energyYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area17,213 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 181.13 cr
Spent of the estimate0.0%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 141.75 cr-
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 22.52 cr-
Payment of chargesRs 16.86 cr-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRohini C Kurwatti
EngineerYOGESH H P

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionSep 2024 → Jun 2025

No reason recorded in the filing

EX/PRM/KA/RERA/1251/446/PR/250704/002647Jun 2025 → Jun 2026

Reason as filed by the promoterAwaiting OC

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
00633/2026-CONCORDE HOUSING CORPORATION PVT LTD02/06/2026

Documents filed80

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/190704/002647 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4CC sd (1).pdf14 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Auriga Arch Certificate (3).pdf14 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Auriga Engn Certificate (2).pdf14 Jan 2026
Q3 2025-26 Water supply and sewage board14 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)14 Jan 2026
Q3 2025-26 KPTCL- BESCOM14 Jan 2026
Q3 2025-26 Fire and Safety14 Jan 2026
Q3 2025-26 Labour and Education Department14 Jan 2026
Q3 2025-26 Airport Authority of India14 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department14 Jan 2026
Notarised Affidavit Form - BFile: FORM B-AURIGA.pdf1 Jul 2025
CertificateFile: CERTIFICATE OF INCORPORATION.PDF-
Architect Certificate for Work Completion Schedule till DateFile: FORM EX-1 Architect Certificate.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: FORM-EX-5 Engineer Certificate.pdf-
CA Certificate for Funds UtilizationFile: Form 4.pdf-
Architect Certificate for Pending Work Completion Schedule.File: FORM EX-2 Architect Certificate.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: FORM-EX-6 Engineer Certificate.pdf-
CA Certificate for Funds required for Project CompletionFile: Form 4.pdf-
AffidavitFile: Form EX 7 - AFFIDAVIT_compressed.pdf-
Latest Encumbrance CertificateFile: E C_compressed.pdf-
Details Of Sold/ Un-sold UnitsFile: Concorde Auriga_Inventory.pdf-
Document 1File: Clearance certificate from Karnataka State Fire & Emergency services.pdf-
BBMP Licence & Plan Sanction Letter_compressed-
Site plan_compressed-
all plans comibned-compressed-
Proforma sale deed-
Proforma Sale agreement-
Sale deed & RTC of medihalli-
Section plan_compressed-
Site plan_compressed-
Allotment letter - Concorde Auriga-
Concorde Auriga Handout-
Auriga-Specifications-
EC_compressed-
AFFIDAVIT-
Affidavit cum declaration-
Katha Certificate and extract -
JDA of medihalli-
Conversion_order-
NOC_Fire-
NOC_AAI-
NOC_BESCOM-
NOC_BWSSB_compressed-
NOC_KSPCB_CFE_compressed-
NOC_MOEF_compressed-
NOC_BSNL-
Site plan_compressed-
Section plan-
Legal Opinion-
Balance Sheet 2017 - 2018File: balance sheet FY 2017-18-16.pdf-
Balance Sheet 2016 - 2017File: balance sheet FY 2016-17-17.pdf-
Balance Sheet 2015 - 2016File: BS 15-16 CHCPL-Financials-Final-39-39.pdf-
Audited Profit and Loss Statement 2017 - 2018File: P&L FY 2017-18-17.pdf-
Audited Profit and Loss Statement 2016 - 2017File: P& L FY 2016-17-18.pdf-
Audited Profit and Loss Statement 2015 - 2016File: P& L 15-16 CHCPL-Financials-Final-40-40.pdf-
Director's Report 2017 - 2018File: Directors Report CHCPL 17-18_compressed.pdf-
Director's Report 2016 - 2017File: Directors Report CHCPL 16-17_compressed.pdf-
Director's Report 2015 - 2016File: DIRECTOR RPT 15-16 CHCPL-Financials-Final-8-17-ilovepdf-compressed 67-ilovepdf-compressed.-
Cash Flow Statement 2017 - 2018File: CashFLow FY 2017-18-18-19.pdf-
Cash Flow Statement 2016 - 2017File: cashflow FY 2016-17-19-20.pdf-
Auditor's Report 2017 - 2018File: auditors FY 2017-18-1-8_compressed.pdf-
Auditor's Report 2016 - 2017File: auditors rpt FY 2016-17-2-10_compressed.pdf-
Auditor's Report 2015 - 2016File: AUDITORS RPT 15-16 CHCPL-Financials-Final-31-33.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: ITR ACK CHCPL 17-18.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: CHCPL ITR 2016-17.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR Acknowledgement.pdf-
From B-
Prospectus/BrochureFile: auriga-brochure.pdf-
Advertisement Copy 1File: A4 Size Poster_3_Auriga.jpg-
Tower Excel SheetFile: PRM_KA_RERA_1251_446_PR_190704_002647.xlsx-
Stability CertificateFile: Structural satibility certificate.pdf-
NOC issued by the Fire Force department after completion of workFile: KSPCB-CFO.pdf-
Occupancy CertificateFile: OCCUPANCY CERTIFICATE.pdf-
Consent for operation issued by KSPCBFile: KSPCB-CFO.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: Lift licences_compressed.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: Electrical Inspectorate.pdf-
Architect certificate for having completed the work(in format no 5)File: Form 5 Architect certificate.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: Form 4 CC Auriga.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: COMPLETION AFFIDAVIT-AURIGA.pdf-

How this compares with Bengaluru Urban

85%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 21 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep CONCORDE AURIGA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: CONCORDE HOUSING CORPORATION PVT LTD

Concorde Housing Corporation Pvt Ltd has 11 registrations on RERA Karnataka, including Concorde Mayfair and Concorde Spring Meadows. Its filings declare 12 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if CONCORDE AURIGA is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of CONCORDE AURIGA?

The registered promoter entity is CONCORDE HOUSING CORPORATION PVT LTD, a company as per the filing. Its CIN U70102KA2008PTC046886 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in CONCORDE AURIGA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against CONCORDE AURIGA?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at CONCORDE AURIGA?

The professionals named in the filing: Architect: Rohini C Kurwatti; Engineer: YOGESH H P. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CONCORDE AURIGA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CONCORDE AURIGA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CONCORDE AURIGA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.