Home / Browse projects / Bengaluru Urban, Karnataka / CoEvolve Misty Shores

Registration approved No litigation declared Residential/Group Housing project

CoEvolve Misty Shores

By CoEvolve East End Ventures LLP

RG-KA-38120 · RERA PRM/KA/RERA/1251/446/PR/150425/007664 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2029Possession promisedno revision filed
0 of 17Construction stages donefurthest along: Earth work and other leveling..., 80%
150 of 153Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 112 documents Report an error

CoEvolve Misty Shores is a Residential/Group Housing project by CoEvolve East End Ventures LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/150425/007664 on 15 Apr 2025. Possession is promised by 31 Dec 2029. 3 of the 153 units on this registration are recorded sold or booked, and 0 of 17 construction stages are filed complete.

At a glance

Project

  • NameCoEvolve Misty Shores
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/150425/007664
  • ReraGenie IDRG-KA-38120

Builder

  • NameCoEvolve East End Ventures LLP
  • Entity typePartnership Firm
  • LLPINACA-2418
  • GSTIN29AASFC5211D1ZJ
  • Authorized SignatoryKishore M

Key dates

this monthRegisteredApr 2025PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on15 Apr 2025
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed112 files

Current status

2%3 of 153 units booked
52.3%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
tower---1530153

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 17 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 80%.

Building: 20% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work80%
Foundation footing work80%
Upto Plinth Level80%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)50%
Retaining wall (All types)Not applicable
RCC or MS Framed structure30%
Masonry Construction9%
Plastering inside , outside & Ceiling5%
Joinery: Doors, Windows, Ventilators etc1%
Basic work of Water supply, Sanitary and Electrification1%
Dadoing, Skirting, Flooring, Tiles work (All types)1%
Railing and Grill fixing1%
Electrification, Water supply and Sanitary Finishing1%
Painting1%
Fire prevention and fire fighting fitting and fixture with network2%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities41

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes10%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes2%
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes10%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes60%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes0%
Community HallYes25%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
Communication RoomYes5%
StaircasesYes8%
LiftsYes7%
Corridor/LobbiesYes10%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes10%
BasementYes50%
TerraceYes0%
Outer WallYes5%
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership3

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners3
LandownerVillageDistrict
Jogee Bhar--
Jogee Bhar--
Jogee Bhar--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 111.49 cr
Cost incurredRs 58.33 cr
Spent of the estimate52.32%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 111.49 crRs 58.33 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectINDRAJIT SHARAD KEMBHAVI
EngineerChetan Megharaj Sidgiddi
Chartered AccountantB A M & Co

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed112

As listed on the registration, under the names the promoter filed them with; the newest 80 of 112 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/150425/007664 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM-4 CA QU Q2 26-27 Misty.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: FORM-5 Architects QU Q2 26-27 Misty- signed.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM-6 Engineers QU Q2 26-27 - Misty.pdf15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM-4 CA QU Q1 26-27 Misty.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: FORM-5 Architects QU Q1 26-27 Misty.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM-6 Engineers QU Q1 26-27 - Misty.pdf15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: 29 FORM-4 CA QU Q4 25-26 Misty-31032026.pdf14 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5, Architect - April-Signed Misty.pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Coevolve Misty Shores (1).pdf14 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM-4 CA QU Q3 25-26 Misty.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: FORM-5 Architects QU Q3 25-26 Misty.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM-6 Engineers QU Q3 25-26 - Misty.pdf15 Jan 2026
EC from 30/7/2024 to till date for Survey Number 77/5File: ECC-08042025-245602.pdf8 Apr 2025
Building LicenseFile: BBMP Approval Letter cc_BBMP_EoDB_CH_44605_24-25.pdf28 Mar 2025
BBMP Approved PlanFile: BBMP Approved Plan PRJ_5167_24-25.pdf28 Mar 2025
Amenities and CA detailsFile: CoEvolve Misty Shores - AMinities & Common Area Details.pdf28 Mar 2025
SpecificationsFile: CoEvolve Misty Shores - specs.pdf28 Mar 2025
ECOSTP technologyFile: ECOSTP - CoEvolve Misty Shores.pdf28 Mar 2025
Engineer certificateFile: CoEvolve Misty Shores Form 3.pdf28 Mar 2025
Architect CertificateFile: Form-2 CEMS.pdf28 Mar 2025
Guideline value calculation sheetFile: Guideline value calculation sheet.pdf28 Mar 2025
project section 3(1) notarized affidavitFile: Annexure 90 Notarized 3(1).pdf20 Mar 2025
AoS with Payment planFile: Co-Evolve Misty Shores - RERA Agreement to Sell with payment plan.pdf20 Mar 2025
ECsFile: EC.pdf20 Mar 2025
Notarised HAL NOCFile: Notarized HAL NOC.pdf20 Mar 2025
ECOSTP TechnologyFile: ECOSTP Technical Note - Misty Shores.pdf20 Mar 2025
Single Layout approval plan blue print in readable formatFile: BDA single plot layout.pdf26 Feb 2025
Single Layout approval order copyFile: BDA WO PRL 83.pdf26 Feb 2025
Allotment letterFile: Allottment Letter Template CoEvolve Misty Shores.pdf26 Feb 2025
BESCOM NOC recieptFile: BESCOM Challan.pdf26 Feb 2025
BWSSB NOC recieptFile: BWSSB fee reciept.pdf26 Feb 2025
Structural Stability certificateFile: CoEvolve Misty Shores - Structural Stability certificate.pdf26 Feb 2025
STP technologyFile: ECOSTP TECHNOLOGY REPORT - COEVOLVE FLORENZA.pdf26 Feb 2025
ADLR SketchFile: ADLR Survey Sketch.pdf26 Feb 2025
Village MapFile: Village Map.pdf26 Feb 2025
Advocate search reportFile: Advocate search report.pdf26 Feb 2025
Guideline Value reportFile: Guideline value.pdf26 Feb 2025
Title DeedFile: Title deed - sale deed.pdf26 Feb 2025
RTC 77/1AFile: RTC 77:1A.pdf26 Feb 2025
RTC 77/3File: RTC 77:3.pdf26 Feb 2025
RTC 77/5File: RTC 77:5.pdf26 Feb 2025
Project Engineer license certificateFile: Project Engineer - BBMP Registration Certificate.pdf26 Feb 2025
Draft Agreement to SellFile: Co-Evolve Misty Shores - RERA Agreement to Sell.pdf26 Feb 2025
HAL NOCFile: HAL NOC-BG-113_24.pdf26 Feb 2025
RTC, survey 77/3-
Mutation, survey 77/3-
Encumbrance Certificate, survey 77/3-
Conversion/Alienation Order, survey 77/3-
JDA, survey 77/3-
Khatha, survey 77/3-
RTC, survey 77/1A-
Mutation, survey 77/1A-
Encumbrance Certificate, survey 77/1A-
Conversion/Alienation Order, survey 77/1A-
JDA, survey 77/1A-
Khatha, survey 77/1A-
RTC, survey 77/5-
Mutation, survey 77/5-
Encumbrance Certificate, survey 77/5-
Conversion/Alienation Order, survey 77/5-
JDA, survey 77/5-
Khatha, survey 77/5-
Registration CertificateFile: CoEvolve East End-COI.pdf-
GST CertificateFile: GST Certificate-Coevolve eastend Ventures LLP.pdf-
Partnership DeedFile: EAST END LLP-Agreement.pdf-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: FORM 1 CA certificate for Misty shores.pdf-
Certificate issued by Architect Form 2File: Form-2 CEMS.pdf-
Certificate issued by Engineer Form 3File: CoEvolve Misty Shores Form 3.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Annexure 49.pdf-
Balance Sheet 2023 - 2024File: Financial statements NA.pdf-
Balance Sheet 2022 - 2023File: Financial statements NA.pdf-
Balance Sheet 2021 - 2022File: Financial statements NA.pdf-
Audited Profit and Loss Statement 2023 - 2024File: Financial statements NA.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Financial statements NA.pdf-

How this compares with Bengaluru Urban

2%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep CoEvolve Misty Shores on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: CoEvolve East End Ventures LLP

CoEvolve East End Ventures LLP has 1 registration on RERA Karnataka, including CoEvolve Misty Shores. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if CoEvolve Misty Shores is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of CoEvolve Misty Shores?

The registered promoter entity is CoEvolve East End Ventures LLP, a partnership firm as per the filing. Its LLPIN ACA-2418 and GSTIN 29AASFC5211D1ZJ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in CoEvolve Misty Shores?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at CoEvolve Misty Shores?

The professionals named in the filing: Architect: INDRAJIT SHARAD KEMBHAVI; Engineer: Chetan Megharaj Sidgiddi; Chartered Accountant: B A M & Co. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CoEvolve Misty Shores?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CoEvolve Misty Shores. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CoEvolve Misty Shores to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.