Registration approved Residential/Group Housing project

Cityville Valmark

By VALMARK DEVELOPERS PVT LTD

RG-KA-54993 · RERA PRM/KA/RERA/1251/310/PR/171222/000914

Source: official RERA Karnataka filing

Red flags

  • 3 complaints at RERA Karnataka
  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • Separate project account declared
Sep 2022Possession promisedmoved 9 months from the original
3Complaints at RERA Karnatakaon this registration
Jump to the 57 documents Report an error

Cityville Valmark is a Residential/Group Housing project by VALMARK DEVELOPERS PVT LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/171222/000914 on 22 Dec 2017. Possession is promised by 30 Sep 2022. The completion date has moved by 9 months from the original filing. 3 complaints are on record with the regulator.

At a glance

Project

  • NameCityville Valmark
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/171222/000914
  • ReraGenie IDRG-KA-54993

Builder

  • NameVALMARK DEVELOPERS PVT LTD
  • Entity typeCompany
  • CINU70102KA2006PTC040887
  • Authorized SignatoryMAHAVEER GULECHA

Key dates

this monthRegisteredDec 2017First promiseDec 2021Revised toSep 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on22 Dec 2017
  • Promised completion30 Sep 2022
  • Revised completionRevised to 30 Sep 2022 (originally 31 Dec 2021)
  • Buildings17 building records
  • Documents filed57 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block 3---404
Block 5---24024
Block 6---36036
Block 8---24024
Block 9---36036
Block 13---64064
Block 14---24024
BLOCK 17 (CLUB HOUSE)---404
Block 7---50050
Block 10---38038
Block 11---16016
Block 2---58058
Block 12---20020
Block 4---12012
Block 1---38038
Block 15---76076
Block 16---24024

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationNoNot applicable
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area112,602 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 540.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectV T Anand
EngineerManish A

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2021 → Sep 2022

No reason recorded in the filing

Complaints filed with RERA Karnataka3

Case no.ComplainantRespondentFiled
CMP/200910/0006543-VALMARK DEVELOPERS PVT LTD10/09/2020
CMP/220207/0008969-VALMARK DEVELOPERS PVT LTD07/02/2022
01210/2023-VALMARK DEVELOPERS PVT LTD03/08/2023

Documents filed57

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/171222/000914 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Certificate of incorporation VDPL.pdf-
VDPL commencement certificate-
BDA DP approved - 07-10-15-
BDA DP approved - 07-10-15-
CV SALE DEED-
CV SALE & CONSTRUCTION AGREEMENT DRAFT-
DEVELOPMENT PLAN 544 units-
approved section building plan-
Sale deed-
approved section building plan-
DEVELOPMENT PLAN 544 units-
Allotment cum cost break up letter draft-
Cityville Leaflet-
CITYVILLE - LIST OF NOCs-
CV SPECIFICATIONS-
EC merged and compressed-
Khata Certificate-
jda-
Mutation-
BWSSB NOC (05-11-14)-
KSPCB CFE-
MOEF cityville_Compressed_Compressed-
Title report-
Balance Sheet 2015 - 2016File: Balancesheet2016.pdf-
Balance Sheet 2014 - 2015File: BalanceSheet 2015.pdf-
Balance Sheet 2013 - 2014File: BalanceSheet2014.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Profit & Loss 2016.pdf-
Audited Profit and Loss Statement 2014 - 2015File: Profit&Loss 2015.pdf-
Audited Profit and Loss Statement 2013 - 2014File: Profit&Loss 2014.pdf-
Director's Report 2015 - 2016File: VDPL-DIR REP 2016.pdf-
Director's Report 2014 - 2015File: VDPL-DIR REP 2015.pdf-
Director's Report 2013 - 2014File: VDPL-DIR REP 2014.pdf-
Cash Flow Statement 2015 - 2016File: CashFlow2016.pdf-
Cash Flow Statement 2014 - 2015File: CashFlow2015.pdf-
Auditor's Report 2015 - 2016File: Auditor's report 2016.pdf-
Auditor's Report 2014 - 2015File: Auditor's report 2015.pdf-
Auditor's Report 2013 - 2014File: Auditor's report 2014.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR 2016.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: ITR 2015.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: ITR 2014.pdf-
Declaration-
Prospectus/BrochureFile: Cityville ebrochure.pdf-
Advertisement Copy 1File: CityVille ad.jpg-
Tower Excel SheetFile: PRM_KA_RERA_1251_310_PR_171222_000914.xlsx-
Loan raised documentFile: loanDetails.xlsx-
Stability CertificateFile: Structural Stability certificate.pdf-
Occupancy CertificateFile: Partial OC copy - 20-07-2022.pdf-
Consent for operation issued by KSPCBFile: CITYVILLE KSPCB NOC CONSENT.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: CV lifts.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: BESCOM Power Sanction Letter City Ville.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: VDPL BWSSB NOC 051114.pdf-
Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: CV EXTERNAL DEVELOPMENT.jpg-
Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: common area note.pdf-
Details of undivided share of land handed over to the association of allotteesFile: common area note.pdf-
Architect certificate for having completed the work(in format no 5)File: Architect's Project Completion certificate for PH 1.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: RERA Form 4 CA Closure CV.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit cum declaration VDPL.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Cityville Valmark on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: VALMARK DEVELOPERS PVT LTD

VALMARK DEVELOPERS PVT LTD has 1 registration on RERA Karnataka, including Cityville Valmark. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Cityville Valmark is delayed beyond 30 Sep 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Cityville Valmark?

The registered promoter entity is VALMARK DEVELOPERS PVT LTD, a company as per the filing. Its CIN U70102KA2006PTC040887 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Cityville Valmark?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Cityville Valmark?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Cityville Valmark?

The professionals named in the filing: Architect: V T Anand; Engineer: Manish A. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Cityville Valmark?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Cityville Valmark. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Cityville Valmark to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.