CITILIGHTS SEASONS PHASE - II

By CITILIGHTS ESTATES PVT LTD

RG-KA-83964 · RERA PRM/KA/RERA/1251/308/PR/180227/001898

Source: official RERA Karnataka filing

Red flags

  • 2 complaints at RERA Karnataka
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Dec 2019Possession promisedmoved 12 months from the original
2Complaints at RERA Karnatakaon this registration
Jump to the 52 documents Report an error

CITILIGHTS SEASONS PHASE - II is a Plotted Development project by CITILIGHTS ESTATES PVT LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/180227/001898 on 27 Feb 2018. Possession is promised by 31 Dec 2019. The completion date has moved by 12 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameCITILIGHTS SEASONS PHASE - II
  • TypePlotted Development
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/308/PR/180227/001898
  • ReraGenie IDRG-KA-83964

Builder

  • NameCITILIGHTS ESTATES PVT LTD
  • Entity typeCompany
  • Authorized SignatoryMr.Badar Abbas Karimi
  • DirectorsMr.Salim Karimi, Ms.Rukhsana Karimi, Ms.Jannki Mithaiwala

Key dates

this monthRegisteredFeb 2018First promiseDec 2018Revised toDec 2019

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on27 Feb 2018
  • Promised completion31 Dec 2019
  • Revised completionRevised to 31 Dec 2019 (originally 31 Dec 2018)
  • BuildingsNot stated in filing
  • Documents filed52 files

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area41,884 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 5.41 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMR.JAYANTH
EngineerMR.VENKATESH BABU REDDY

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/308/PR/191014/001898Dec 2018 → Dec 2019

Reason as filed by the promoterDelay in Approvals

Complaints filed with RERA Karnataka2

Case no.ComplainantRespondentFiled
CMP/221215/0010462-CITILIGHTS ESTATES PVT LTD15/12/2022
00147/2023-CITILIGHTS ESTATES PVT LTD01/02/2023

Documents filed52

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/180227/001898 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Company Certificate.jpg-
Architect Certificate for Work Completion Schedule till DateFile: ARC Status of work.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Eng Status of work.pdf-
CA Certificate for Funds UtilizationFile: CA fund utilisation.pdf-
Architect Certificate for Pending Work Completion Schedule.File: ARC Pending work.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Eng Pending work.pdf-
CA Certificate for Funds required for Project CompletionFile: CA funds Required.pdf-
AffidavitFile: Form - B.pdf-
Latest Encumbrance Certificate-
Consent letter from 2/3rd of AllotteesFile: Consent of Allottees.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
Document 1File: affidavit.pdf-
Document 2File: Utilised amount clarification.pdf-
Document 3File: Letter anekal Planning Authority ltr.pdf-
C_CC-
Approved Layout plan-
Approved Layout plan-
O_Proforma AGREEMENT FOR SALE-
O_Proforma AGREEMENT FOR SALE-
Sale Deed-
Sanction plan-Phase II-
B_Ec-
Allotment letter-
C_CC-
L_PRoject Specification-
B_Ec-
Khatha full-pdf-
land doc-
Conversion copy -Phase II final-
Balance Sheet 2015 - 2016File: Citilights Estates Pvt Ltd Balance Sheet 2015-16.pdf-
Balance Sheet 2014 - 2015File: Citilights Estates Pvt Ltd Balance Sheet 2014-15.pdf-
Balance Sheet 2013 - 2014File: Citilights Estate Pvt Ltd Balance Sheet 2013-14.pdf-
Audited Profit and Loss Statement 2015 - 2016File: 2015-16 PL.jpg-
Audited Profit and Loss Statement 2014 - 2015File: Citilights Estates Pvt Ltd Profit & Loss account 2014-15.pdf-
Audited Profit and Loss Statement 2013 - 2014File: Citilights Estates Pvt Ltd Auditors Report 2013-14.pdf-
Director's Report 2015 - 2016File: Citilights Estates Pvt Ltd Directors Report 2015-16.pdf-
Director's Report 2014 - 2015File: Citilights Estates Pvt Ltd Directors Report 2014-15.pdf-
Director's Report 2013 - 2014File: Citilights Estates Pvt Ltd Directors Report 2013-14.pdf-
Cash Flow Statement 2015 - 2016File: Citilights Estates Pvt Ltd Cash Flow Statement 2015-16.pdf-
Cash Flow Statement 2014 - 2015File: Citilights Estates Pvt Ltd Cash FlowStatement 2014-15.pdf-
Auditor's Report 2015 - 2016File: Citilights Estates Pvt Ltd Auditors report 2015-16.pdf-
Auditor's Report 2014 - 2015File: Citilights Estates Pvt Ltd Audit Report 2014-15.pdf-
Auditor's Report 2013 - 2014File: Citilights Estates Pvt Ltd Auditors Report 2013-14.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: IT Return Ack - 15 - 16.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: IT Return Ack 14 - 15.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: IT Return Ack - 13 - 14.pdf-
M_form B-min-
Plot Excel SheetFile: PRM_KA_RERA_1251_308_PR_180227_001898 (2).xlsx-
Occupancy CertificateFile: 04_11_2015_RELINQUISHMENT DEED.pdf-
Completion certificateFile: 20_11_2019_Final release order.pdf-
Registered Agreement of SaleFile: 28_06_2016_AOS.pdf-
Registered conveyance deed for an individual unitFile: 13_04_2017_Sale Deed.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep CITILIGHTS SEASONS PHASE - II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: CITILIGHTS ESTATES PVT LTD

CITILIGHTS ESTATES PVT LTD has 1 registration on RERA Karnataka, including CITILIGHTS SEASONS PHASE - II. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if CITILIGHTS SEASONS PHASE - II is delayed beyond 31 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of CITILIGHTS SEASONS PHASE - II?

The registered promoter entity is CITILIGHTS ESTATES PVT LTD, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in CITILIGHTS SEASONS PHASE - II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against CITILIGHTS SEASONS PHASE - II?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at CITILIGHTS SEASONS PHASE - II?

The professionals named in the filing: Architect: MR.JAYANTH; Engineer: MR.VENKATESH BABU REDDY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CITILIGHTS SEASONS PHASE - II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CITILIGHTS SEASONS PHASE - II. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CITILIGHTS SEASONS PHASE - II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.