Home / Browse projects / Bengaluru Urban, Karnataka / Century Xenon

Registration approved No litigation declared Residential/Group Housing project

Century Xenon

By Century Real Estate Holdings Private Limited

RG-KA-24690 · RERA PRM/KA/RERA/1251/309/PR/140923/006265 · Last updated on RERA Karnataka portal: 1 Sep 2023

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2024Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 117 documents Report an error

Century Xenon is a Residential/Group Housing project by Century Real Estate Holdings Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/140923/006265 on 14 Sep 2023. Possession is promised by 31 Dec 2024.

At a glance

Project

  • NameCentury Xenon
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
    • 560092
  • Pincode560092
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/140923/006265
  • ReraGenie IDRG-KA-24690

Builder

  • NameCentury Real Estate Holdings Private Limited
  • Entity typeCompany
  • CINU70101KA2007PTC042078
  • GSTIN29AADCC0651M1ZJ
  • Authorized SignatoryMahesh Prabhu
  • Executive DirectorMahesh Prabhu
  • DirectorP Ravindra Pai
  • Project HeadNeelkanth Patil
  • Other registrations2 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredSep 2023PromisedDec 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on14 Sep 2023
  • Promised completion31 Dec 2024
  • Revised completionNone
  • Buildings2 building records
  • Documents filed117 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower A---24024
Tower B---24024

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 1 Sep 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 1 Sep 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Solid waste management and disposalYes-
Emergency Evacuation servicesYes-
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyYes-
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingYes-
Street LightingYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesYes-
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,635 sq m
Named landowners2
LandownerVillageDistrict
Century Sheltors Developers Private Limited--
Century Sheltors Developers Private Limited--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 78.50 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 78.50 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectChandrashekar R
EngineerSwaroop Devaiah KL
Chartered AccountantSugnana Kumar H

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed117

As listed on the registration, under the names the promoter filed them with; the newest 80 of 117 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/140923/006265 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
RERA Reply 01092023File: RERA Reply 01092023.pdf1 Sep 2023
Annexure R27 - Clarification on BESCOM NoCFile: Annexure R27 - Clarification on BESCOM NoC.pdf1 Sep 2023
Annexure R28 - Clarification on BWSSB NoCFile: Annexure R28 - Clarification on BWSSB NoC.pdf1 Sep 2023
Annexure R24 - Cost Break-upFile: Annexure R24 - Cost Break-up.pdf1 Sep 2023
Annexure R29 - Clarification on Land CostFile: Annexure R29 - Clarification on Land Cost.pdf1 Sep 2023
RERA Reply 19082023File: RERA Reply 19082023.pdf19 Aug 2023
Annexure R1 - Financials 2019-20File: Annexure R1 - Financials 2019-20_compressed.pdf19 Aug 2023
Annexure R2 - Financials 2020-21File: Annexure R2 - Financials 2020-21_compressed.pdf19 Aug 2023
Annexure R3 - Financials 2021-22File: Annexure R3 - Financials 2021-22.pdf19 Aug 2023
Annexure R4 - Bank Confirmation & StatementFile: Annexure R4 - Bank Confirmation & Statement.pdf19 Aug 2023
Annexure R5 - Proposal for Credit FacilityFile: Annexure R5 - Proposal for Credit Facility.pdf19 Aug 2023
Annexure R6 - Reg1 CA (Reg)File: Annexure R6 - Reg1 CA (Reg).pdf19 Aug 2023
Annexure R7 - Compromise Petition OrderFile: Annexure R7 - Compromise Petition Order.PDF19 Aug 2023
Annexure R8 - Updated ECFile: Annexure R8 - Updated EC.pdf19 Aug 2023
Annexure R9 - Guidance ValueFile: Annexure R9 - Guidance Value.pdf19 Aug 2023
Annexure R10 - DPFile: Annexure R10 - DP.pdf19 Aug 2023
Annexure R11 - Phasewise DemarcationFile: Annexure R11 - Phasewise Demarcation.pdf19 Aug 2023
Annexure R12 - SEIAA NoC & ExtensionFile: Annexure R12 - SEIAA NoC & Extension.pdf19 Aug 2023
Annexure R13 - Site DrawingFile: Annexure R13 - Site Drawing_compressed.pdf19 Aug 2023
Annexure R14 - Amalgamation KathaFile: Annexure R14 - Amalgamation Katha.pdf19 Aug 2023
Annexure R15 - CDP MapFile: Annexure R15 - CDP Map.pdf19 Aug 2023
Annexure R16 - Village MapFile: Annexure R16 - Village Map.pdf19 Aug 2023
Annexure R17 - Relinquishment DeedFile: Annexure R17 - Relinquishment Deed.pdf19 Aug 2023
Annexure R18 - Commencement CertificateFile: Annexure R18 - Commencement Certificate.pdf19 Aug 2023
Annexure R19 - Engg LicenseFile: Annexure R19 - Engg License.pdf19 Aug 2023
Annexure R20 - STP drawingsFile: Annexure R20 - STP drawings.pdf19 Aug 2023
Annexure R21 - BWSSB NOCFile: Annexure R21 - BWSSB NOC.pdf19 Aug 2023
Annexure R22 - Fire NoCFile: Annexure R22 - Fire NoC.pdf19 Aug 2023
Annexure R23 - KSPCB NoCFile: Annexure R23 - KSPCB NoC.pdf19 Aug 2023
Annexure R24 - Cost Break-upFile: Annexure R24 - Cost Break-up.pdf19 Aug 2023
Annexure R25 - Form - 3 Engineer (Reg)File: Annexure R25 - Form - 3 Engineer (Reg).pdf19 Aug 2023
Annexure R26 - Agreement for SaleFile: Annexure R26 - Agreement for Sale.pdf19 Aug 2023
RTC, survey 108/1-
Mutation, survey 108/1-
Encumbrance Certificate, survey 108/1-
Conversion/Alienation Order, survey 108/1-
Sale/Title/Gift Deed, survey 108/1-
JDA, survey 108/1-
Khatha, survey 108/1-
RTC, survey 116/3-
Mutation, survey 116/3-
Encumbrance Certificate, survey 116/3-
Conversion/Alienation Order, survey 116/3-
Sale/Title/Gift Deed, survey 116/3-
JDA, survey 116/3-
Khatha, survey 116/3-
Registration CertificateFile: Annexure 1 CoI.pdf-
Organization StructureFile: Annexure 11 Orgination Structure.pdf-
Certificate issued by CA Form 1File: Annexure 56 & 57 Form - Reg1 CA (PR).pdf-
Certificate issued by Architect Form 2File: Annexure 59 Form - 2 Architect (PR).pdf-
Certificate issued by Engineer Form 3File: Annexure 58 Form - 3 Engineer (PR).pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Annexure 45 No Litigation Affidavit.pdf-
Certificate from Chartered AccountFile: Annexure 56 & 57 Form - Reg1 CA (PR).pdf-
Balance Sheet 2021 - 2022File: Balance Sheet 2022.pdf-
Balance Sheet 2020 - 2021File: Balance Sheet 2021.pdf-
Balance Sheet 2019 - 2020File: Balance Sheet 2020.pdf-
Audited Profit and Loss Statement 2021 - 2022File: Profit and Loss Account 2022.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Profit and Loss Account 2021.pdf-
Audited Profit and Loss Statement 2019 - 2020File: Profit and Loss Accoount 2020.pdf-
Director's Report 2021 - 2022File: CREH Board Report 2022 Final Print_compressed.pdf-
Director's Report 2020 - 2021File: CREH Board Report 2021 Final Print_compressed.pdf-
Director's Report 2019 - 2020File: CREH Board Report 2020_compressed.pdf-
Cash Flow Statement 2021 - 2022File: Statement of Cash Flowas 2022.pdf-
Cash Flow Statement 2020 - 2021File: Statement of Cash Flow 2021.pdf-
Auditor's Report 2021 - 2022File: Audit Report CREH 2022_compressed.pdf-
Auditor's Report 2020 - 2021File: CREH Audit Report 20-21_compressed.pdf-
Auditor's Report 2019 - 2020File: CREH audit Report FY 2019 20 (1).pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR-6_Ack_FY 2021-22_CREH.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR-6_Ack_FY 2020-21_CREH.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: ITR-6_Ack_FY 2019-20_CREH.pdf-
Annexure 67 - Plan Approval Letter-
Annexure 68 BESCOM-
Annexure 69 BWSSB-
Annexure 70 Site Plan-
Annexure 71 Building Plan-
Annexure 72 Site Plan-
Annexure 73 Section & Elevation-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Century Xenon on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmCentury XenonOther 21Dot size: filed unitsN

Filed coordinates, straight-line distance. 21 registered projects within 2 km.

Builder: Century Real Estate Holdings Private Limited

Century Real Estate Holdings Private Limited has 3 registrations on RERA Karnataka, including Century Xenon and Century Breeze. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Century Xenon is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Century Xenon?

The registered promoter entity is Century Real Estate Holdings Private Limited, a company as per the filing. Its CIN U70101KA2007PTC042078 and GSTIN 29AADCC0651M1ZJ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Century Xenon?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Century Xenon?

The professionals named in the filing: Architect: Chandrashekar R; Engineer: Swaroop Devaiah KL; Chartered Accountant: Sugnana Kumar H. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Century Xenon?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Century Xenon. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Century Xenon to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.