Century Regalia (Project 2) is a Residential/Group Housing project by Suruchi Properties Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/150325/007586 on 15 Mar 2025. Possession is promised by 28 Feb 2030. 80 of the 128 units on this registration are recorded sold or booked, and 2 of 18 construction stages are filed complete.
At a glance
Project
- NameCentury Regalia (Project 2)
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- 560075
- Pincode560075
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/446/PR/150325/007586
- ReraGenie IDRG-KA-52154
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on15 Mar 2025
- Promised completion28 Feb 2030
- Revised completionNone
- Buildings1 building record
- Documents filed220 files
Current status
Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| B | - | - | - | 128 | 0 | 128 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 18 construction stages are filed complete. The stage furthest along is Retaining wall (All types), at 70%.
Building: 18% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 45% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 0% |
| Retaining wall (All types) | 70% |
| RCC or MS Framed structure | 0% |
| Masonry Construction | 0% |
| Plastering inside , outside & Ceiling | 0% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | 0% |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | Yes | 0% |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | Yes | 0% |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | Yes | 0% |
| Community Hall | Yes | 0% |
| Outdoor Sports facility | Yes | 0% |
| Indoor Sports facility | Yes | 0% |
| Swimming Pool | Yes | 0% |
| Gym | Yes | 0% |
| Parks | Yes | 0% |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 10% |
| Lifts | Yes | 10% |
| Corridor/Lobbies | Yes | 10% |
| Fire escapes | Yes | 0% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 0% |
| Basement | Yes | 100% |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | 0% |
| Common storage spaces | No | Not applicable |
Land and ownership20
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Suruchi Properties Private Limited | - | - |
| Suruchi Properties Private Limited | - | - |
| Suruchi Properties Private Limited | - | - |
| Suruchi Properties Private Limited | - | - |
| Suruchi Properties Private Limited | - | - |
| Suruchi Properties Private Limited | - | - |
| Suruchi Properties Private Limited | - | - |
| Suruchi Properties Private Limited | - | - |
| Suruchi Properties Private Limited | - | - |
| Suruchi Properties Private Limited | - | - |
| M Narayanaswamy | - | - |
| M Babu | - | - |
| M Nagaraj | - | - |
| M Srinivas | - | - |
| Suruchi Properties Private Limited | - | - |
| Suruchi Properties Private Limited | - | - |
| Suruchi Properties Private Limited | - | - |
| Suruchi Properties Private Limited | - | - |
| Suruchi Properties Private Limited | - | - |
| Suruchi Properties Private Limited | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for construction | Rs 250.00 cr | Rs 133.84 cr |
| Estimated Cost of Construction as certified by Engineer | Rs 140.87 cr | Rs 39.66 cr |
| On-site expenditure-Salaries of workers | Rs 25.16 cr | - |
| On-site expenditure-Site Overhead | Rs 3.40 cr | - |
| On-site expenditure-Consultants Fees | Rs 2.07 cr | - |
| On-site expenditure-Cost Of Services(Water, Electricity, Sewage) | Rs 1.68 cr | - |
| Payment of taxes | Rs 20.80 lakh | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Chandrashekar R |
| Engineer | VARA PRASAD REDDY S |
| Chartered Accountant | Sugnana Kumar H |
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 840 | The High Court of Karnataka | - |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed220
As listed on the registration, under the names the promoter filed them with; the newest 80 of 220 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/150325/007586 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Regalia2 Form - 4 CA (Q22026-27).pdf | 14 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Regalia2 Form 5 - Architect (Q22026-27).pdf | 14 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Regalia2 Form 6 - Engineer (Q22026-27).pdf | 14 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 14 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 14 Oct 2026 |
| Q2 2026-27 KSPCB- MOEF (Above 50 Acres) | 14 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 14 Oct 2026 |
| Q2 2026-27 Fire and Safety | 14 Oct 2026 |
| Q2 2026-27 Airport Authority of India | 14 Oct 2026 |
| Q2 2026-27 BSNL/Telecommunication Department | 14 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Regalia2 Form - 4 CA (Q12026-27).pdf | 13 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Regalia2 Form 5 - Architect (Q12026-27).pdf | 13 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Regalia2 Form 6 - Engineer (Q12026-27).pdf | 13 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 13 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 13 Jul 2026 |
| Q1 2026-27 KSPCB- MOEF (Above 50 Acres) | 13 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 13 Jul 2026 |
| Q1 2026-27 Fire and Safety | 13 Jul 2026 |
| Q1 2026-27 Airport Authority of India | 13 Jul 2026 |
| Q1 2026-27 BSNL/Telecommunication Department | 13 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Regalia2 Form - 4 CA (Q42025-26).pdf | 14 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Regalia2 Form 5 - Architect (Q42026).pdf | 14 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Regalia2 Form 6 - Engineer (Q42026).pdf | 14 Apr 2026 |
| Q4 2025-26 Water supply and sewage board | 14 Apr 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 14 Apr 2026 |
| Q4 2025-26 KSPCB- MOEF (Above 50 Acres) | 14 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 14 Apr 2026 |
| Q4 2025-26 Fire and Safety | 14 Apr 2026 |
| Q4 2025-26 Airport Authority of India | 14 Apr 2026 |
| Q4 2025-26 BSNL/Telecommunication Department | 14 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Regalia2 Form - 4 CA (Q32025-26).pdf | 10 Feb 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Regalia2 Form 5 - Architect (Q32026).pdf | 10 Feb 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Regalia2 Form 6 - Engineer (Q32026).pdf | 10 Feb 2026 |
| Q3 2025-26 Water supply and sewage board | 10 Feb 2026 |
| Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 10 Feb 2026 |
| Q3 2025-26 KSPCB- MOEF (Above 50 Acres) | 10 Feb 2026 |
| Q3 2025-26 KPTCL- BESCOM | 10 Feb 2026 |
| Q3 2025-26 Fire and Safety | 10 Feb 2026 |
| Q3 2025-26 Airport Authority of India | 10 Feb 2026 |
| Q3 2025-26 BSNL/Telecommunication Department | 10 Feb 2026 |
| RERA Reply 06032025File: RERA Reply 06032025.pdf | 6 Mar 2025 |
| Annexure R20 Affidavit and Undertaking on LitigationFile: Annexure R20 Affidavit and Undertaking on Litigation.pdf | 6 Mar 2025 |
| RERA Reply 01032025File: RERA Reply 01032025.pdf | 1 Mar 2025 |
| Annexure R1 Confirmation of Borrowing not yet disbursedFile: Annexure R1 Confirmation of Borrowing not yet disbursed.pdf | 1 Mar 2025 |
| Annexure R2 Sources of FundsFile: Annexure R2 Sources of Funds.pdf | 1 Mar 2025 |
| Annexure R3 Audited Annual Report 2023-24File: Annexure R3 Audited Annual Report 2023-24.pdf | 1 Mar 2025 |
| Annexure R4 Clarification on RTCFile: Annexure R4 Clarification on RTC.pdf | 1 Mar 2025 |
| Annexure R5 Updated ECFile: Annexure R5 Updated EC.pdf | 1 Mar 2025 |
| Annexure R6 Conversion Non ApplicabilityFile: Annexure R6 Conversion Non Applicability.pdf | 1 Mar 2025 |
| Annexure R7 Amenities & Common Area DetailsFile: Annexure R7 Amenities & Common Area Details.pdf | 1 Mar 2025 |
| Annexure R8 Cost CertificateFile: Annexure R8 Cost Certificate.pdf | 1 Mar 2025 |
| Annexure R9 Project SpecificationFile: Annexure R9 Project Specification.pdf | 1 Mar 2025 |
| Annexure R10 ATS with ClarificationFile: Annexure R10 ATS with Clarification.pdf | 1 Mar 2025 |
| Annexure R11 BESCOM ReceiptFile: Annexure R11 BESCOM Receipt.pdf | 1 Mar 2025 |
| Annexure R12 BWSSB NoC & ReceiptFile: Annexure R12 BWSSB NoC & Receipt.pdf | 1 Mar 2025 |
| Annexure R13 STPFile: Annexure R13 STP.pdf | 1 Mar 2025 |
| Annexure R14 Structural CertificateFile: Annexure R14 Structural Certificate.pdf | 1 Mar 2025 |
| Annexure R15 Development PlanFile: Annexure R15 Layout (Development Plan).pdf | 1 Mar 2025 |
| Annexure R16 Work Order (Development Plan)File: Annexure R16 Work Order (Development Plan).pdf | 1 Mar 2025 |
| Annexure R17 Village MapFile: Annexure R17 Village Map.pdf | 1 Mar 2025 |
| Annexure R18 ADLR SketchFile: Annexure R18 ADLR Sketch.pdf | 1 Mar 2025 |
| Annexure R19 SEIAA NoCFile: Annexure R19 SEIAA NoC.pdf | 1 Mar 2025 |
| RTC, survey Sy No. 146/1 | - |
| Mutation, survey Sy No. 146/1 | - |
| Encumbrance Certificate, survey Sy No. 146/1 | - |
| Sale/Title/Gift Deed, survey Sy No. 146/1 | - |
| Khatha, survey Sy No. 146/1 | - |
| RTC, survey Sy No. 147/1(P) | - |
| Mutation, survey Sy No. 147/1(P) | - |
| Encumbrance Certificate, survey Sy No. 147/1(P) | - |
| Sale/Title/Gift Deed, survey Sy No. 147/1(P) | - |
| Khatha, survey Sy No. 147/1(P) | - |
| RTC, survey Sy No. 147/2(P) | - |
| Mutation, survey Sy No. 147/2(P) | - |
| Encumbrance Certificate, survey Sy No. 147/2(P) | - |
| Sale/Title/Gift Deed, survey Sy No. 147/2(P) | - |
| Khatha, survey Sy No. 147/2(P) | - |
| RTC, survey Sy No. 155/1A (Part 1) | - |
| Mutation, survey Sy No. 155/1A (Part 1) | - |
| Encumbrance Certificate, survey Sy No. 155/1A (Part 1) | - |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| CENTURY REGALIA (PROJECT 1) | Sy No. 146/2, 146/3A, 146/3B, 143/3, 148 of Kodihalli Village, Varthur Hobli, Bangalore | Ongoing | Apr 2029 | Not due yet |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Century Regalia (Project 2) on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 7 registered projects within 2 km.
SRI LAKSHMI VALLABHA VISTA
SRI LAKSHMI VALLABHA BUILDERS LLP
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
See every Bengaluru Urban project, with the district possession charts
Builder: Suruchi Properties Private Limited
Suruchi Properties Private Limited has 2 registrations on RERA Karnataka, including Century Regalia (Project 2) and Century Regalia (Project 1). Its filings declare 1 earlier project, none of them declared completed. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Century Regalia (Project 2) is delayed beyond 28 Feb 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Century Regalia (Project 2)?
The registered promoter entity is Suruchi Properties Private Limited, a company as per the filing. Its CIN U45201KA2003PTC064723 and GSTIN 29AAHCS8877M1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Century Regalia (Project 2)?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Century Regalia (Project 2)?
The professionals named in the filing: Architect: Chandrashekar R; Engineer: VARA PRASAD REDDY S; Chartered Accountant: Sugnana Kumar H. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Century Regalia (Project 2)?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback