Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Century Kindle Phase 1 is a Residential/Group Housing project by Hebbal Properties Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/200326/008542 on 20 Mar 2026. Possession is promised by 14 Mar 2031. 336 of the 458 units on this registration are recorded sold or booked, and 3 of 18 construction stages are filed complete.
At a glance
Project
- NameCentury Kindle Phase 1
- TypeResidential/Group Housing
- Location
- Bengaluru North
- Bengaluru Urban
- 560064
- Pincode560064
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/309/PR/200326/008542
- ReraGenie IDRG-KA-32107
Builder
- NameHebbal Properties Private Limited
- Entity typeCompany
- CINU70109KA2021PTC145179
- GSTIN29AAFCH6957D1ZA
- Authorized SignatoryMahesh Prabhu
- Non-executive directorP Ravindra Pai
- DirectorsP Ravindra Pai, P Ashwin Pai
- Project HeadNeelkanth Patil
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on20 Mar 2026
- Promised completion14 Mar 2031
- Revised completionNone
- Buildings2 building records
- Documents filed128 files
Current status
Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tower 1 | - | - | - | 229 | 0 | 229 |
| Tower 2 | - | - | - | 229 | 0 | 229 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 18 construction stages are filed complete. The stage furthest along is Sub-structure flooring (Parking Floor, at 15%.
Building: 18% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 15% |
| Retaining wall (All types) | 15% |
| RCC or MS Framed structure | 0% |
| Masonry Construction | 0% |
| Plastering inside , outside & Ceiling | 0% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | 0% |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | Yes | 0% |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | Yes | 0% |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | Yes | 0% |
| Community Hall | Yes | 0% |
| Outdoor Sports facility | Yes | 0% |
| Indoor Sports facility | Yes | 0% |
| Swimming Pool | Yes | 0% |
| Gym | Yes | 0% |
| Parks | Yes | 0% |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 0% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | Yes | 0% |
| Fire escapes | Yes | 0% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 0% |
| Basement | Yes | 0% |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | 0% |
| Common storage spaces | No | Not applicable |
Land and ownership5
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Hebbal Properties Private Limited | - | - |
| Hebbal Properties Private Limited | - | - |
| Hebbal Properties Private Limited | - | - |
| Hebbal Properties Private Limited | - | - |
| Hebbal Properties Private Limited | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC) | Rs 270.00 cr | Rs 65.78 cr |
| Estimated Cost of Construction as certified by Engineer | Rs 154.79 cr | Rs 47.99 cr |
| On-site expenditure-Salaries of workers | Rs 89.30 cr | - |
| On-site expenditure-Site Overhead | Rs 44.65 cr | - |
| On-site expenditure-Cost Of Services(Water, Electricity, Sewage) | Rs 5.95 cr | - |
| On-site expenditure-Consultants Fees | Rs 2.98 cr | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Chandrashekar R |
| Engineer | Swaroop Devaiah K L |
| Chartered Accountant | Sugnana Kumar H |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed128
As listed on the registration, under the names the promoter filed them with; the newest 80 of 128 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/200326/008542 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Kindle1 Form - 4 CA (Q2 2026-27).pdf | 13 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Kindle1 Form 5 - Architect (Q2 2026-27).pdf | 13 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Kindle1 Form 6 - Engineer (Q2 2026-27).pdf | 13 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 13 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 13 Oct 2026 |
| Q2 2026-27 KSPCB- MOEF (Above 50 Acres) | 13 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 13 Oct 2026 |
| Q2 2026-27 Fire and Safety | 13 Oct 2026 |
| Q2 2026-27 Airport Authority of India | 13 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Kindle1 Form - 4 CA (Q1 2026-27).pdf | 14 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Kindle1 Form 5 - Architect (Q1 2026-27).pdf | 14 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Kindle1 Form 6 - Engineer (Q1 2026-27).pdf | 14 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 14 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 14 Jul 2026 |
| Q1 2026-27 KSPCB- MOEF (Above 50 Acres) | 14 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 14 Jul 2026 |
| Q1 2026-27 Fire and Safety | 14 Jul 2026 |
| Q1 2026-27 Airport Authority of India | 14 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Kindle1 Form - 4 CA (Q42026).pdf | 30 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Kindle1 Form 5 - Architect (Q42026).pdf | 30 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Kindle1 Form 6 - Engineer (Q42026).pdf | 30 Apr 2026 |
| Q4 2025-26 Water supply and sewage board | 30 Apr 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 30 Apr 2026 |
| Q4 2025-26 KSPCB- MOEF (Above 50 Acres) | 30 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 30 Apr 2026 |
| Q4 2025-26 Fire and Safety | 30 Apr 2026 |
| Q4 2025-26 Airport Authority of India | 30 Apr 2026 |
| Structural engineer certificate and licenseFile: Annexure R1 Structural engineer license and certificate.pdf | 18 Mar 2026 |
| Affidavit for BESCOM NOCFile: Annexure R2 Affidavit for BESCOM NOC.pdf | 18 Mar 2026 |
| Affidavit for NOCsFile: Annexure R3 Affidavit for NOCs.pdf | 18 Mar 2026 |
| STP DrawingFile: Annexure R4 STP drawing.pdf | 18 Mar 2026 |
| clarification on sources of fundsFile: Annexure R1 Clarification on Sources of Funds.pdf | 9 Mar 2026 |
| clarification on estimated costFile: Annexure R2 Clarification on estimated cost.pdf | 9 Mar 2026 |
| structural stability certificateFile: Annexure R3 Stability certificate.pdf | 9 Mar 2026 |
| Proforma of agreement to sellFile: Annexure R4 ATS.pdf | 9 Mar 2026 |
| sale deedFile: Annexure R5 Sale deed.pdf | 9 Mar 2026 |
| STP DrawingFile: Annexure R6 STP Drawing.pdf | 9 Mar 2026 |
| BWSSB NOCFile: Annexure R7 BWSSB NOC.pdf | 9 Mar 2026 |
| Bescom payment receiptFile: Annexure BESCOM Payment receipt.pdf | 9 Mar 2026 |
| RepliesFile: RERA Reply (1).pdf | 9 Mar 2026 |
| RTC, survey 77/2 | - |
| Mutation, survey 77/2 | - |
| Encumbrance Certificate, survey 77/2 | - |
| Conversion/Alienation Order, survey 77/2 | - |
| Sale/Title/Gift Deed, survey 77/2 | - |
| Khatha, survey 77/2 | - |
| RTC, survey 78 | - |
| Mutation, survey 78 | - |
| Encumbrance Certificate, survey 78 | - |
| Conversion/Alienation Order, survey 78 | - |
| Sale/Title/Gift Deed, survey 78 | - |
| Khatha, survey 78 | - |
| RTC, survey 79 | - |
| Mutation, survey 79 | - |
| Encumbrance Certificate, survey 79 | - |
| Conversion/Alienation Order, survey 79 | - |
| Sale/Title/Gift Deed, survey 79 | - |
| Khatha, survey 79 | - |
| RTC, survey 80/1 | - |
| Mutation, survey 80/1 | - |
| Encumbrance Certificate, survey 80/1 | - |
| Conversion/Alienation Order, survey 80/1 | - |
| Sale/Title/Gift Deed, survey 80/1 | - |
| Khatha, survey 80/1 | - |
| RTC, survey 80/2 | - |
| Mutation, survey 80/2 | - |
| Encumbrance Certificate, survey 80/2 | - |
| Conversion/Alienation Order, survey 80/2 | - |
| Sale/Title/Gift Deed, survey 80/2 | - |
| Khatha, survey 80/2 | - |
| Registration CertificateFile: Annexure 1 HPPL COI.PDF | - |
| Memorandum of AssociationFile: Annexure 15 HPPL MOA.pdf | - |
| Article of AssociationFile: Annexure 16 HPPL AOA.pdf | - |
| GST CertificateFile: Annexure 3 HPPL GSTIN Certificate.pdf | - |
| Organization StructureFile: Annexure 14 Orgination Structure.pdf | - |
| Certificate issued by CA Form 1File: Annexure 59 Form 1 CA Kindle Ph 1.pdf | - |
| Certificate issued by Architect Form 2File: Annexure 61 Form - 2 Architect (PR) - New.pdf | - |
| Certificate issued by Engineer Form 3File: Annexure 60 Form - 3 Engineer (PR).pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Century Kindle Phase 1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 35 registered projects within 2 km.
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
Sattva Lumina
Sattva Resi Private Limited
Brigade Eternia
Brigade Enterprises Ltd
Nikoo Homes V - Phase - 1
Bhartiya Urban Private Limited
GODREJ AVELINE
GODREJ SSPDL GREEN ACRES PRIVATE LIMITED
ORCHID SALISBURY
GOYAL HARIYANA ENTERPRISES
See every Bengaluru Urban project, with the district possession charts
Builder: Hebbal Properties Private Limited
Hebbal Properties Private Limited has 2 registrations on RERA Karnataka, including Century Bliss and Century Kindle Phase 1. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Century Kindle Phase 1 is delayed beyond 14 Mar 2031?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Century Kindle Phase 1?
The registered promoter entity is Hebbal Properties Private Limited, a company as per the filing. Its CIN U70109KA2021PTC145179 and GSTIN 29AAFCH6957D1ZA can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Century Kindle Phase 1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Century Kindle Phase 1?
The professionals named in the filing: Architect: Chandrashekar R; Engineer: Swaroop Devaiah K L; Chartered Accountant: Sugnana Kumar H. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Century Kindle Phase 1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback