Red flags

  • 8 complaints at RERA Karnataka
  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • Separate project account declared
Sep 2022Possession promisedmoved 21 months from the original
8Complaints at RERA Karnatakaon this registration
Jump to the 53 documents Report an error

Century Ethos is a Residential/Group Housing project by Century Real Estate Holdings Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/171014/000283 on 14 Oct 2017. Possession is promised by 30 Sep 2022. The completion date has moved by 21 months from the original filing. 8 complaints are on record with the regulator.

At a glance

Project

  • NameCentury Ethos
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/309/PR/171014/000283
  • ReraGenie IDRG-KA-16660

Builder

  • NameCentury Real Estate Holdings Private Limited
  • Entity typeCompany
  • CINU70101KA2007PTC042078
  • Authorized SignatoryMahesh Prabhu
  • OthersNeelakantha Patil
  • Other registrations2 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredOct 2017First promiseDec 2020Revised toSep 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on14 Oct 2017
  • Promised completion30 Sep 2022
  • Revised completionRevised to 30 Sep 2022 (originally 31 Dec 2020)
  • Buildings5 building records
  • Documents filed53 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK ARGON---1210121
TOWER BRONZE---1210121
TOWER CHROME---43043
BLOCK XENON 1---44044
BLOCK XENON 2---44044

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area29,574 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 452.98 cr

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2020 → Sep 2021

No reason recorded in the filing

EX/PRM/KA/RERA/1251/309/PR/221121/000283Sep 2021 → Sep 2022

Reason as filed by the promoterForce Majeure

Complaints filed with RERA Karnataka8

Case no.ComplainantRespondentFiled
CMP/200111/0005185-Century Real Estate Holdings Private Limited11/01/2020
CMP/210729/0008169-Century Real Estate Holdings Private Limited29/07/2021
CMP/211206/0008688-Century Real Estate Holdings Private Limited06/12/2021
CMP/220912/0009998-Century Real Estate Holdings Private Limited12/09/2022
00054/2024-Century Real Estate Holdings Private Limited11/01/2024
00251/2024-Century Real Estate Holdings Private Limited06/03/2024
01267/2024-Century Real Estate Holdings Private Limited30/11/2024
00877/2025-Century Real Estate Holdings Private Limited30/06/2025

Documents filed53

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/171014/000283 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: CREH-RegistrationCertificate.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Century Ethos Form Ex 1.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Century Ethos Form Ex 5.pdf-
CA Certificate for Funds UtilizationFile: CA certificate - fund utilized ethos.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Century Ethos Form Ex 2.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Century Ethos Form Ex 6.pdf-
CA Certificate for Funds required for Project CompletionFile: CA certificate - funds required ethos.pdf-
AffidavitFile: CREH Affidavits REDUCED.pdf-
Latest Encumbrance CertificateFile: ETHOS EC reduced.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
Commencement Certificate-ETHOS-
Building Plan-ETHOS-
Ethos-DP-
Sale Deed - FORMAT-
Ethos-AgreementtoSell-
Title opinion Final-
Sanction drawing-ETHOS compressed new-
Ethos-DP-
Allotment letter-
ETHOS Brochure (RERA)-
NOC Final-
SPECIFICATIONS-
Ethos - EC - Combined-
Ethos - Khata Certificate - Extract-
Ethos - JDA - Combined-
Ethos - Sale Deed - Combined-
ETHOS - CONVERSION ORDERS_new-
FIRE-NOC-
AAI-NOC-
BESCOM-NOC-
BWSSB-NOC_opt-
MOEF-NOC-
BSNL-NOC-
Balance Sheet 2015 - 2016File: CREH-AUDITED FINANCIAL STATEMENT-FY-2015-16_opt.pdf-
Balance Sheet 2014 - 2015File: CREH-FINANCIALS-FY-2014-15 revised.pdf-
Balance Sheet 2013 - 2014File: CREH Bs 2014 final.pdf-
Audited Profit and Loss Statement 2015 - 2016File: CREH-AUDITED FINANCIAL STATEMENT-FY-2015-16_opt.pdf-
Audited Profit and Loss Statement 2014 - 2015File: CREH-FINANCIALS-FY-2014-15 revised.pdf-
Audited Profit and Loss Statement 2013 - 2014File: CREH Bs 2014 final.pdf-
Director's Report 2015 - 2016File: Board Report-2016.pdf-
Director's Report 2014 - 2015File: BoardReport-2015.pdf-
Director's Report 2013 - 2014File: Directors Report.pdf-
Cash Flow Statement 2015 - 2016File: CREH-AUDITED FINANCIAL STATEMENT-FY-2015-16_opt.pdf-
Cash Flow Statement 2014 - 2015File: CREH-FINANCIALS-FY-2014-15 revised.pdf-
Auditor's Report 2015 - 2016File: Audit Report-2016.pdf-
Auditor's Report 2014 - 2015File: Audit Report-2015.pdf-
Auditor's Report 2013 - 2014File: Audit Report.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: CREH ITR Ack AY 2016-17.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: Ack ITR 2015-16 O.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: CREH Ack ITR 2014-15 O.pdf-
Form B Ethos-
Prospectus/BrochureFile: Ethos Brochure.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_309_PR_171014_000283.xlsx-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Century Eden-CompletedJul 2017No date filed

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 21 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Century Ethos on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Century Real Estate Holdings Private Limited

Century Real Estate Holdings Private Limited has 3 registrations on RERA Karnataka, including Century Xenon and Century Breeze. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Century Ethos is delayed beyond 30 Sep 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Century Ethos?

The registered promoter entity is Century Real Estate Holdings Private Limited, a company as per the filing. Its CIN U70101KA2007PTC042078 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Century Ethos?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Century Ethos?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

What should I check before booking in Century Ethos?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Century Ethos. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Century Ethos to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.