Red flags

  • 19 complaints at RERA Karnataka
  • Completion date moved by 33 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
Mar 2026Possession promisedmoved 33 months from the original
18 of 18Construction stages doneevery applicable stage filed complete
17 of 252Units unsoldnot recorded sold or booked
19Complaints at RERA Karnatakaon this registration
Jump to the 73 documents Report an error

CENTREO by Enessen Estates & Prime One Corp is a Residential/Group Housing project by SILVERSTREAM DEVELOPERS PVT LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/190823/002820 on 23 Aug 2019. Possession is promised by 30 Mar 2026. The completion date has moved by 33 months from the original filing. 235 of the 252 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete. 19 complaints are on record with the regulator.

At a glance

Project

  • NameCENTREO by Enessen Estates & Prime One Corp
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/190823/002820
  • ReraGenie IDRG-KA-83149

Builder

  • NameSILVERSTREAM DEVELOPERS PVT LTD
  • Entity typeCompany
  • CINU70100KA2015PTC078919
  • Authorized SignatoryRamana Reddy

Key dates

this monthRegisteredAug 2019First promiseJun 2023Revised toMar 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on23 Aug 2019
  • Promised completion30 Mar 2026
  • Revised completionRevised to 30 Mar 2026 (originally 30 Jun 2023)
  • Buildings3 building records
  • Documents filed73 files

Current status

93%235 of 252 units booked
128.1%Of the estimated cost spent so far

Figures as on 8 Apr 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Acacia---96096
Banyan---1020102
Cypress---54054

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 8 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 18 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Painting100%
Elevation work100%
Internal and External work including landscapes as per santioned drawings100%

Progress on shared amenities41

As on 8 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes100%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes100%
Water conservationYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes100%
Emergency Evacuation servicesYes100%
Storm water drainsYes100%
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseYes100%
Community HallYes100%
Outdoor Sports facilityYes100%
Indoor Sports facilityYes100%
Swimming PoolYes100%
GymYes100%
ParksYes100%
Power BackupYes100%
GasYes100%
Water and SanitationYes100%
Air Conditioning And incerntionNoNot applicable
StaircasesYes100%
LiftsYes100%
Staircases and Lift lobbies, corridor,lobbies, corridorYes100%
Fire escapesYes100%
Common entrance and exit for the building / common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areas and common storage spacesYes100%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,926 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 231.08 cr
Cost incurredRs 295.95 cr
Spent of the estimate128.07%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 163.57 crRs 188.57 cr
Total Estimated Cost of the Internal and External Development works inculding amenities and facilities and consultant charges etc- Certified by EngineerRs 67.51 crRs 107.38 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTilak A Thomas
EngineerAnagha Engineering Consultants

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJun 2023 → Mar 2024

No reason recorded in the filing

EX/PRM/KA/RERA/1251/310/PR/240328/002820Mar 2024 → Mar 2025

Reason as filed by the promoterShortage of Labour

ExtensionMar 2025 → Mar 2026

No reason recorded in the filing

Complaints filed with RERA Karnataka19

Case no.ComplainantRespondentFiled
CMP/221028/0010135-SILVERSTREAM DEVELOPERS PVT LTD28/10/2022
00583/2025-SILVERSTREAM DEVELOPERS PVT LTD03/04/2025
00666/2025-SILVERSTREAM DEVELOPERS PVT LTD22/04/2025
01185/2025-SILVERSTREAM DEVELOPERS PVT LTD18/09/2025
01255/2025-SILVERSTREAM DEVELOPERS PVT LTD09/10/2025
01273/2025-SILVERSTREAM DEVELOPERS PVT LTD14/10/2025
01316/2025-SILVERSTREAM DEVELOPERS PVT LTD29/10/2025
01325/2025-SILVERSTREAM DEVELOPERS PVT LTD30/10/2025
01329/2025-SILVERSTREAM DEVELOPERS PVT LTD31/10/2025
01336/2025-SILVERSTREAM DEVELOPERS PVT LTD03/11/2025
01340/2025-SILVERSTREAM DEVELOPERS PVT LTD04/11/2025
01341/2025-SILVERSTREAM DEVELOPERS PVT LTD05/11/2025
01343/2025-SILVERSTREAM DEVELOPERS PVT LTD06/11/2025
01347/2025-SILVERSTREAM DEVELOPERS PVT LTD06/11/2025
01356/2025-SILVERSTREAM DEVELOPERS PVT LTD10/11/2025
00112/2026-SILVERSTREAM DEVELOPERS PVT LTD12/02/2026
00446/2026-SILVERSTREAM DEVELOPERS PVT LTD23/04/2026
00678/2026-SILVERSTREAM DEVELOPERS PVT LTD09/06/2026
01113/2026-SILVERSTREAM DEVELOPERS PVT LTD10/09/2026

Documents filed73

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/190823/002820 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CentreoForm4Dec 25_final.pdf8 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Q3 (25-26) _QU_Architect - Dec 25 - Centreo_signed.pdf8 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Q3 (25-26)_QU_Engineer - Dec 25 - Centreo_Signed.pdf8 Apr 2026
Q4 2025-26 Water supply and sewage board8 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)8 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)8 Apr 2026
Q4 2025-26 KPTCL- BESCOM8 Apr 2026
Q4 2025-26 Fire and Safety8 Apr 2026
Q4 2025-26 Labour and Education Department8 Apr 2026
Q4 2025-26 Airport Authority of India8 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department8 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Centreo-Form-4_Dec 25.pdf31 Mar 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Q3 (25-26) _QU_Architect - Dec 25 - Centreo_signed.pdf31 Mar 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Q3 (25-26)_QU_Engineer - Dec 25 - Centreo_Signed.pdf31 Mar 2026
Q3 2025-26 Water supply and sewage board31 Mar 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)31 Mar 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)31 Mar 2026
Q3 2025-26 KPTCL- BESCOM31 Mar 2026
Q3 2025-26 Fire and Safety31 Mar 2026
Q3 2025-26 Labour and Education Department31 Mar 2026
Q3 2025-26 Airport Authority of India31 Mar 2026
Q3 2025-26 BSNL/Telecommunication Department31 Mar 2026
CertificateFile: Certificate of Incorporation-Silverstream.pdf-
Project Details-
Architect Certificate for Work Completion Schedule till DateFile: Architect Certificate A1 Work Completed.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer Certificate E1 Work Completed.pdf-
CA Certificate for Funds UtilizationFile: CA Certificate Amount Utilized.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Architect Certificate A1 Work Pending.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer Certificate E1 Work Pending.pdf-
CA Certificate for Funds required for Project CompletionFile: CA Certificate Funds Required.pdf-
AffidavitFile: Form B Affidavit.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
Document 1File: Board resolution.pdf-
Site plan-
Deed of Sale-Avasarala Technologies Ltd-
AVS-BBMP Approval Letter-12-02-2018-min_compressed-
AVS-BBMP Approval Letter-12-02-2018-min_compressed-
Project Specifications - RERA Specs for CETREO (1)-
AVS EC till date-
3(1) silverstreams-
Khata- Silverstream developers-
Deed of Sale-Avasarala Technologies Ltd-
Conversion Order for conversion of land from agricultural to non- agricultural industrial -
Conversion Order - Residential purposes_compressed-
fire noc MVC_compressed (1)-
Airport NOC-
BESCOM NOC-
BWSSB NoC-
Silver Stream CFE_compressed-
SEIAA 41 CON 2017_Silverstream_compressed-
BSNL NOC-
Unnamed document-
Site plan-
Title Report of Anup Shah-
Balance Sheet 2017 - 2018File: BS 2017-18.pdf-
Balance Sheet 2016 - 2017File: BS 2016-17.pdf-
Balance Sheet 2015 - 2016File: BS 2015-16.pdf-
Audited Profit and Loss Statement 2017 - 2018File: P _ L 17-18.pdf-
Audited Profit and Loss Statement 2016 - 2017File: P&L sighned 16-17.pdf-
Audited Profit and Loss Statement 2015 - 2016File: P _ L 15-16.pdf-
Director's Report 2017 - 2018File: Directors Report 17-18.pdf-
Director's Report 2016 - 2017File: directors report 16-17_compressed.pdf-
Director's Report 2015 - 2016File: Directors Report 2015-16-Silverstream.pdf-
Cash Flow Statement 2017 - 2018File: P _ L 17-18.pdf-
Auditor's Report 2017 - 2018File: Audited Financials 17-18.pdf-
Auditor's Report 2016 - 2017File: auditor report 16-17.pdf-
Auditor's Report 2015 - 2016File: Signed audit report-Silverstream-15-16.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: IT return acknowledgement AY 18-19.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: IT return acknowledgement AY 17-18.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: IT return acknowledgement AY 16-17.pdf-
form b silverstreams-
Prospectus/BrochureFile: centreo-e-brochure_.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_310_PR_190823_002820 (1).xlsx-

How this compares with Bengaluru Urban

93%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 33 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep CENTREO by Enessen Estates & Prime One Corp on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmCENTREO by Enessen EstatOther 32Dot size: filed unitsN

Filed coordinates, straight-line distance. 32 registered projects within 2 km.

Builder: SILVERSTREAM DEVELOPERS PVT LTD

SILVERSTREAM DEVELOPERS PVT LTD has 1 registration on RERA Karnataka, including CENTREO by Enessen Estates & Prime One Corp. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if CENTREO by Enessen Estates & Prime One Corp is delayed beyond 30 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of CENTREO by Enessen Estates & Prime One Corp?

The registered promoter entity is SILVERSTREAM DEVELOPERS PVT LTD, a company as per the filing. Its CIN U70100KA2015PTC078919 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in CENTREO by Enessen Estates & Prime One Corp?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against CENTREO by Enessen Estates & Prime One Corp?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at CENTREO by Enessen Estates & Prime One Corp?

The professionals named in the filing: Architect: Tilak A Thomas; Engineer: Anagha Engineering Consultants. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CENTREO by Enessen Estates & Prime One Corp?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CENTREO by Enessen Estates & Prime One Corp. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CENTREO by Enessen Estates & Prime One Corp to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.