Home / Browse projects / Bengaluru Urban, Karnataka / CBR SARASTHIRA
CBR SARASTHIRA
By CBR Builders
RG-KA-37285 · RERA PRM/KA/RERA/1251/446/PR/200117/003195 · Last updated on RERA Karnataka portal: 31 May 2022
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 9 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
CBR SARASTHIRA is a Residential/Group Housing project by CBR Builders in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/200117/003195 on 17 Jan 2020. Possession is promised by 20 Mar 2024. The completion date has moved by 9 months from the original filing.
At a glance
Project
- NameCBR SARASTHIRA
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/446/PR/200117/003195
- ReraGenie IDRG-KA-37285
Builder
- NameCBR Builders
- Entity typeProprietorship Firm
- Authorized SignatoryC.Ashok Kumar Reddy
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on17 Jan 2020
- Promised completion20 Mar 2024
- Revised completionRevised to 20 Mar 2024 (originally 20 Jun 2023)
- Buildings1 building record
- Documents filed86 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | - | - | - | 120 | 0 | 120 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 31 May 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
As on 31 May 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | No | Not applicable |
| Parks & Tree planting | Yes | - |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation | Yes | - |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | - |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SNS Associates |
| Engineer | SNS Associates |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed86
As listed on the registration, under the names the promoter filed them with; the newest 80 of 86 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/200117/003195 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Water NOCFile: Water NOC.pdf | 31 May 2022 |
| Airport Authority NOCFile: AIRPORT AUTHORITY NOC.pdf | 31 May 2022 |
| BESCOM NOCFile: BESCOM NOC.pdf | 31 May 2022 |
| FIRE NOCFile: FIRE NOC.pdf | 31 May 2022 |
| KSPCB NOCFile: KSPCB NOC.pdf | 31 May 2022 |
| CA CERTIFICATEFile: CA Certificate.pdf | 31 May 2022 |
| CLARIFICATIONS TO QUERY RAISEDFile: Rera queries clarification.pdf | 31 May 2022 |
| Airport Authority NOCFile: AIRPORT AUTHORITY NOC.pdf | 23 Mar 2022 |
| BESCOM NOCFile: BESCOM NOC.pdf | 23 Mar 2022 |
| FIRE NOCFile: FIRE NOC.pdf | 23 Mar 2022 |
| KSPCB NOCFile: KSPCB NOC.pdf | 23 Mar 2022 |
| MODIFIED PLANFile: MODIFIED PLAN.pdf | 23 Mar 2022 |
| WATER NOCFile: Water NOC.pdf | 23 Mar 2022 |
| Pollution Board - NOC AcknowledgementFile: CBR -kspcb-Acknowledgment.pdf | 10 Apr 2021 |
| RERA Area StatementFile: RERA AREA Statement.pdf | 10 Apr 2021 |
| NOC ClarificationsFile: RERA - NOC Clarifications.pdf | 10 Apr 2021 |
| Designated bank account statementFile: CBRBUILDERS Statement for yr2020-21.pdf | 10 Apr 2021 |
| Audited Balance sheet P and L 2018-19File: Balance sheet P and L 2018-19.pdf | 13 Jan 2020 |
| Audited Balance sheet P and L 2017-18File: Balance sheet P and L 2017-18.pdf | 13 Jan 2020 |
| Audited Balance sheet P and L 2016-17File: Balance sheet P and L 2016-17.pdf | 13 Jan 2020 |
| Site PlanFile: Site Plan.tif | 7 Jan 2020 |
| Basement PlanFile: Basement Floor Plan.tif | 7 Jan 2020 |
| Complete Floor PlanFile: Complete Floor Plan.tif | 7 Jan 2020 |
| Section and Elevation PlanFile: Section and Elevation Plan.tif | 7 Jan 2020 |
| KhathaFile: Khatha.pdf | 7 Jan 2020 |
| KPTCL NOCFile: KPTCL NOC.pdf | 7 Jan 2020 |
| Complete Income Tax 2016-17 along with audited balance sheet, P&L accountFile: IT 2016-17.pdf | 7 Jan 2020 |
| Complete Income Tax 2017-18 along with audited balance sheet, P&L accountFile: IT 2017-18.pdf | 7 Jan 2020 |
| Complete Income Tax 2018-19 along with audited balance sheet, P&L accountFile: IT 2018-19.pdf | 7 Jan 2020 |
| Fire Department NOCFile: Fire Department NOC.pdf | 7 Jan 2020 |
| Airport Authority NOCFile: Airport Authority NOC.pdf | 7 Jan 2020 |
| BSNL NOCFile: BSNL NOC.pdf | 7 Jan 2020 |
| BESCOM NOCFile: BESCOM NOC.pdf | 7 Jan 2020 |
| Pollution Control Board NOCFile: KSPCB NOC.pdf | 7 Jan 2020 |
| CertificateFile: Certificate.jpg | - |
| Modified plan details site plan, floor plans, Plan Licence LetterFile: Modified Plan cum License.pdf | - |
| Chartered Accountant CertificateFile: CA Certificate Form 4.pdf | - |
| Notarized AffidavitFile: AFFIDAVIT - CBR.pdf | - |
| Engineer CertificateFile: ENGINEER'S CERTIFICATE.pdf | - |
| Architect CertificateFile: ARCHITECT'S CERTIFICATE.pdf | - |
| Structural Engineer Certificate for stability of structureFile: STRUCTURAL STABILITY CERTIFICATE.pdf | - |
| Modification of Plan DetailsFile: Complete Plan Uploaded.jpg | - |
| Modification of Plan DetailsFile: Modified Plan.pdf | - |
| Modification of Plan DetailsFile: Commencement Certificate.pdf | - |
| Modification of Plan DetailsFile: Commencement Certificate.pdf | - |
| Document 1File: AIRPORT AUTHORITY NOC.pdf | - |
| RERA Area StatementFile: RERA AREA Statement.pdf | - |
| BDA Plan Sanction - Commencement | - |
| Confirmation Deed to JDA | - |
| Old Sale Deeds | - |
| Complete Plan Uploaded | - |
| Complete Plan Uploaded | - |
| Project Specifications | - |
| Encumbrance Till Date | - |
| Affidavit and Form-B | - |
| affidavit land owner and builder along with GPA | - |
| Khatha | - |
| joint development agreement | - |
| Fire Department NOC | - |
| Conversion Orders | - |
| Airport Authority NOC | - |
| BESCOM NOC | - |
| KSPCB NOC | - |
| BSNL NOC | - |
| Complete Plan Uploaded | - |
| Legal Report | - |
| Balance Sheet 2018 - 2019File: IT 2018-19.pdf | - |
| Balance Sheet 2017 - 2018File: IT 2017-18.pdf | - |
| Balance Sheet 2016 - 2017File: IT 2016-17.pdf | - |
| Audited Profit and Loss Statement 2018 - 2019File: IT 2018-19.pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: IT 2017-18.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: IT 2016-17.pdf | - |
| Cash Flow Statement 2018 - 2019File: IT 2018-19.pdf | - |
| Cash Flow Statement 2017 - 2018File: IT 2017-18.pdf | - |
| Income Tax Return Acknowledgement 2018 - 2019File: IT 2018-19.pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: IT 2017-18.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: IT 2016-17.pdf | - |
| Form - B | - |
| Prospectus/BrochureFile: cbr sarasthira brochure.pdf | - |
| Advertisement Copy 1File: cbr sarasthira brochure.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep CBR SARASTHIRA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: CBR Builders
CBR Builders has 1 registration on RERA Karnataka, including CBR SARASTHIRA. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if CBR SARASTHIRA is delayed beyond 20 Mar 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of CBR SARASTHIRA?
The registered promoter entity is CBR Builders, a proprietorship firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in CBR SARASTHIRA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at CBR SARASTHIRA?
The professionals named in the filing: Architect: SNS Associates; Engineer: SNS Associates. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in CBR SARASTHIRA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.