Red flags

  • 13 complaints at RERA Karnataka
  • Completion date moved by 57 months
  • 3 extensions taken

Clear

  • Separate project account declared
Sep 2025Possession promisedmoved 57 months from the original
13Complaints at RERA Karnatakaon this registration
Jump to the 117 documents Report an error

Castleton Greens is a Residential/Group Housing project by Associate Dwellings Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/190913/002843 on 13 Sep 2019. Possession is promised by 30 Sep 2025. The completion date has moved by 57 months from the original filing. 13 complaints are on record with the regulator.

At a glance

Project

  • NameCastleton Greens
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/308/PR/190913/002843
  • ReraGenie IDRG-KA-30196

Builder

  • NameAssociate Dwellings Private Limited
  • Entity typeCompany
  • CINU45205KA2013PTC070122
  • Authorized SignatoryRAJESH.PK
  • OthersNARENDRAN THULASI RAMAN

Key dates

this monthRegisteredSep 2019First promiseDec 2020Revised toSep 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on13 Sep 2019
  • Promised completion30 Sep 2025
  • Revised completionRevised to 30 Sep 2025 (originally 31 Dec 2020)
  • Buildings1 building record
  • Documents filed117 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CASTLETON GREENS (CG104)---1040104

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 28 Jun 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities45

As on 28 Jun 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Sewage Treatment Plant (STP)Yes-
Electricity supply transformer and substationYes-
Fire protection and fire safety requirements for Common AreasYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
Club House, Community Hall, Gym and Indoor SportsYes-
Children Play Area, Pet Area and Senior Citizen AreaYes-
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area25,596 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 56.64 cr

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2020 → Sep 2021

No reason recorded in the filing

EX/PRM/KA/RERA/1251/308/PR/220928/002843Sep 2021 → Sep 2022

Reason as filed by the promoterAwaiting Approvals

ExtensionSep 2022 → Sep 2025

No reason recorded in the filing

Complaints filed with RERA Karnataka13

Case no.ComplainantRespondentFiled
00379/2024-Associate Dwellings Private Limited15/04/2024
00685/2024-Associate Dwellings Private Limited03/08/2024
00114/2025-Associate Dwellings Private Limited17/01/2025
01164/2025-Associate Dwellings Private Limited12/09/2025
01165/2025-Associate Dwellings Private Limited12/09/2025
01166/2025-Associate Dwellings Private Limited12/09/2025
01167/2025-Associate Dwellings Private Limited12/09/2025
00064/2026-Associate Dwellings Private Limited30/01/2026
00091/2026-Associate Dwellings Private Limited06/02/2026
00092/2026-Associate Dwellings Private Limited06/02/2026
01045/2026-Associate Dwellings Private Limited24/08/2026
01207/2026-Associate Dwellings Private Limited08/10/2026
01209/2026-Associate Dwellings Private Limited09/10/2026

Documents filed117

As listed on the registration, under the names the promoter filed them with; the newest 80 of 117 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/190913/002843 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
ASSOCIATE VENDOR DETAILSFile: ASSOCIATE VENDOR DETAILS.pdf28 Jun 2022
BESCOM modified NOC Amount Paid ChallanFile: BESCOM modified NOC Amount Paid Challan.jpeg28 Jun 2022
BROCHURE DECLARATIONFile: BROCHURE DECLARATION.pdf28 Jun 2022
Castleton greens Stability CertificateFile: Castleton greens Stability Certificate.pdf28 Jun 2022
CG104 Allotment FormFile: CG104 Allotment Form.pdf28 Jun 2022
Latitude and longitudeFile: Latitude and longitude.pdf28 Jun 2022
Legal opinion Advocate Search ReportFile: Legal opinion Advocate Search Report.pdf28 Jun 2022
List of AllotteesFile: List of Allottees.PDF28 Jun 2022
MODIFIED AREA DETAILSFile: MODIFIED AREA DETAILS.pdf28 Jun 2022
Modified NOC from KSPCB CG 104File: Modified NOC from KSPCB CG 104.pdf28 Jun 2022
NEW AGREEMENT FOR SALE BY GOKFile: NEW AGREEMENT FOR SALE BY GOK.pdf28 Jun 2022
New NOC For Water SupplyFile: New NOC For Water Supply.PDF28 Jun 2022
NOC From BESCOMFile: NOC From BESCOM.pdf28 Jun 2022
Reason for ModificationFile: Reason for Modification.pdf28 Jun 2022
SEWAGE TREATMENT PLANT 70 KLD SBR sectional viewFile: SEWAGE TREATMENT PLANT 70 KLD SBR sectional view.pdf28 Jun 2022
SEWAGE TREATMENT PLANT sludge drying bed detailsFile: SEWAGE TREATMENT PLANT sludge drying bed details.pdf28 Jun 2022
Specification of CG for RERAFile: Specification of CG for RERA.PDF28 Jun 2022
Modified RERA Area Details Excel formatFile: Modified RERA Area Details.xlsx28 Jun 2022
VILLA 05 Modification Consent LetterFile: VILLA 05 Modification Consent Letter.pdf28 Jun 2022
VILLA 06 Modification Consent LetterFile: VILLA 06 Modification Consent Letter.pdf28 Jun 2022
VILLA 12 Modification Consent LetterFile: VILLA 12 Modification Consent Letter.pdf28 Jun 2022
VILLA 13 Modification Consent LetterFile: VILLA 13 Modification Consent Letter.pdf28 Jun 2022
VILLA 15 Modification Consent LetterFile: VILLA 15 Modification Consent Letter.pdf28 Jun 2022
VILLA 16 Modification Consent LetterFile: VILLA 16 Modification Consent Letter.pdf28 Jun 2022
VILLA 23 Modification Consent LetterFile: VILLA 23 Modification Consent Letter.pdf28 Jun 2022
VILLA 27 Modification Consent LetterFile: VILLA 27 Modification Consent Letter.pdf28 Jun 2022
VILLA 44 Modification Consent LetterFile: VILLA 44 Modification Consent Letter.pdf28 Jun 2022
VILLA 53 Modification Consent LetterFile: VILLA 53 Modification Consent Letter.pdf28 Jun 2022
VILLA 92 Modification Consent LetterFile: VILLA 92 Modification Consent Letter.pdf28 Jun 2022
Modified BESCOM NOCFile: Modified BESCOM NOC.pdf6 Apr 2022
New NOC For Water SupplyFile: New NOC For Water Supply.PDF6 Apr 2022
ADDENDUM from KSPCB CG 104 ModifiedFile: ADDENDUM from KSPCB CG 104 Modified.pdf6 Apr 2022
Anekal Group Housing Letter 14 01 2022File: Anekal Group Housing Letter 14 01 2022.pdf26 Jan 2022
BESCOM modified NOC Amount Paid ChallanFile: BESCOM modified NOC Amount Paid Challan.jpeg26 Jan 2022
Application submitted to Pollution Control BoardFile: Application submitted to Pollution Control Board.pdf26 Jan 2022
BLOCK AFile: CG 104 BLOCK A.pdf26 Jan 2022
BLOCK BFile: CG 104 BLOCK B.pdf26 Jan 2022
BLOCK CFile: CG 104 BLOCK C.pdf26 Jan 2022
BLOCK DFile: CG 104 BLOCK D.pdf26 Jan 2022
BLOCK EFile: CG 104 BLOCK E.pdf26 Jan 2022
BLOCK FFile: CG 104 BLOCK F.pdf26 Jan 2022
BLOCK GFile: CG 104 BLOCK G.pdf26 Jan 2022
CG 104File: CG 104 SANCTION APPROVAL DWG.pdf26 Jan 2022
MASTER PLANFile: MASTER PLAN 104 VILLAS.pdf26 Jan 2022
Commencement CertificateFile: Anekal Group Housing Letter 26 08 2021 104 Commencement Certificate.pdf30 Dec 2021
BESCOM modified NOC Amount Paid ChallanFile: BESCOM modified NOC Amount Paid Challan.jpeg30 Dec 2021
CG 104 SANCTION APPROVAL DWGFile: CG 104 SANCTION APPROVAL DWG.pdf30 Dec 2021
Form EX 3 Funds UtilizationFile: Form EX 3 Funds Utilization.pdf30 Dec 2021
Form EX 4 Fund RequiredFile: Form EX 4 Fund Required.pdf30 Dec 2021
INVENTORY DETAILSFile: INVENTORY DETAILS.pdf30 Dec 2021
KSPCB NOC till 28 08 2022File: KSPCB NOC till 28 08 2022.pdf30 Dec 2021
New Commencement CertificateFile: New Commencement Certificate.pdf30 Dec 2021
New NOC For Water SupplyFile: New NOC For Water Supply.PDF30 Dec 2021
Relinquishment deedFile: Relinquishment deed.pdf30 Dec 2021
SEWAGE TREATMENT PLANT 70 KLD SBR sectional viewFile: SEWAGE TREATMENT PLANT 70 KLD SBR sectional view.pdf30 Dec 2021
SEWAGE TREATMENT PLANT sludge drying bed detailsFile: SEWAGE TREATMENT PLANT sludge drying bed details.pdf30 Dec 2021
CertificateFile: IOC.jpg-
Project Details-
Already registered project ongoing detailsFile: FORM 5 ARCH FOR MODIFICATION.pdf-
Modified plan details site plan, floor plans, Plan Licence LetterFile: MASTER PLAN 104 VILLAS 4MB.pdf-
Elevation, Sections, Specifications ( If changes are there )File: MASTER PLAN 104 VILLAS 4MB.pdf-
List Of AllotteesFile: LIST OF ALLOTTEES.pdf-
List Of ComplaintsFile: NO COMPLAINTS.pdf-
Consent LetterFile: Villa No 05 Consent Letter for Modification Plan.pdf-
List Of Pending LitigationsFile: NO LITIGATIONS.pdf-
Chartered Accountant CertificateFile: FORM 4 CA FOR MODIFICATION.pdf-
Notarized AffidavitFile: Modification Affidavit.pdf-
Engineer CertificateFile: FORM 6 ENGR FOR MODIFICATION.pdf-
Architect CertificateFile: FORM 5 ARCH FOR MODIFICATION.pdf-
Structural Engineer Certificate for stability of structureFile: Castleton greens Stability Certificate.pdf-
Modification of Plan DetailsFile: Castleton Greens Approved plan.pdf-
Modification of Plan DetailsFile: CG 104 SANCTION APPROVAL DWG.pdf-
Modification of Plan DetailsFile: Anekal Group Housing Letter 26 08 2021 104 Commencement Certificate.pdf-
Modification of Plan DetailsFile: Anekal Group Housing Letter 14 01 2022 CC.pdf-
Modification of Plan DetailsFile: SOLD UNSOLD DETAILS.pdf-
Modification of Plan DetailsFile: LIST OF ALLOTTEES.pdf-
Document 1File: Modified BESCOM NOC.pdf-
Document 2File: New NOC For Water Supply.PDF-
Document 3File: Modified NOC from KSPCB CG 104.pdf-
All Consent Lettters for ModificationFile: All Consent Lettters for Modification 5MB.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 57 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Castleton Greens on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Associate Dwellings Private Limited

Associate Dwellings Private Limited has 1 registration on RERA Karnataka, including Castleton Greens. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Castleton Greens is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Castleton Greens?

The registered promoter entity is Associate Dwellings Private Limited, a company as per the filing. Its CIN U45205KA2013PTC070122 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Castleton Greens?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Castleton Greens?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

What should I check before booking in Castleton Greens?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Castleton Greens. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Castleton Greens to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.