Home / Browse projects / Bengaluru Urban, Karnataka / Casagrand Orlena

Registration approved Residential/Group Housing project

Casagrand Orlena

By Casa Grande Garden City Builders Pvt ltd

RG-KA-00379 · RERA PRM/KA/RERA/1251/446/PR/210928/004324 · Last updated on RERA Karnataka portal: 1 Oct 2024

Source: official RERA Karnataka filing

Red flags

  • 103 complaints at RERA Karnataka
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Aug 2025Possession promisedmoved 12 months from the original
103Complaints at RERA Karnatakaon this registration
Jump to the 87 documents Report an error

Casagrand Orlena is a Residential/Group Housing project by Casa Grande Garden City Builders Pvt ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/210928/004324 on 28 Sep 2021. Possession is promised by 21 Aug 2025. The completion date has moved by 12 months from the original filing. 103 complaints are on record with the regulator.

At a glance

Project

  • NameCasagrand Orlena
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/210928/004324
  • ReraGenie IDRG-KA-00379

Builder

  • NameCasa Grande Garden City Builders Pvt ltd
  • Entity typeCompany
  • CINU45400TN2018PTC125174
  • Authorized SignatoryKarjee Kishore Kumar
  • DirectorsArun Kumar M N, K R Anerudan
  • Other registrations16 more →
  • Declared earlier projects12 →

Key dates

this monthRegisteredSep 2021First promiseAug 2024Revised toAug 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on28 Sep 2021
  • Promised completion21 Aug 2025
  • Revised completionRevised to 21 Aug 2025 (originally 21 Aug 2024)
  • Buildings2 building records
  • Documents filed87 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building 1---1120112
Building 2---1840184

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 1 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 1 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationYes-
CCTV SurveillanceYes-
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area16,161 sq m
Named landowners2
LandownerVillageDistrict
S Kempanna--
Mohammed Shafiq Arshad--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 81.68 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSuresh Kumar Marthandan - Destination Designs
EngineerV G Palaksha - Anagha Engineering Consultants

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/446/PR/241009/004324Aug 2024 → Aug 2025

Reason as filed by the promoterShortage of Labour

Complaints filed with RERA Karnataka103

Case no.ComplainantRespondentFiled
00969/2024-Casa Grande Garden City Builders Pvt ltd04/10/2024
00079/2025-Casa Grande Garden City Builders Pvt ltd08/01/2025
00518/2025-Casa Grande Garden City Builders Pvt ltd19/03/2025
00528/2025-Casa Grande Garden City Builders Pvt ltd19/03/2025
00532/2025-Casa Grande Garden City Builders Pvt ltd20/03/2025
00539/2025-Casa Grande Garden City Builders Pvt ltd21/03/2025
00580/2025-Casa Grande Garden City Builders Pvt ltd03/04/2025
00614/2025-Casa Grande Garden City Builders Pvt ltd09/04/2025
00624/2025-Casa Grande Garden City Builders Pvt ltd11/04/2025
00721/2025-Casa Grande Garden City Builders Pvt ltd12/05/2025
00731/2025-Casa Grande Garden City Builders Pvt ltd13/05/2025
00732/2025-Casa Grande Garden City Builders Pvt ltd13/05/2025
00738/2025-Casa Grande Garden City Builders Pvt ltd14/05/2025
00752/2025-Casa Grande Garden City Builders Pvt ltd17/05/2025
00753/2025-Casa Grande Garden City Builders Pvt ltd19/05/2025
00754/2025-Casa Grande Garden City Builders Pvt ltd19/05/2025
00831/2025-Casa Grande Garden City Builders Pvt ltd12/06/2025
00850/2025-Casa Grande Garden City Builders Pvt ltd17/06/2025
00872/2025-Casa Grande Garden City Builders Pvt ltd20/06/2025
00884/2025-Casa Grande Garden City Builders Pvt ltd30/06/2025
00894/2025-Casa Grande Garden City Builders Pvt ltd01/07/2025
01020/2025-Casa Grande Garden City Builders Pvt ltd20/08/2025
01086/2025-Casa Grande Garden City Builders Pvt ltd28/08/2025
01088/2025-Casa Grande Garden City Builders Pvt ltd28/08/2025
01125/2025-Casa Grande Garden City Builders Pvt ltd01/09/2025
01134/2025-Casa Grande Garden City Builders Pvt ltd06/09/2025
01135/2025-Casa Grande Garden City Builders Pvt ltd06/09/2025
01162/2025-Casa Grande Garden City Builders Pvt ltd12/09/2025
01241/2025-Casa Grande Garden City Builders Pvt ltd29/09/2025
01256/2025-Casa Grande Garden City Builders Pvt ltd09/10/2025
01370/2025-Casa Grande Garden City Builders Pvt ltd11/11/2025
01375/2025-Casa Grande Garden City Builders Pvt ltd12/11/2025
01393/2025-Casa Grande Garden City Builders Pvt ltd17/11/2025
01422/2025-Casa Grande Garden City Builders Pvt ltd21/11/2025
01498/2025-Casa Grande Garden City Builders Pvt ltd20/12/2025
01503/2025-Casa Grande Garden City Builders Pvt ltd22/12/2025
01525/2025-Casa Grande Garden City Builders Pvt ltd26/12/2025
01534/2025-Casa Grande Garden City Builders Pvt ltd29/12/2025
01535/2025-Casa Grande Garden City Builders Pvt ltd29/12/2025
01536/2025-Casa Grande Garden City Builders Pvt ltd29/12/2025
01537/2025-Casa Grande Garden City Builders Pvt ltd29/12/2025
01538/2025-Casa Grande Garden City Builders Pvt ltd29/12/2025
01539/2025-Casa Grande Garden City Builders Pvt ltd29/12/2025
01540/2025-Casa Grande Garden City Builders Pvt ltd29/12/2025
01541/2025-Casa Grande Garden City Builders Pvt ltd29/12/2025
01542/2025-Casa Grande Garden City Builders Pvt ltd29/12/2025
01543/2025-Casa Grande Garden City Builders Pvt ltd29/12/2025
01544/2025-Casa Grande Garden City Builders Pvt ltd29/12/2025
01550/2025-Casa Grande Garden City Builders Pvt ltd31/12/2025
00005/2026-Casa Grande Garden City Builders Pvt ltd02/01/2026
00006/2026-Casa Grande Garden City Builders Pvt ltd02/01/2026
00015/2026-Casa Grande Garden City Builders Pvt ltd05/01/2026
00027/2026-Casa Grande Garden City Builders Pvt ltd08/01/2026
00035/2026-Casa Grande Garden City Builders Pvt ltd12/01/2026
00089/2026-Casa Grande Garden City Builders Pvt ltd05/02/2026
00124/2026-Casa Grande Garden City Builders Pvt ltd17/02/2026
00143/2026-Casa Grande Garden City Builders Pvt ltd19/02/2026
00265/2026-Casa Grande Garden City Builders Pvt ltd17/03/2026
00266/2026-Casa Grande Garden City Builders Pvt ltd17/03/2026
00267/2026-Casa Grande Garden City Builders Pvt ltd17/03/2026

Documents filed87

As listed on the registration, under the names the promoter filed them with; the newest 80 of 87 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/210928/004324 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
orlena Quarterly update detailsFile: 1 orlena Quarterly update details.pdf1 Oct 2024
Reason for delay LetterFile: 2 Reason for delay Letter.pdf1 Oct 2024
Designated bank account statementFile: 3 Designated bank account statement.pdf1 Oct 2024
Notarized Extension AffidavitFile: 4 Notarized Extension Affidavit.pdf1 Oct 2024
Orlena building planFile: 5 Orlena building plan.pdf1 Oct 2024
ORLENA BBMP BUILDING LICENCEFile: 6 ORLENA BBMP BUILDING LICENCE.pdf1 Oct 2024
Demand note issued by BWSSBFile: 1Demand Note from BWSSB.pdf16 Sep 2021
High Court order to issue NOC-BWSSBFile: 2High Court Order copy.pdf16 Sep 2021
Payment Details made towards Demand DraftFile: 4DD paid to NOC BWSSB.pdf16 Sep 2021
Request Letter to BBMPFile: 3Request letter to BBMP.pdf16 Sep 2021
Revenue-Mutation CopyFile: Revenue-Mutation extract for Survey No 18.pdf27 Aug 2021
Revenue- Endorsement issued by BDAFile: Revenue-Endorsement issued by BDA.pdf27 Aug 2021
NOC-Airport AuthorityFile: NOC-Airport Authority.pdf27 Aug 2021
NOC-BSNLFile: NOC-BSNL.pdf27 Aug 2021
NOC-FireFile: NOC-FIre.pdf27 Aug 2021
NOC-SEIAAFile: NOC-SEIAA.pdf27 Aug 2021
CertificateFile: Certificate of Incorporation.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Architect Certificate for work completion.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer Certificate for Work Completion.pdf-
CA Certificate for Funds UtilizationFile: CA Certificate for Fund Utilization.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Architect Certificate for Pending work.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer Certificate for Pending Work.pdf-
CA Certificate for Funds required for Project CompletionFile: CA cetificate for Funds required.pdf-
Latest Encumbrance CertificateFile: Encumbrance Certificate (2).pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
Document 1File: Seeking Extension Affidavit.pdf-
Document 2File: Form B Affidavit Orlena.pdf-
Building license-
Site Plan-
Approved plan-
Three Sale Deedso-
Section Plan-
Site Plan-
Specificationsc-
Up to date ECc-
Notarized Affidavit for 3(1) Voliation-
Joint Declaration Affidavitc-
Khatha Khatha extract MR and RTC-
JDA and GPA-
MOA and AOA-
Conversion Order-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
NOC-BESCOM-
NOC-BWSSB-
NOC-PCB-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Approved plan-
Specificationsc-
Board Resolution-
Unnamed document-
Balance Sheet 2019 - 2020File: Balance sheet 2019-20.pdf-
Balance Sheet 2018 - 2019File: Balance Sheet 2018-19.pdf-
Balance Sheet 2017 - 2018File: Balance Sheet 2017-18.pdf-
Audited Profit and Loss Statement 2019 - 2020File: Profit and loss 2019-20.pdf-
Audited Profit and Loss Statement 2018 - 2019File: Profit and loss 2018-19.pdf-
Audited Profit and Loss Statement 2017 - 2018File: Profit and loss 2017-18.pdf-
Director's Report 2019 - 2020File: Director's Report 2019-20.pdf-
Director's Report 2018 - 2019File: Director's Report 2018-19.pdf-
Director's Report 2017 - 2018File: Director's Report 2017-18.pdf-
Cash Flow Statement 2019 - 2020File: Cash flow 2019-20.pdf-
Cash Flow Statement 2018 - 2019File: Cash flow 2018-19.pdf-
Auditor's Report 2019 - 2020File: Auditor's Report 2019-20.pdf-
Auditor's Report 2018 - 2019File: Audit Report 2018-19.pdf-
Auditor's Report 2017 - 2018File: Auditor's Report 2017-18.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Casagrand Royce-Completed-No date filed

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Casagrand Orlena on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmCasagrand OrlenaOther 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 25 registered projects within 2 km.

Builder: Casa Grande Garden City Builders Pvt ltd

Casa Grande Garden City Builders Pvt ltd has 17 registrations on RERA Karnataka, including Casagrand Florella Phase 2 and CASAGRAND VIVACITY. Its filings declare 12 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Casagrand Orlena is delayed beyond 21 Aug 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Casagrand Orlena?

The registered promoter entity is Casa Grande Garden City Builders Pvt ltd, a company as per the filing. Its CIN U45400TN2018PTC125174 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Casagrand Orlena?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Casagrand Orlena?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Casagrand Orlena?

The professionals named in the filing: Architect: Suresh Kumar Marthandan - Destination Designs; Engineer: V G Palaksha - Anagha Engineering Consultants. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Casagrand Orlena?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Casagrand Orlena. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Casagrand Orlena to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.