ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / CASAGRAND BOULEVARD

Registration approved Residential/Group Housing project

CASAGRAND BOULEVARD

By GAZY MAG PVT LTD

RG-KA-76871 · RERA PRM/KA/RERA/1251/446/PR/201001/003629 · Last updated on RERA Karnataka portal: 29 Sep 2020

Source: official RERA Karnataka filing

Red flags

  • 29 complaints at RERA Karnataka

Clear

  • Completion date never moved
  • Separate project account declared
Dec 2024Possession promisedno revision filed
29Complaints at RERA Karnatakaon this registration
Jump to the 72 documents Report an error

CASAGRAND BOULEVARD is a Residential/Group Housing project by GAZY MAG PVT LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/201001/003629 on 1 Oct 2020. Possession is promised by 31 Dec 2024. 29 complaints are on record with the regulator.

At a glance

Project

  • NameCASAGRAND BOULEVARD
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/201001/003629
  • ReraGenie IDRG-KA-76871

Builder

  • NameGAZY MAG PVT LTD
  • Entity typeCompany
  • CINU45400TN2018PTC125174
  • Authorized SignatoryKarjee Kishore Kumar
  • DirectorsRaghunathan Sumanth Krishna, Ashok Kumar

Key dates

this monthRegisteredOct 2020PromisedDec 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on1 Oct 2020
  • Promised completion31 Dec 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed72 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Casagrand Boulavard---5280528

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 29 Sep 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 29 Sep 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationYes-
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area31,059 sq m
Named landowners1
LandownerVillageDistrict
GAZY MAG PVT LTD--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 176.03 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectP. N. Medappa
EngineerC. Ramkumar

Complaints filed with RERA Karnataka29

Case no.ComplainantRespondentFiled
CMP/210518/0007954-GAZY MAG PVT LTD18/05/2021
CMP/221221/0010505-GAZY MAG PVT LTD21/12/2022
01225/2023-GAZY MAG PVT LTD05/08/2023
00279/2024-GAZY MAG PVT LTD14/03/2024
00420/2024-GAZY MAG PVT LTD30/04/2024
00421/2024-GAZY MAG PVT LTD02/05/2024
00603/2024-GAZY MAG PVT LTD15/06/2024
00854/2024-GAZY MAG PVT LTD10/09/2024
01032/2024-GAZY MAG PVT LTD19/10/2024
01246/2024-GAZY MAG PVT LTD26/11/2024
01288/2024-GAZY MAG PVT LTD18/12/2024
01315/2024-GAZY MAG PVT LTD19/12/2024
00135/2025-GAZY MAG PVT LTD18/01/2025
00151/2025-GAZY MAG PVT LTD21/01/2025
00207/2025-GAZY MAG PVT LTD28/01/2025
00236/2025-GAZY MAG PVT LTD03/02/2025
00279/2025-GAZY MAG PVT LTD11/02/2025
00297/2025-GAZY MAG PVT LTD13/02/2025
00343/2025-GAZY MAG PVT LTD27/02/2025
00364/2025-GAZY MAG PVT LTD03/03/2025
00725/2025-GAZY MAG PVT LTD12/05/2025
00785/2025-GAZY MAG PVT LTD28/05/2025
00845/2025-GAZY MAG PVT LTD17/06/2025
01100/2025-GAZY MAG PVT LTD29/08/2025
01212/2025-GAZY MAG PVT LTD22/09/2025
01220/2025-GAZY MAG PVT LTD24/09/2025
01311/2025-GAZY MAG PVT LTD28/10/2025
01548/2025-GAZY MAG PVT LTD29/12/2025
00758/2026-GAZY MAG PVT LTD29/06/2026

Documents filed72

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/201001/003629 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Bank StatementFile: Bank Statement.pdf29 Sep 2020
Khatha in the name of GAZY MAG PRIVATE LIMITEDFile: khatha.pdf24 Sep 2020
CertificateFile: Incorporation Certificate.PDF-
Approval letters from BDA-
Site Plan-
All plans-
SALE DEED-
Site Plan-
Site Plan-
Specification-
Up to date Encumbrance Certificate-
Sec 3(1) non violation affidavit-
CHIKKA GUBBI KHATHA-
MOA - Gazy Mag digitally signed-
Conversion-
BOARD RESOLUTION-GAZY MAG-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
BESCOM-NOC-
WATER-NOC-
KSPCB-NOC-
STATE ENVIRONMENT-NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
All plans-
Section plan with specification-
Chikkagubbi Advocate Search Report-
Balance Sheet 2018 - 2019File: clarification.pdf-
Balance Sheet 2017 - 2018File: Balance Sheet 2018-19.pdf-
Balance Sheet 2016 - 2017File: clarification.pdf-
Audited Profit and Loss Statement 2018 - 2019File: clarification.pdf-
Audited Profit and Loss Statement 2017 - 2018File: Prifit & Loss 2018-19.pdf-
Audited Profit and Loss Statement 2016 - 2017File: clarification.pdf-
Director's Report 2018 - 2019File: clarification.pdf-
Director's Report 2017 - 2018File: clarification.pdf-
Director's Report 2016 - 2017File: clarification.pdf-
Cash Flow Statement 2018 - 2019File: clarification.pdf-
Cash Flow Statement 2017 - 2018File: Cash Floow 2018-19.pdf-
Auditor's Report 2018 - 2019File: clarification.pdf-
Auditor's Report 2017 - 2018File: clarification.pdf-
Auditor's Report 2016 - 2017File: clarification.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: clarification.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: clarification.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: clarification.pdf-
FORM B-
Prospectus/BrochureFile: Boulevard-Brochure.pdf-
Advertisement Copy 1File: paper ad.jpg-
Tower Excel SheetFile: PRM_KA_RERA_1251_446_PR_201001_003629.xlsx-
Stability CertificateFile: Stability certificate.pdf-
Occupancy CertificateFile: Occupancy certificate.pdf-
Consent for operation issued by KSPCBFile: KSPCB CFE.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: BESCOM NOC ( Boulevard).pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: BESCOM NOC ( Boulevard).pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: Water NOC Gram Panchyath.pdf-
Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: Work completion.pdf-
Details of undivided share of land handed over to the association of allotteesFile: Details of Undivided Share .pdf-
Architect certificate for having completed the work(in format no 5)File: Form-5 Architect CC.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: CA Form 4 CC.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: completion Affidavit.pdf-
Form-6 Engineer CCFile: Form-6 Engineer CC.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep CASAGRAND BOULEVARD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmCASAGRAND BOULEVARDOther 40Dot size: filed unitsN

Filed coordinates, straight-line distance. 40 registered projects within 2 km.

Builder: GAZY MAG PVT LTD

GAZY MAG PVT LTD has 1 registration on RERA Karnataka, including CASAGRAND BOULEVARD. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if CASAGRAND BOULEVARD is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of CASAGRAND BOULEVARD?

The registered promoter entity is GAZY MAG PVT LTD, a company as per the filing. Its CIN U45400TN2018PTC125174 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in CASAGRAND BOULEVARD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against CASAGRAND BOULEVARD?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at CASAGRAND BOULEVARD?

The professionals named in the filing: Architect: P. N. Medappa; Engineer: C. Ramkumar. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CASAGRAND BOULEVARD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CASAGRAND BOULEVARD. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CASAGRAND BOULEVARD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.