Registration revoked Residential/Group Housing project

Brigade Parkside West

By Brigade Enterprises Ltd

RG-KA-15161 · RERA PRM/KA/RERA/1251/310/PR/180611/001894

Source: official RERA Karnataka filing

Red flags

  • Registration revoked
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • Separate project account declared
Jump to the 38 documents Report an error

Brigade Parkside West is a Residential/Group Housing project by Brigade Enterprises Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/180611/001894 on 11 Jun 2018. Possession is promised by 30 Jun 2021. The completion date has moved by 6 months from the original filing.

At a glance

Project

  • NameBrigade Parkside West
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/180611/001894
  • ReraGenie IDRG-KA-15161

Builder

  • NameBrigade Enterprises Ltd
  • Entity typeCompany
  • CINL85110KA1995PLC019126
  • Authorized SignatoryViswa Prathap Desu
  • OthersRaghunandan S, Srinivasa N, Vinod Kumar Kulkarni, Suresh B C
  • Other registrations45 more →
  • No longer live1 withdrawn or revoked
  • Declared earlier projects67 →

Key dates

this monthRegisteredJun 2018First promiseDec 2020Revised toJun 2021

Key facts

Registration and timeline

  • StatusRegistration revoked
  • Registered on11 Jun 2018
  • Promised completion30 Jun 2021
  • Revised completionRevised to 30 Jun 2021 (originally 31 Dec 2020)
  • Buildings21 building records
  • Documents filed38 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---404
B---12012
C---16016
D---14014
E---16016
F---20020
G---12012
H---15015
J---20020
K---16016
L---14014
M---11011
N---16016
P---23023
Q---12012
R---16016
S---808
T---12012
U---12012
V---11011
W---12012

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes-
Water conservationYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallNoNot applicable
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area20,234 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 108.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMindspace Architects
EngineerBASE Engineering Services

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2020 → Jun 2021

No reason recorded in the filing

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/180611/001894 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Certificate of Incorporation - BEL copy.pdf-
Plan Sanction copy-
Parkside West Architect 28-05-2018-
Site Plan Demarcated Parkside West-
Sale deed draft from RERA-
Brigade Parkside West - Agreement to Sell-
All Sale Deeds-
Section & Elevation copy-
Site Plan Compressed-
Pro forma Brigade Parkside -West-
Brigade Parkside West_RERA Brochure_16 05 2018-
Parkside West Specifications-
EC till date-
KHATA-
Parkside West Conversion Order-
Site Plan-
Section & Elevation and Specifications-
Balance Sheet 2016 - 2017File: Balance Sheet - 31-03-2017.pdf-
Balance Sheet 2015 - 2016File: Balance Sheet - 31-03-2016.pdf-
Balance Sheet 2014 - 2015File: Balance Sheet - 31-03-2015.pdf-
Audited Profit and Loss Statement 2016 - 2017File: P&L Account - 31-03-2017.pdf-
Audited Profit and Loss Statement 2015 - 2016File: P&L Account - 31-03-2016.pdf-
Audited Profit and Loss Statement 2014 - 2015File: P&L Account - 31-03-2015.pdf-
Director's Report 2016 - 2017File: Director's Report 2016-17.pdf-
Director's Report 2015 - 2016File: Director's Report 2015-16.pdf-
Director's Report 2014 - 2015File: Director's Report 2014-15.pdf-
Cash Flow Statement 2016 - 2017File: Cash Flow Statement - 31-03-2017.pdf-
Cash Flow Statement 2015 - 2016File: Cash Flow Statement - 31-03-2016.pdf-
Auditor's Report 2016 - 2017File: Auditor's Report - 31-03-2017.pdf-
Auditor's Report 2015 - 2016File: Auditor's Report - 31-03-2016.pdf-
Auditor's Report 2014 - 2015File: Auditor's Report - 31-03-2015.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: ITR 2017.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR 2016.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: ITR 2015.pdf-
Form - B (Parkside West)-
Prospectus/BrochureFile: Parkside West A4 Booklet v4.pdf-
Advertisement Copy 1File: Parkside Ads.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_310_PR_180611_001894.xlsx-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 6 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is among them

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Brigade Parkside West on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmBrigade Parkside WestOther 26Dot size: filed unitsN

Filed coordinates, straight-line distance. 26 registered projects within 2 km.

Builder: Brigade Enterprises Ltd

Brigade Enterprises Ltd has 46 registrations on RERA Karnataka, including Brigade Oasis - Phase 1 and Brigade Atmosphere- Phase 1. Its filings declare 67 earlier projects, 41 of them declared completed. Litigation is declared on 10 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What does it mean that Brigade Parkside West shows as registration revoked on RERA Karnataka?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the RERA Karnataka portal, and take legal advice before paying any further instalment.

What are my rights if Brigade Parkside West is delayed beyond 30 Jun 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Brigade Parkside West?

The registered promoter entity is Brigade Enterprises Ltd, a company as per the filing. Its CIN L85110KA1995PLC019126 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Brigade Parkside West?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Brigade Parkside West?

The professionals named in the filing: Architect: Mindspace Architects; Engineer: BASE Engineering Services. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Brigade Parkside West?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Brigade Parkside West. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Brigade Parkside West to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.