Home / Browse projects / Bengaluru Urban, Karnataka / Brigade Padmini Tech Valley - Cloud
Brigade Padmini Tech Valley - Cloud
RG-KA-36527 · RERA PRM/KA/RERA/1251/446/PR/110823/006147 · Last updated on RERA Karnataka portal: 8 Aug 2023
Source: official RERA Karnataka filing
Red flags
- Litigation declared
Clear
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Brigade Padmini Tech Valley - Cloud is a Commercial project by Brigade Enterprises Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/110823/006147 on 11 Aug 2023. Possession is promised by 30 Jun 2024.
At a glance
Project
- NameBrigade Padmini Tech Valley - Cloud
- TypeCommercial
- Location
- Bengaluru East
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/446/PR/110823/006147
- ReraGenie IDRG-KA-36527
Builder
- NameBrigade Enterprises Ltd
- Entity typeCompany
- CINL85110KA1995PLC019126
- GSTIN29AAACB7459F1ZI
- Authorized SignatoryArindam Mukherjee
- Managing DirectorPavitra Shankar
- DirectorsM. R. Jaishankar, Velloor Venkatakrishnan Ranganathan, Roshin Mathew, Bijou Kurien, Aroon Raman, Lakshmi Venkatachalam, Pradeep Kumar Panja, Venkatesh Panchapagesan, Amar Mysore, Pavitra Shankar, Nirupa Shankar, Pradyumna Krishnakumar
- Project HeadProvash Naskar
- Other registrations45 more →
- No longer live1 withdrawn or revoked
- Declared earlier projects67 →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on11 Aug 2023
- Promised completion30 Jun 2024
- Revised completionNone
- Buildings1 building record
- Documents filed105 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Brigade Padmini Tech Valley - Cloud | - | - | - | 0 | 21 | 21 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 8 Aug 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Upto Plinth Level | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| Retaining wall (All types) | - |
| RCC or MS Framed structure | - |
| Masonry Construction | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Painting | - |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | - |
| Internal and External work including landscapes as per sanctioned drawings | - |
Progress on shared amenities40
As on 8 Aug 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Sewage and Drainage System | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | Yes | - |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Sewage Treatment Plant (STP) | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | No | Not applicable |
| Piped Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Corridor/Lobbies | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | No | Not applicable |
| Open parking areas | Yes | - |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership2
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| N Surekha and Others | - | - |
| N Surekha and Others | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 83.17 cr | - |
| On-site expenditure-Site Overhead | Rs 4.62 cr | - |
| Principal sum and interest payable to financial institutions-Scheduled Banks | Rs 3.82 cr | - |
| On-site expenditure-Salaries of workers | Rs 20.01 lakh | - |
| On-site expenditure-Consultants Fees | Rs 8.02 lakh | - |
| Payment of taxes | Rs 5.36 lakh | - |
| Payment of Premiums | Rs 34,741 | - |
| Payment of cess | Rs 30,612 | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Tilak Thomas |
| Engineer | RENUKA PRASAD H N |
| Chartered Accountant | R. Srinivasan |
Litigation declaredYes
The promoter declares litigation on this registration. The case records are in the filed documents.
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed105
As listed on the registration, under the names the promoter filed them with; the newest 80 of 105 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/110823/006147 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Note on O.S No. 762/2016File: Note on OS No 762 of 2016.pdf | 8 Aug 2023 |
| Building DetailsFile: Building Details.pdf | 8 Aug 2023 |
| Commencement CertificateFile: Brigade Padmini - Commencement Certificate - Building 3.pdf | 8 Aug 2023 |
| Sanction PlansFile: Sanction Plans.pdf | 8 Aug 2023 |
| Floor PlansFile: Sanction Plans.pdf | 8 Aug 2023 |
| Sections PlansFile: Sanction Plans.pdf | 8 Aug 2023 |
| Elevation PlansFile: Sanction Plans.pdf | 8 Aug 2023 |
| Blown up Plan - Area Demarcation PlanFile: Blownup Plan.pdf | 8 Aug 2023 |
| Zonal Regulations by BDAFile: BDA Zoning Regulations - RMP 2015.pdf | 8 Aug 2023 |
| Development Plan OrderFile: Brigade Padmini - Work Order.pdf | 8 Aug 2023 |
| Zonal Regulations showing Lake BufferFile: BDA Zoning Regulations - RMP 2015.pdf | 8 Aug 2023 |
| Zonal Regulations showing Nala BufferFile: BDA Zoning Regulations - RMP 2015.pdf | 8 Aug 2023 |
| Engineer CertificateFile: Cloud - Form 3 New.pdf | 8 Aug 2023 |
| STP PlanFile: STP Plan.pdf | 8 Aug 2023 |
| STP ReportFile: STP Report.pdf | 8 Aug 2023 |
| Proforma Allotment LetterFile: Allotment - Brigade Padmini Tech Centre.pdf | 8 Aug 2023 |
| Proforma Agreement to SellFile: Brigade Padmini Tech Valley - Cloud - Agreement to Sell.pdf | 8 Aug 2023 |
| Land Calculation Sheet - Self AttestedFile: Brigade Padmini Tech Valley - Guideline Value Details.pdf | 8 Aug 2023 |
| Section 3(1) - Notarized AffidavitFile: Cloud - Affidavit for Section 3.pdf | 8 Aug 2023 |
| BWSSB NOC - Fee ReceiptFile: BWSSB Fee Receipt.pdf | 8 Aug 2023 |
| BWSSB NOC - Self AttestedFile: BWSSB NOC - Self Attested.pdf | 8 Aug 2023 |
| Responses to the QueriesFile: Brigade Padmini Tech Valley - Cloud - List of Queries raised by RERA and BEL.pdf | 8 Aug 2023 |
| RTC, survey 10 | - |
| Mutation, survey 10 | - |
| Encumbrance Certificate, survey 10 | - |
| Conversion/Alienation Order, survey 10 | - |
| Sale/Title/Gift Deed, survey 10 | - |
| JDA, survey 10 | - |
| Khatha, survey 10 | - |
| RTC, survey 12/2A | - |
| Mutation, survey 12/2A | - |
| Encumbrance Certificate, survey 12/2A | - |
| Conversion/Alienation Order, survey 12/2A | - |
| Sale/Title/Gift Deed, survey 12/2A | - |
| JDA, survey 12/2A | - |
| Khatha, survey 12/2A | - |
| Registration CertificateFile: Certificate of Incorporation - BEL copy.pdf | - |
| Organization StructureFile: Organogram.pdf | - |
| Certificate issued by CA Form 1File: Cloud - Form 1.pdf | - |
| Certificate issued by Architect Form 2File: Cloud - Form 2.pdf | - |
| Certificate issued by Engineer Form 3File: Cloud - Form 3 New.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| Land Litigation Details | - |
| Land Litigation Details | - |
| Certificate from Chartered AccountFile: Cloud - Approval Cost Certificate.pdf | - |
| Balance Sheet 2021 - 2022File: Balance Sheet - 2022-23.pdf | - |
| Balance Sheet 2020 - 2021File: Balance Sheet - 2021-22 with CA UDIN.pdf | - |
| Balance Sheet 2019 - 2020File: Balance Sheet - 2020-21.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: Profit and Loss - 2022-23.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: Profti and Loss - 2021-22.pdf | - |
| Audited Profit and Loss Statement 2019 - 2020File: Profti and Loss - 2020-21.pdf | - |
| Director's Report 2021 - 2022File: Board Report - 2022-23.pdf | - |
| Director's Report 2020 - 2021File: Board Report - 2021-22.pdf | - |
| Director's Report 2019 - 2020File: Board Report - 2020-21.pdf | - |
| Cash Flow Statement 2021 - 2022File: Cash Flow Statement - 2022-23.pdf | - |
| Cash Flow Statement 2020 - 2021File: Cash Flow Statement - 2021-22.pdf | - |
| Auditor's Report 2021 - 2022File: Auditors Report - 2022-23.pdf | - |
| Auditor's Report 2020 - 2021File: Auditors Report - 2021-22.pdf | - |
| Auditor's Report 2019 - 2020File: Auditors Report - 2020-21.pdf | - |
| Income Tax Return Acknowledgement 2021 - 2022File: ITRV - 2021-22.pdf | - |
| Income Tax Return Acknowledgement 2020 - 2021File: ITRV - 2020-21.pdf | - |
| Income Tax Return Acknowledgement 2019 - 2020File: ITRV - 2019-20.pdf | - |
| Brigade Padmini Tech Valley - Plan Sanction Ltr | - |
| Brigade Padmini - BESCOM NOC | - |
| Brigade Padmini Tech Centre - BWSSB NOC | - |
| Brigade Padmini - Development Plan | - |
| Site Plan and Blownup Plan | - |
| Cloud at Brigade Padmini Tech Valley - Typical Floor Plan | - |
| Section and Specification | - |
| Section | - |
| Brigade Padmini Tech Valley - RERA Specifications New | - |
| Section | - |
| Brigade Padmini - Development Plan | - |
| Brigade Padmini Tech Valley - Cloud - Strcutural Stability Certificate | - |
| Title Opinion | - |
| Brigade Padmini - JD and SA | - |
| Conversion Order - Sy No 10, 12 & 13 | - |
| Conversion Order - Sy No 10, 12 & 13 | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Brigade Padmini Tech Valley - Cloud on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: Brigade Enterprises Ltd
Brigade Enterprises Ltd has 46 registrations on RERA Karnataka, including Brigade Oasis - Phase 1 and Brigade Atmosphere- Phase 1. Its filings declare 67 earlier projects, 41 of them declared completed. Litigation is declared on 10 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Brigade Padmini Tech Valley - Cloud is delayed beyond 30 Jun 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Brigade Padmini Tech Valley - Cloud?
The registered promoter entity is Brigade Enterprises Ltd, a company as per the filing. Its CIN L85110KA1995PLC019126 and GSTIN 29AAACB7459F1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Brigade Padmini Tech Valley - Cloud?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Brigade Padmini Tech Valley - Cloud?
The professionals named in the filing: Architect: Tilak Thomas; Engineer: RENUKA PRASAD H N; Chartered Accountant: R. Srinivasan. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Brigade Padmini Tech Valley - Cloud?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback