Home / Browse projects / Bengaluru Urban, Karnataka / Brigade Northridge Neo

Registration approved Residential/Group Housing project

Brigade Northridge Neo

By Brigade Enterprises Ltd

RG-KA-41933 · RERA PRM/KA/RERA/1251/309/PR/210824/004288 · Last updated on RERA Karnataka portal: 5 May 2022

Source: official RERA Karnataka filing

Red flags

  • 2 complaints at RERA Karnataka
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • Separate project account declared
Sep 2022Possession promisedmoved 6 months from the original
2Complaints at RERA Karnatakaon this registration
Jump to the 111 documents Report an error

Brigade Northridge Neo is a Residential/Group Housing project by Brigade Enterprises Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/210824/004288 on 24 Aug 2021. Possession is promised by 30 Sep 2022. The completion date has moved by 6 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameBrigade Northridge Neo
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/210824/004288
  • ReraGenie IDRG-KA-41933

Builder

  • NameBrigade Enterprises Ltd
  • Entity typeCompany
  • CINL85110KA1995PLC019126
  • Authorized SignatoryViswa Prathap Desu
  • OthersKeerthi Kumar H M, Balasubramanian MN
  • Other registrations45 more →
  • No longer live1 withdrawn or revoked
  • Declared earlier projects67 →

Key dates

this monthRegisteredAug 2021First promiseMar 2022Revised toSep 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on24 Aug 2021
  • Promised completion30 Sep 2022
  • Revised completionRevised to 30 Sep 2022 (originally 31 Mar 2022)
  • Buildings2 building records
  • Documents filed111 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block A---36036
Block B---64064

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 5 May 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etcNot applicable
Plastering inside , outside & CeilingNot applicable
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 5 May 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityYes-
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksYes-
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceNoNot applicable
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership5

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,940 sq m
Named landowners5
LandownerVillageDistrict
Govind Malu--
Nandakishore Malu--
Navalkishore Malu--
Vimal Malu--
Savitri Devi Malu--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 48.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectALAY Design Collaborators
EngineerS and S associates

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/309/PR/220630/004288Mar 2022 → Sep 2022

Reason as filed by the promoterothers

Complaints filed with RERA Karnataka2

Case no.ComplainantRespondentFiled
00245/2023-Brigade Enterprises Ltd24/02/2023
00953/2024-Brigade Enterprises Ltd30/09/2024

Documents filed111

As listed on the registration, under the names the promoter filed them with; the newest 80 of 111 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/210824/004288 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer Certificate with License NumberFile: Brigade Northridge Neo - Form 6.pdf5 May 2022
Reply to the QueriesFile: Brigade Northridge Neo - List of Queries raised by RERA and BEL Reply.pdf5 May 2022
Engineer Certificate - Work completedFile: Brigade Northridge Neo - Form 5.pdf30 Mar 2022
Engineer Certificate - Works PendingFile: Brigade Northridge Neo - Form 6.pdf30 Mar 2022
List of AllotteesFile: Brigade Northridge Neo - List of Allottees.pdf30 Mar 2022
KSPCB NOCFile: Brigade Northridge Neo - Consent for Operation.pdf30 Mar 2022
Structural Stability CertificateFile: Stability Certificate.jpg30 Mar 2022
STP Provision demarcated in Site PlanFile: Northridge Neo - Site plan.pdf30 Mar 2022
STP Layout PlanFile: Northridge Neo - STP Layout.pdf30 Mar 2022
Reply to QueriesFile: Brigade Northridge Neo - List of Queries raised by RERA.pdf30 Mar 2022
Project RERA Account Bank StatementFile: Brigade Northridge Neo - Statement of Account.pdf12 Aug 2021
RERA Account Opening FormFile: RERA Account Opening Form.pdf2 Aug 2021
List of Queries and Brigade Enterprises Limited responseFile: Brigade Northridge Neo - List of Queries raised by RERA and Brigade Enterprises Limited.pd30 Jul 2021
RERA Bank Account Opening FormFile: RERA Account Opening Form.pdf30 Jul 2021
Title OpinionFile: Brigade Northridge - Title Opinion - Kogilu.pdf30 Jul 2021
Consent for Operation (KSPCB NOC)File: KSPCB NOC.pdf30 Jul 2021
Demarcation Plan with detailed area calculation signed by ArchitectFile: Site Plan with Blown Up and Demarcation Plan.pdf30 Jul 2021
Occupancy Certificate for Phase 1 - Brigade NorthridgeFile: Brigade Northridge - Partial Occupancy Certificate.pdf30 Jul 2021
Project Member DetailsFile: Project Member Details.pdf30 Jul 2021
statutory payment towards appeal against order in CMP No 4196File: Appeal fees receipt-4196.pdf5 Jul 2021
Appeal (CMP 4245) order stating settlement and withdrawal of caseFile: Rera - Harsha Kashyap.pdf5 Jul 2021
Executed Sale Agreement - CMP 1777File: Sale Agreeement- 1777.pdf5 Jul 2021
CertificateFile: Certificate of Incorporation - BEL copy.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Brigade Northridge Neo - Form Ex1.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Brigade Northridge Neo - Form Ex5.pdf-
CA Certificate for Funds UtilizationFile: Brigade Northridge Neo - Form Ex3.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Brigade Northridge Neo - Form Ex2.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Brigade Northridge Neo - Form Ex6.pdf-
CA Certificate for Funds required for Project CompletionFile: Brigade Northridge Neo - Form Ex4.pdf-
AffidavitFile: Brigade Northridge Neo - Form Ex7.pdf-
Latest Encumbrance CertificateFile: Brigade Northridge Neo - Encumbrance Certificate.pdf-
Details Of Sold/ Un-sold UnitsFile: Brigade Northridge Neo - SoldUnsoldDetails.xlsx-
Document 1File: Brigade Northridge Neo - Form B.pdf-
Document 2File: Brigade Northridge Neo - Authorization Ltr.pdf-
Document 3File: Reasons for delay.pdf-
Brigade Northridge - Phase 2 - Plan Sanction Letter-
Site Plan with Blown Up Plan-
Typical Floor Plans-
Sale Deed Draft-
Brigade Northridge Neo - Agreement to Sell-
Brigade Northridge - Sale Deed and RTC-
Elevation and Section-
Brigade Northridge - Development Plan-
Brigade Northridge Neo - Allotment Letter-
Brigade Northridge Neo-
Specifications-
Brigade Northridge - Encumbrance Certificate-
Brigade Northridge - Notarised Affidavit for 3(1) Violation-
Joint Affidavit from Promoter and Landowner-
Brigade Northridge - Khata Certificate & Extract-
Brigade Northridge - JDA-
Brigade Northridge - Development Plan 1-
Brigade Northridge - Conversion Order-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Brigade Northridge - Fire NOC-
Brigade Northridge - Phase 2 - AAI NOC-
Brigade Northridge - Phase 2 - BESCOM NOC-
Brigade Northridge - BWSSB NOC-
Brigade Northridge - CFE-
Brigade Northridge - Environmental Clearance-
Brigade Northridge - BSNL NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Elevation and Section-
Blown Up Plan-
Section and Specification-
Brigade Northridge - Conversion Order-
Brigade Northridge - Title Opinion - Kogilu-
Balance Sheet 2019 - 2020File: Balance Sheet - 2019-20 with CA UDIN.pdf-
Balance Sheet 2018 - 2019File: Balance Sheet - 2018-19.pdf-

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 not delivered by the promised date2 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Brigade Deccan Heights-OngoingDec 2022Not delivered
Brigade Parkside North-OngoingDec 2021Not delivered
Brigade Senate 2-Completed-No date filed
Brigade Senate 1-Completed-No date filed

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 6 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Brigade Northridge Neo on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmBrigade Northridge NeoOther 30Dot size: filed unitsN

Filed coordinates, straight-line distance. 30 registered projects within 2 km.

Builder: Brigade Enterprises Ltd

Brigade Enterprises Ltd has 46 registrations on RERA Karnataka, including Brigade Oasis - Phase 1 and Brigade Atmosphere- Phase 1. Its filings declare 67 earlier projects, 41 of them declared completed. Litigation is declared on 10 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Brigade Northridge Neo is delayed beyond 30 Sep 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Brigade Northridge Neo?

The registered promoter entity is Brigade Enterprises Ltd, a company as per the filing. Its CIN L85110KA1995PLC019126 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Brigade Northridge Neo?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Brigade Northridge Neo?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Brigade Northridge Neo?

The professionals named in the filing: Architect: ALAY Design Collaborators; Engineer: S and S associates. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Brigade Northridge Neo?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Brigade Northridge Neo. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Brigade Northridge Neo to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.