Home / Browse projects / Bengaluru Urban, Karnataka / Brigade Deccan Heights
Brigade Deccan Heights
RG-KA-22640 · RERA PRM/KA/RERA/1251/309/PR/180905/002006
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 21 months
- 2 extensions taken
Clear
- No complaints on record
- Separate project account declared
Saved.
Brigade Deccan Heights is a Commercial project by Brigade Enterprises Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/180905/002006 on 5 Sep 2018. Possession is promised by 30 Dec 2023. The completion date has moved by 21 months from the original filing.
At a glance
Project
- NameBrigade Deccan Heights
- TypeCommercial
- Location
- Bengaluru North
- Bengaluru Urban
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/309/PR/180905/002006
- ReraGenie IDRG-KA-22640
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on5 Sep 2018
- Promised completion30 Dec 2023
- Revised completionRevised to 30 Dec 2023 (originally 31 Mar 2022)
- Buildings1 building record
- Documents filed53 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | - | - | - | 0 | 173 | 173 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | Not applicable |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | Yes | - |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | No | Not applicable |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Reason as filed by the promoterothers
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed53
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/180905/002006 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: Certificate of Incorporation - BEL copy.pdf | - |
| Architect Certificate for Work Completion Schedule till DateFile: Brigade Deccan Heights - Form EX1.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Brigade Deccan Heights - Form EX5.pdf | - |
| CA Certificate for Funds UtilizationFile: Brigade Deccan Heights - Form EX3.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: Brigade Deccan Heights - Form EX2.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Brigade Deccan Heights - Form EX6.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: Brigade Deccan Heights - Form EX4.pdf | - |
| AffidavitFile: Brigade Deccan Heights - Form EX7.pdf | - |
| Latest Encumbrance CertificateFile: Brigade Deccan Heights - Encumbarance Certificate.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: Brigade Deccan - SoldUnsoldDetails.xlsx | - |
| Document 1File: Brigade Deccan Heights - Form B.pdf | - |
| Deccan - Plan Sanction | - |
| Site 1 compressed | - |
| Site 1 compressed | - |
| Awaiting draft sale deed from RERA | - |
| Brigade Deccan Heights - RERA Agmt | - |
| All Sale Deeds | - |
| Elevation & Section compressed | - |
| Site 1 compressed | - |
| Deccan Heights - Allotment Notice format for RERA | - |
| Deccan Heights RERA Brochure 20_07 | - |
| Deccan Heights RERA Specifications | - |
| EC Combined | - |
| Brigade Deccan - Amalgamated Khata | - |
| Deccan -JDA dated 05-05-2017 | - |
| Deccan - Endorsement for Non Availability of Conversion order | - |
| Site (1) | - |
| Elevation & Section and Specifications | - |
| Balance Sheet 2016 - 2017File: Balance Sheet - 31-03-2017.pdf | - |
| Balance Sheet 2015 - 2016File: Balance Sheet - 31-03-2016.pdf | - |
| Balance Sheet 2014 - 2015File: Balance Sheet - 31-03-2015.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: P&L Account - 31-03-2017.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: P&L Account - 31-03-2016.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: P&L Account - 31-03-2015.pdf | - |
| Director's Report 2016 - 2017File: Director's Report 2016-17.pdf | - |
| Director's Report 2015 - 2016File: Director's Report 2015-16.pdf | - |
| Director's Report 2014 - 2015File: Director's Report 2014-15.pdf | - |
| Cash Flow Statement 2016 - 2017File: Cash Flow Statement - 31-03-2017.pdf | - |
| Cash Flow Statement 2015 - 2016File: Cash Flow Statement - 31-03-2016.pdf | - |
| Auditor's Report 2016 - 2017File: Auditor's Report - 31-03-2017.pdf | - |
| Auditor's Report 2015 - 2016File: Auditor's Report - 31-03-2016.pdf | - |
| Auditor's Report 2014 - 2015File: Auditor's Report - 31-03-2015.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: ITR 2017.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ITR 2016.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: ITR 2015.pdf | - |
| FormB - Affidavit cum Declaration -Deccan Heights | - |
| Prospectus/BrochureFile: Deccan Heights Brochure_v2.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1251_309_PR_180905_002006.xlsx | - |
| Occupancy CertificateFile: Brigade Deccan Heights - Occupancy Certificate.pdf | - |
| Completion certificate issued by the competent authorityFile: Brigade Deccan Heights - Occupancy Certificate.pdf | - |
| Registered Agreement of SaleFile: ATS - 1101, BDH - scan copy.pdf | - |
| Registered conveyance deed for an individual unitFile: Hemant Kumar - Sale Deed.pdf | - |
| InsuranceFile: Insurance Copy.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Brigade Deccan Heights on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 17 registered projects within 2 km.
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: Brigade Enterprises Ltd
Brigade Enterprises Ltd has 46 registrations on RERA Karnataka, including Brigade Oasis - Phase 1 and Brigade Atmosphere- Phase 1. Its filings declare 67 earlier projects, 41 of them declared completed. Litigation is declared on 10 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Brigade Deccan Heights is delayed beyond 30 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Brigade Deccan Heights?
The registered promoter entity is Brigade Enterprises Ltd, a company as per the filing. Its CIN L85110KA1995PLC019126 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Brigade Deccan Heights?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
What should I check before booking in Brigade Deccan Heights?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.