ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / Brigade Bricklane

Registration approved Residential/Group Housing project

Brigade Bricklane

By Brigade Enterprises Ltd

RG-KA-86570 · RERA PRM/KA/RERA/1251/309/PR/180808/001981

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 15 months
  • 2 extensions taken

Clear

  • No complaints on record
  • Separate project account declared
Mar 2023Possession promisedmoved 15 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 63 documents Report an error

Brigade Bricklane is a Residential/Group Housing project by Brigade Enterprises Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/180808/001981 on 8 Aug 2018. Possession is promised by 31 Mar 2023. The completion date has moved by 15 months from the original filing.

At a glance

Project

  • NameBrigade Bricklane
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/180808/001981
  • ReraGenie IDRG-KA-86570

Builder

  • NameBrigade Enterprises Ltd
  • Entity typeCompany
  • CINL85110KA1995PLC019126
  • Authorized SignatoryViswa Prathap Desu
  • Other registrations45 more →
  • No longer live1 withdrawn or revoked
  • Declared earlier projects67 →

Key dates

this monthRegisteredAug 2018First promiseDec 2021Revised toMar 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on8 Aug 2018
  • Promised completion31 Mar 2023
  • Revised completionRevised to 31 Mar 2023 (originally 31 Dec 2021)
  • Buildings20 building records
  • Documents filed63 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---20020
B---19019
C---40040
D---40040
E---38038
F---39039
G---40040
H---40040
I---40040
J---38038
K---39039
L---40040
M---40040
N---39039
O---39039
P---40040
Q---40040
R---39039
S---39039
T---40040

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes-
Water conservationYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallNoNot applicable
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area33,184 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 250.00 cr

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2021 → Sep 2022

No reason recorded in the filing

EX/PRM/KA/RERA/1251/309/PR/221028/001981Sep 2022 → Mar 2023

Reason as filed by the promoterForce Majeure; Shortage of Labour; Transport strike - Delay in Delivery of Material

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed63

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/180808/001981 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Certificate of Incorporation - BEL copy.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Brigade Bricklane - Form Ex 1.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Brigade Bricklane - Form Ex 5.pdf-
CA Certificate for Funds UtilizationFile: Brigade Bricklane - Form Ex 3.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Brigade Bricklane - Form Ex 2.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Brigade Bricklane - Form Ex 6.pdf-
CA Certificate for Funds required for Project CompletionFile: Brigade Bricklane - Form Ex 4.pdf-
AffidavitFile: Brigade Bricklane - Form Ex 7.pdf-
Latest Encumbrance CertificateFile: Brigade Bricklane - Encumbrance Certificate.pdf-
Details Of Sold/ Un-sold UnitsFile: Brigade Bricklane - Sold & Unsold Details.xlsx-
Document 1File: Request Letter for Extension.pdf-
Document 2File: Brigade Bricklane - Form B.pdf-
Bricklane - Plan sanction letter-
Bricklane Site Plan-
01 BBL- SITE PLAN-
Awaiting draft sale deed from RERA-
Agreement to Sell RERA -
All Sales Deeds and RTC-
Bricklane Section Plans-compressed (1)-
Bricklane Site Plan-
Pro forma Allotment Letter Brigade Bricklane-
Brigade Bricklane_A4-Brochure-
Specifications-
EC - Bricklane All 30-07-2018-
Katha certificate and Extract-
Brigade Bricklane GPA and JDA-
01 BBL- SITE PLAN-
Bricklane All Section Plans and Specification-
Bricklane - Conversion Order All Compressed-
Balance Sheet 2016 - 2017File: Balance Sheet - 31-03-2017.pdf-
Balance Sheet 2015 - 2016File: Balance Sheet - 31-03-2016.pdf-
Balance Sheet 2014 - 2015File: Balance Sheet - 31-03-2015.pdf-
Audited Profit and Loss Statement 2016 - 2017File: P&L Account - 31-03-2017.pdf-
Audited Profit and Loss Statement 2015 - 2016File: P&L Account - 31-03-2016.pdf-
Audited Profit and Loss Statement 2014 - 2015File: P&L Account - 31-03-2015.pdf-
Director's Report 2016 - 2017File: Director's Report 2016-17.pdf-
Director's Report 2015 - 2016File: Director's Report 2015-16.pdf-
Director's Report 2014 - 2015File: Director's Report 2014-15.pdf-
Cash Flow Statement 2016 - 2017File: Cash Flow Statement - 31-03-2017.pdf-
Cash Flow Statement 2015 - 2016File: Cash Flow Statement - 31-03-2016.pdf-
Auditor's Report 2016 - 2017File: Auditor's Report - 31-03-2017.pdf-
Auditor's Report 2015 - 2016File: Auditor's Report - 31-03-2016.pdf-
Auditor's Report 2014 - 2015File: Auditor's Report - 31-03-2015.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: ITR 2017.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR 2016.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: ITR 2015.pdf-
Bricklane Form B-
Prospectus/BrochureFile: Bricklane Brochure.pdf-
Advertisement Copy 1File: Marketing - No Ad.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_309_PR_180808_001981.xlsx-
Stability CertificateFile: Brigade Bricklane - STRUCTURAL STABILITY CERTIFICATE.PDF-
Road cutting permission letter issued by the planning Authority for laying Water supply line, sanitary line, UFile: Brigade Bricklane - Road Cutting Permission Letter.pdf-
Occupancy CertificateFile: Brigade Bricklane - Occupancy Certificate.pdf-
Consent for operation issued by KSPCBFile: Brigade Bricklane - CFO.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: Brigade Bricklane - Lift Approval1.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: Brigade Bricklane - Power Connection Letter.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: Brigade Bricklane - Water Connection Payment.pdf-
Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: Brigade Bricklane - Amenities Details.pdf-
Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: Brigade Bricklane - Handing over to Association.pdf-
Details of undivided share of land handed over to the association of allotteesFile: Brigade Bricklane - Deed of Declaration.pdf-
Architect certificate for having completed the work(in format no 5)File: Brigade Bricklane - Form 5 Completion Certificate.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: Brigade Bricklane - Form 4 Completion Certificate1.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Brigade Bricklane - Affidavit.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 15 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Brigade Bricklane on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmBrigade BricklaneOther 34Dot size: filed unitsN

Filed coordinates, straight-line distance. 34 registered projects within 2 km.

Builder: Brigade Enterprises Ltd

Brigade Enterprises Ltd has 46 registrations on RERA Karnataka, including Brigade Oasis - Phase 1 and Brigade Atmosphere- Phase 1. Its filings declare 67 earlier projects, 41 of them declared completed. Litigation is declared on 10 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Brigade Bricklane is delayed beyond 31 Mar 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Brigade Bricklane?

The registered promoter entity is Brigade Enterprises Ltd, a company as per the filing. Its CIN L85110KA1995PLC019126 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Brigade Bricklane?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in Brigade Bricklane?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Brigade Bricklane. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Brigade Bricklane to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.