ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / BIRLA TISYA

Registration approved No litigation declared Mixed Development project

BIRLA TISYA

By BIRLA TISYA LLP

RG-KA-55953 · RERA PRM/KA/RERA/1251/309/PR/211022/004371 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Dec 2026Possession promisedno revision filed
18 of 18Construction stages doneevery applicable stage filed complete
0 of 392Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 106 documents Report an error

BIRLA TISYA is a Mixed Development project by BIRLA TISYA LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/211022/004371 on 22 Oct 2021. Possession is promised by 31 Dec 2026. 392 of the 392 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameBIRLA TISYA
  • TypeMixed Development
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/211022/004371
  • ReraGenie IDRG-KA-55953

Builder

  • NameBIRLA TISYA LLP
  • Entity typePartnership Firm
  • Authorized SignatoryNaveen N
  • OthersNaveen N

Key dates

this monthRegisteredOct 2021PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on22 Oct 2021
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed106 files

Current status

100%392 of 392 units booked
1.6%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER-1---2100210
TOWER-2---1820182

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 18 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Painting100%
Elevation work100%
Internal and External work including landscapes as per santioned drawings100%

Progress on shared amenities41

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Internal Roads & FootpathsYes100%
Sewage and Drainage SystemYes100%
Parks & Tree plantingYes100%
Street LightingYes100%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes100%
Emergency Evacuation servicesYes100%
Storm water drainsYes100%
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseYes100%
Community HallNoNot applicable
Outdoor Sports facilityYes100%
Indoor Sports facilityNoNot applicable
Swimming PoolYes100%
GymYes100%
ParksNoNot applicable
Power BackupYes100%
GasNoNot applicable
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes100%
LiftsYes100%
Staircases and Lift lobbies, corridor,lobbies, corridorYes100%
Fire escapesYes100%
Common entrance and exit for the building / common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areas and common storage spacesYes100%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area19,121 sq m
Named landowners1
LandownerVillageDistrict
M/s. SUBADRA TEXTILE PRIVATE LIMITED-Director Mr. V.S Rajagopal--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 323.50 cr
Cost incurredRs 5.33 cr
Spent of the estimate1.65%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 252.98 crRs 1.97 cr
On-site expenditure-Salaries of workersRs 61.92 crRs 3.14 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 8.60 crRs 22.31 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectC. B. Vivek Uthaiah
EngineerMurali Guruvappan

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
01663/2023-BIRLA TISYA LLP04/11/2023

Documents filed106

As listed on the registration, under the names the promoter filed them with; the newest 80 of 106 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/211022/004371 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA certificate with OC.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form -5, Architect-SEPT 26-Tisya.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU) Tisya Sep-26.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Birla Tisya - Form -4 - Certificate - June 26 - Signed.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form -5, Architect-July 26-Tisya.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU) Tisya Jun-26.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form -4 - Certificate - March 26.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form -5 Architect-Mar 26.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer Mar26.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA certificate Dec 25.pdf14 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form -5 Architect-Dec 25.pdf14 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer certificate Dec25.pdf14 Jan 2026
Q3 2025-26 Water supply and sewage board14 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)14 Jan 2026
Q3 2025-26 KPTCL- BESCOM14 Jan 2026
Q3 2025-26 Fire and Safety14 Jan 2026
Q3 2025-26 Airport Authority of India14 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department14 Jan 2026
AAI NOCFile: AAI NOC.pdf11 Oct 2021
BESCOM NOCFile: BESCOM NOC.PDF11 Oct 2021
BSNL NOCFile: BSNL NOC.pdf11 Oct 2021
BWSSB NOCFile: BWSSB NOC.pdf11 Oct 2021
FIRE NOCFile: FIRE NOC.pdf11 Oct 2021
HAL NOCFile: HAL NOC.pdf11 Oct 2021
KSPCB CFEFile: KSPCB CFE NOC.pdf11 Oct 2021
KSPCB NOCFile: KSPCB NOC.pdf11 Oct 2021
SEIAAFile: SEIAA NOC.pdf11 Oct 2021
Audit reportFile: Auditor report 2021.pdf18 Sep 2021
balance sheetFile: Balance sheet 2021.pdf18 Sep 2021
Cashflow statementFile: Cashflow statement 2021.pdf18 Sep 2021
profit and lossFile: Profit and loss 2021.pdf18 Sep 2021
Bank account with declarationFile: Bank statement with declaration.pdf18 Sep 2021
bank accountFile: BANK STATEMENT.pdf18 Sep 2021
CertificateFile: Company incorporation certificate.pdf-
Building Licence-
Sanction Plan-
Sanction Plan-
Performa Sale deed-
Performa AOS-
Sale deed-
Sanction Plan-
CDP-
Allotment letter-
BROCHURE-
Specification-
EC 2021-
Section(3) Affidavit-
JD Affidavit-
KATHA-
JDA GPA-
Land document-
Converstion-
Fire NOC-
AIRPORT NOC-
BESCOM NOC-
BWSSB NOC-
KSPCB-
MOEF-

How this compares with Bengaluru Urban

100%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep BIRLA TISYA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: BIRLA TISYA LLP

BIRLA TISYA LLP has 1 registration on RERA Karnataka, including BIRLA TISYA. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if BIRLA TISYA is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of BIRLA TISYA?

The registered promoter entity is BIRLA TISYA LLP, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in BIRLA TISYA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against BIRLA TISYA?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at BIRLA TISYA?

The professionals named in the filing: Architect: C. B. Vivek Uthaiah; Engineer: Murali Guruvappan. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BIRLA TISYA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BIRLA TISYA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BIRLA TISYA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.