Home / Browse projects / Bengaluru Urban, Karnataka / Birla Ojasvi

Registration approved No litigation declared Residential/Group Housing project

Birla Ojasvi

By Birla Estates Private Limited

RG-KA-52315 · RERA PRM/KA/RERA/1251/310/PR/040924/006989 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jan 2031Possession promisedno revision filed
0 of 18Construction stages donefurthest along: Earth work and other leveling..., 94%
32 of 615Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 169 documents Report an error

Birla Ojasvi is a Residential/Group Housing project by Birla Estates Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/040924/006989 on 4 Sep 2024. Possession is promised by 11 Jan 2031. 583 of the 615 units on this registration are recorded sold or booked, and 0 of 18 construction stages are filed complete.

At a glance

Project

  • NameBirla Ojasvi
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560059
  • Pincode560059
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/040924/006989
  • ReraGenie IDRG-KA-52315

Builder

  • NameBirla Estates Private Limited
  • Entity typeCompany
  • CINU70100MH2017PTC303291
  • GSTIN29AAHCB5831G1ZL
  • Authorized SignatoryNaveen N
  • MdK T Jitendran
  • DirectorsK T Jitendran, Rajendra Kumar Dalmia
  • Project HeadVeerapratap Marati
  • Declared earlier projects3 →

Key dates

this monthRegisteredSep 2024PromisedJan 2031

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on4 Sep 2024
  • Promised completion11 Jan 2031
  • Revised completionNone
  • Buildings4 building records
  • Documents filed169 files

Current status

95%583 of 615 units booked
27.8%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER 1---1210121
TOWER 2---2480248
TOWER 3---2380238
TOWER 4---808

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 18 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 94%.

Building: 15% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work94%
Foundation footing work88%
Upto Plinth Level80%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)0%
RCC or MS Framed structure15%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes0%
Community HallNoNot applicable
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areasYes0%
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyYes0%
Common storage spacesYes0%

Land and ownership4

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area41,429 sq m
Named landowners4
LandownerVillageDistrict
Birla Estates Private Limited--
Birla Estates Private Limited--
Birla Estates Private Limited--
Birla Estates Private Limited--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 477.41 cr
Cost incurredRs 132.59 cr
Spent of the estimate27.77%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 400.00 crRs 76.68 cr
Administrative CostRs 53.18 cr-
On-site expenditure-Consultants FeesRs 20.23 crRs 38.08 cr
Payment of taxesRs 4.00 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRana Ram
EngineerArun Srikanth Nadig
Chartered AccountantAnilkumar Rajkumar Gupta

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed169

As listed on the registration, under the names the promoter filed them with; the newest 80 of 169 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/040924/006989 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Cert- Birla Ojasvi Signed-Sept 2026.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Arc Cert - Birla Ojasvi - Sep 26.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Eng Cert - Birla Ojasvi - Sep 26.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q2 2026-27 Fire and Safety14 Oct 2026
Q2 2026-27 Airport Authority of India14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 CA Cerrt - June 26 Ojasvi.pdf10 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) Jun'26 Ojasvi.pdf10 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU) Jun'26 ojasvi - LH signed.pdf10 Jul 2026
Q1 2026-27 Water supply and sewage board10 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)10 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)10 Jul 2026
Q1 2026-27 KPTCL- BESCOM10 Jul 2026
Q1 2026-27 Fire and Safety10 Jul 2026
Q1 2026-27 Airport Authority of India10 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Signed Ojasvi Mar 26.pdf14 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) Mar'26 Ojasvi.pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer - (QU) Mar'26 ojasvi - LH signed.pdf14 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Ojasvi_Form 4_Q3-Signed.pdf14 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) dec'25 Ojasvi.pdf14 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer - (QU) Dec'25 ojasvi - LH signed.pdf14 Jan 2026
Complaint Copy and Postal receipt-Birla OjasviFile: 1 Complaint Copy and Postal receipt-Birla Ojasvi.pdf26 Jul 2024
Form 1 - Birla OjasviFile: 2 Form 1 - Birla Ojasvi.pdf26 Jul 2024
FORM-3 ENGINEER CERTIFICATEFile: 3 FORM-3 ENGINEER CERTIFICATE.pdf26 Jul 2024
BIRLA OJASVI-Inventory TOWER 1 Area StatementFile: 4 BIRLA OJASVI-Inventory TOWER 1.pdf26 Jul 2024
BIRLA OJASVI-Inventory TOWER 2 Area StatementFile: 5 BIRLA OJASVI-Inventory TOWER 2.pdf26 Jul 2024
BIRLA OJASVI-Inventory TOWER 3 Area StatementFile: 6 BIRLA OJASVI-Inventory TOWER 3.pdf26 Jul 2024
BIRLA OJASVI-Inventory ROW HOUSES Area StatementFile: 7 BIRLA OJASVI-Inventory ROW HOUSES.pdf26 Jul 2024
Allottment LetterFile: 8 Allottment Letter.pdf26 Jul 2024
Form B Affidavit (Revised with new completion date)File: 9 Form B Affidavit (Revised with new completion date).pdf26 Jul 2024
Banking Affidavit (Revised with New completion date)File: 10 Banking Affidavit (Revised with New completion date).pdf26 Jul 2024
Engineer BBMP Certificate - ANFile: 11 BBMP Certificate - AN.PDF26 Jul 2024
BBMP Building PlanFile: 12 BBMP Building Plan.pdf26 Jul 2024
Affidavit for no advertisementFile: 1 Affidavit for no advertisement.pdf26 Jul 2024
Affidavit for no advertisementFile: 1 Affidavit for no advertisement.pdf4 Jun 2024
Micro Websites ListFile: 1 Micro Websites List.pdf4 Jun 2024
BIRLA OJASVI-Inventory ROW HOUSESFile: 2 BIRLA OJASVI-Inventory ROW HOUSES.pdf4 Jun 2024
BIRLA OJASVI-Inventory TOWER 1File: 2 BIRLA OJASVI-Inventory TOWER 1.pdf4 Jun 2024
BIRLA OJASVI-Inventory TOWER 2File: 2 BIRLA OJASVI-Inventory TOWER 2.pdf4 Jun 2024
BIRLA OJASVI-Inventory TOWER 3File: 2 BIRLA OJASVI-Inventory TOWER 3.pdf4 Jun 2024
BUILDING LICENSE issued by BBMPFile: 3 BUILDING LICENSE issued by BBMP.pdf4 Jun 2024
Building Plan all the floorsFile: 4 Building Plan all the floors.pdf4 Jun 2024
Section and elevation planFile: 4 Section and elevation plan.pdf4 Jun 2024
Query reply Birla OjasviFile: Query - Birla Ojasvi.pdf4 Jun 2024
Affidavit for no advertisementFile: Affidavit for no advertisement.pdf29 Apr 2024
Micro Websites ListFile: Micro Websites List.pdf29 Apr 2024
Query Answers 29-04-2024File: Query Answers 29-04-2024.pdf29 Apr 2024
Affidavit for no advertisementFile: Affidavit for no advertisement.pdf25 Mar 2024
Engineer LicenseFile: Engineer License.pdf25 Mar 2024
Bank AffidavitFile: Bank Affidavit.pdf25 Mar 2024
Form B AffidavitFile: Form B Affidavit.pdf25 Mar 2024
Proforma of AOSFile: Proforma of AOS.pdf25 Mar 2024
Directors Report 2021File: 1 Directors Report 2021.pdf26 Feb 2024
Directors Report 2022File: 1 Directors Report 2022.pdf26 Feb 2024
Directors Report 2023File: 1 Directors Report 2023.pdf26 Feb 2024
Source of Fund with Supporting DocFile: 2 Source of Fund with Supporting Doc.pdf26 Feb 2024
MR T30File: 3 MR T30.pdf26 Feb 2024
Complaint Copy and Postal receiptFile: 4 Complaint Copy and Postal receipt.pdf26 Feb 2024
Engineer LicenseFile: 5 Engineer License.pdf26 Feb 2024
Agreement for SaleFile: 16 Agreement for Sale.pdf26 Feb 2024
Collection AcFile: 1 Collection Ac.pdf22 Jan 2024
RERA AcFile: 2 RERA Ac.pdf22 Jan 2024
Ops AcFile: 3 Ops Ac.pdf22 Jan 2024
MR 13 Sy 66 2File: 4 MR 13 Sy 66 2.pdf22 Jan 2024
MR T30 Sy 24 2File: 4 MR T30 Sy 24 2.pdf22 Jan 2024
Khatha ExtractFile: 5 Khatha Extract.pdf22 Jan 2024
Akarbandh All Sy NoFile: 6 Akarbandh All Sy No.pdf22 Jan 2024
Village MapFile: 7 Village Map.pdf22 Jan 2024
NALA Classification NOCFile: 8 NALA Classification NOC.pdf22 Jan 2024
Land CalculationFile: 9 Land Calculation.pdf22 Jan 2024
BWSSB Noc with fee receiptFile: 10 BWSSB Noc with fee receipt.pdf22 Jan 2024
Project SpecificationFile: 11 Project Specification.pdf22 Jan 2024
Allottment LetterFile: 12 Allottment Letter.pdf22 Jan 2024
STP DrawingFile: 13 STP Drawing.pdf22 Jan 2024
Structural StabilityFile: 14 Structural Stability.pdf22 Jan 2024
Abstract EstimationFile: 15 Abstract Estimation.pdf22 Jan 2024
CDP MapFile: 16 CDP Map.pdf22 Jan 2024

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date2 under way, not due yet
ProjectLocationStatusPromisedDelivered
Birla Trimaya Phase-1Birla Trimaya, B.K. Halli Road, Akkalenahalli-Mallenahalli Village, Devanahalli Taluk, Bangalore Rural District-562110OngoingOct 2028Not due yet
Birla TisyaBirla Tisya, No. 11, Magadi Main Road, Agrahara Dasarahalli, Bengaluru-560079OngoingDec 2026Not due yet
Birla Alokya LitigationBirla Alokya, Soukya Road, Whitefield, Bengaluru - 560067OngoingMay 2024Not delivered

How this compares with Bengaluru Urban

95%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Birla Ojasvi on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmBirla OjasviOther 27Dot size: filed unitsN

Filed coordinates, straight-line distance. 27 registered projects within 2 km.

Builder: Birla Estates Private Limited

Birla Estates Private Limited has 1 registration on RERA Karnataka, including Birla Ojasvi. Its filings declare 3 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Birla Ojasvi is delayed beyond 11 Jan 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Birla Ojasvi?

The registered promoter entity is Birla Estates Private Limited, a company as per the filing. Its CIN U70100MH2017PTC303291 and GSTIN 29AAHCB5831G1ZL can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Birla Ojasvi?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Birla Ojasvi?

The professionals named in the filing: Architect: Rana Ram; Engineer: Arun Srikanth Nadig; Chartered Accountant: Anilkumar Rajkumar Gupta. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Birla Ojasvi?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Birla Ojasvi. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Birla Ojasvi to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.