Registration approved Residential/Group Housing project

BHAVYA LAKE VISTA

By Bhavya Constructions

RG-KA-65856 · RERA PRM/KA/RERA/1251/446/PR/200811/003527 · Last updated on RERA Karnataka portal: 4 Aug 2020

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Dec 2024Possession promisedmoved 12 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 99 documents Report an error

BHAVYA LAKE VISTA is a Residential/Group Housing project by Bhavya Constructions in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/200811/003527 on 11 Aug 2020. Possession is promised by 31 Dec 2024. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameBHAVYA LAKE VISTA
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/200811/003527
  • ReraGenie IDRG-KA-65856

Builder

  • NameBhavya Constructions
  • Entity typePartnership Firm
  • Authorized SignatoryPuttaVenkataLakshmana Rao
  • OthersN. Venkateswarlu, V. Lakshmi, N. Thirupathi Rao, PuttaVenkataLakshmana Rao, N. Jayasri
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2020First promiseDec 2023Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on11 Aug 2020
  • Promised completion31 Dec 2024
  • Revised completionRevised to 31 Dec 2024 (originally 31 Dec 2023)
  • Buildings1 building record
  • Documents filed99 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Bhavya Lake Vista---1240124

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 4 Aug 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)Not applicable
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 4 Aug 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,165 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 27.75 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSREENIVASA RAO. G
EngineerVIRUPAKSHA SWAMY

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/446/PR/231017/003527Dec 2023 → Dec 2024

Reason as filed by the promoterothers

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed99

As listed on the registration, under the names the promoter filed them with; the newest 80 of 99 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/200811/003527 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Affidavit for NOCFile: Affidavtit for NOC.pdf4 Aug 2020
Letter for NOCFile: Letter for NOC.pdf4 Aug 2020
Bank statementFile: Bank statement.pdf4 Aug 2020
Apply letter for issue for NOCFile: Ack for BWSSB NOC.pdf13 Jul 2020
Ack of NOC for BWSSBFile: Ack for BWSSB NOC.pdf6 Jul 2020
EC for 15 yearsFile: EC for 15 years.pdf29 Jun 2020
Conversion orderFile: Conversion order.pdf29 Jun 2020
Project specification sheetFile: Project Specification sheet.pdf29 Jun 2020
Rectified amalgamtion deedFile: Rectified amalgamation deed.pdf29 Jun 2020
BWSSB NOCFile: bwssb noc.pdf29 Jun 2020
CertificateFile: Certificate of Registration.pdf-
Architect Certificate for Work Completion Schedule till DateFile: ARCHITECTS FORM EX2 work as on date.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: ENGINEERS FORM EX5 Work as on date.pdf-
CA Certificate for Funds UtilizationFile: CA certificate Fund utilization.pdf-
Architect Certificate for Pending Work Completion Schedule.File: ARCHITECTS FORM EX1 Pending work.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: ENGINEERS FORM EX6 Pending Work.pdf-
CA Certificate for Funds required for Project CompletionFile: CA Certificate Fund required certificate.pdf-
AffidavitFile: Form Ex-7 Affidavit.pdf-
Latest Encumbrance CertificateFile: EC Uploaded other documents section.pdf-
Consent letter from 2/3rd of AllotteesFile: Consent Letter_compressed.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
Document 1File: Form-B.pdf-
Document 2File: EC for 15 years.pdf-
Plan approval letter-
Floor Plan and Section Plan-
Floor Section Stilt Site Plan-
Sale Deed Bhavya Lake Vista Rera-
Proforma of agreement sale-
Sale Deed RTC-
Floor Plan and Section Plan-
PROFORMA BOOKING FORM-
BROCHURE NOT AVLBL-
Project Specification sheet-
EC-
Sec 3(1) affidavit-
KATHA KATHA EXTRACT-
Legal Report-
RTC MR AKARABAND-
Convesrion Order-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
ACK BWSSB NOC-
KSPCB-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Floor Plan and Section Plan-
Floor Plan and Section Plan-
Convesrion Order-
Legal Report-
Balance Sheet 2018 - 2019File: Declaration for Financial Statements.pdf-
Balance Sheet 2017 - 2018File: Declaration for Financial Statements.pdf-
Balance Sheet 2016 - 2017File: Declaration for Financial Statements.pdf-
Audited Profit and Loss Statement 2018 - 2019File: Declaration for Financial Statements.pdf-
Audited Profit and Loss Statement 2017 - 2018File: Declaration for Financial Statements.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Declaration for Financial Statements.pdf-
Director's Report 2018 - 2019File: Declaration for Financial Statements.pdf-
Director's Report 2017 - 2018File: Declaration for Financial Statements.pdf-
Director's Report 2016 - 2017File: Declaration for Financial Statements.pdf-
Cash Flow Statement 2018 - 2019File: Declaration for Financial Statements.pdf-
Cash Flow Statement 2017 - 2018File: Declaration for Financial Statements.pdf-
Auditor's Report 2018 - 2019File: Declaration for Financial Statements.pdf-
Auditor's Report 2017 - 2018File: Declaration for Financial Statements.pdf-
Auditor's Report 2016 - 2017File: Declaration for Financial Statements.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: Declaration for Financial Statements.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: Declaration for Financial Statements.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep BHAVYA LAKE VISTA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmBHAVYA LAKE VISTAOther 28Dot size: filed unitsN

Filed coordinates, straight-line distance. 28 registered projects within 2 km.

Builder: Bhavya Constructions

Bhavya Constructions has 2 registrations on RERA Karnataka, including BHAVYA LAKE VISTA and Bhavya Triora. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if BHAVYA LAKE VISTA is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of BHAVYA LAKE VISTA?

The registered promoter entity is Bhavya Constructions, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in BHAVYA LAKE VISTA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at BHAVYA LAKE VISTA?

The professionals named in the filing: Architect: SREENIVASA RAO. G; Engineer: VIRUPAKSHA SWAMY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BHAVYA LAKE VISTA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BHAVYA LAKE VISTA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BHAVYA LAKE VISTA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.