ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Bhaveshwar Nagar Building No. 3

Completed No litigation declared Mixed project

Bhaveshwar Nagar Building No. 3

By Yog Reality

RG-MH-11815 · RERA P51800003355 · Last updated on MahaRERA portal: 6 Apr 2019

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2022Possession promisedregistration recorded completed
10 of 11Construction stages doneacross 2 buildings; furthest along: Installation of Lifts, 95%
1Complaints at MahaRERAon this registration
Jump to the 27 documents Report an error

Bhaveshwar Nagar Building No. 3 is a Mixed project by Yog Reality in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003355 on 5 Aug 2017. The registration is recorded completed; possession was promised by 30 Mar 2022. The completion date has moved by 36 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameBhaveshwar Nagar Building No. 3
  • TypeMixed
  • Location
    • Kurla
    • Mumbai Suburban
    • 400077
  • Pincode400077
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800003355
  • ReraGenie IDRG-MH-11815

Builder

  • NameYog Reality
  • Entity typePartnership
  • PartnerSagar Bharat Satra

Key dates

this monthRegisteredAug 2017First promiseMar 2019Revised toMar 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on5 Aug 2017
  • Promised completion30 Mar 2022
  • Revised completionRevised to 30 Mar 2022 (originally 31 Mar 2019)
  • Buildings1 building record
  • Documents filed27 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Bhaveshwar Nagar Building No 3NA190000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 6 Apr 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 95%.

Bhaveshwar Nagar Building No 3100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
NA Plot Without StructureNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities17

As on 6 Apr 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes95%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
Fitness CentreYes80%
Society OfficeYes80%

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,150 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
Nainesh Bharat SatraKurlaMumbai Suburban
Shree Bhaveshwar Workers CHS LtdKurlaMumbai Suburban
Manish Amarshi ShahThane (M Corp.)Thane

Approvals and building plan

Permissible FSI3668.78
Proposed, not sanctioned3,669 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMUMBAI

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMehul Vaghela of Creative Consultancy
EngineerDilip Parekh
Chartered AccountantKETAN VINODCHANDRA LATHIA
PartnerRole in project
Yog Reality-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800001611Mar 2019 → Mar 2021

Reason as filed by the promoterTwo reasons, on submitting seprate PRC with corrected area of final plot no. 25 & handing over of PTC tenements to SRA, FULL OCCUPATION CERTIFICATE will be granted by planning authority SRA to M/s Yog Reality for building named ‘Bhaveshwar Nagar Building No.3’. The copies of the said order from competent authority and high court is uploaded for verification. The consent/NOC for extenetion from all new flat purchasers is also uploaded for verification. Also a detailed explanation on 2 reasons for delay in project is uploaded for ready reference and verification.

EXT51800005983Mar 2019 → Mar 2021

Reason as filed by the promoterWe vide letter dated 10/02/2020, have explained the Association of Allottees of Bhaveshwar Nagar Building No.3 the reasons for delay in project timeline registered with the Maharashtra Real Estate Regulatory Authority under registration No. P51800003355 which is beyond our control. Accordingly, on 16/03/2020, the Association of Allottees of Bhaveshwar Nagar Building No.3 as per section 7(3) of the MAHA RERA Act, have given us their consent for extension of project completion upto 31/03/2021 wherein 63 numbers of Allottees were present out of total 98 numbers of Allottees of project. Out of 63

Litigation declared3

CaseCourtStatus
104,96,171,98,95,125,102,99,103,101,121,109,100,123,108,110,112,115,116,166,165,162,160,170,169,164,1167/2017Bombay High CourtDISPOSED OFF
L 90/2019BOMBAY HIGH COURTCONSENT TERM FILED ON FOURTH SEPTEMBER TWO THOUSAND NINTEEN
L 190/2019BOMBAY HIGH COURTARBITRATOR APPOINTED DIRECTED PARTIES TO MAINTAIN STATUS QUO ON FIFTEENTH MAY TWO THOUSAND NINTEEN

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000058026Shree Bhaveshwar Workers CHSLYog Reality09/02/2019

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed27

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 5)File: YOG REALITY RERA FORM 5.pdf6 Apr 2019
OtherFile: PART OCC 1ST AND 3RD FLOOR BRAHMAKUMARI.pdf29 Mar 2019
OtherFile: PART OCC 1ST AND 3RD FLOOR BRAHMAKUMARI.pdf29 Mar 2019
Certificates of CA (Form 3)File: FORM 3 CA CERTIFICATE.pdf31 Jul 2017
Declaration in FORM BFile: Form B Declaration Affidavit.pdf30 Jul 2017
Building plan approval or NA orderFile: IOD LETTER 19-07-2017.pdf29 Jul 2017
Building plan approval or NA orderFile: PLAN 1.pdf29 Jul 2017
Building plan approval or NA orderFile: LETTER-pdf-compressed.pdf29 Jul 2017
Layout approvalFile: PLAN 1.pdf29 Jul 2017
PAN CardFile: PAN YOG REALITY (1).pdf29 Jul 2017
Copy of the legal title reportFile: Title Certificate.pdf29 Jul 2017
Details of encumbrancesFile: Encumrance Letter.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: PLAN 1.pdf29 Jul 2017
Building Plan Approval (IOD)File: IOD LETTER 19-07-2017.pdf29 Jul 2017
Building Plan Approval (IOD)File: PLAN 1.pdf29 Jul 2017
Building Plan Approval (IOD)File: LETTER-pdf-compressed.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM - 1-pdf-compressed.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate.pdf29 Jul 2017
Proforma of Allotment letterFile: New Allotment Letter.pdf29 Jul 2017
Proforma of Allotment letterFile: MOFA - Yog Reality.pdf29 Jul 2017
Certificates of Architect (Form 4)File: FORM - 4- pdf-compressed.pdf29 Jul 2017
OtherFile: LOI 05-05-2014.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC REENDOSED 2017.pdf28 Jul 2017
OtherFile: LOI COPY 19-11-2016.pdf28 Jul 2017
OtherFile: REVISED LOI COPY 17-04-2017.pdf28 Jul 2017
OtherFile: Part OCC Letter 01-07-2017.pdf28 Jul 2017
OtherFile: Part OCC Letter 25-10-2016.pdf26 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 36 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Bhaveshwar Nagar Building No. 3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kurla6,700+ in Mumbai Suburban

2 kmBhaveshwar Nagar BuildinCompleted 133Lapsed / revoked 105Other 142Dot size: filed unitsN

Filed coordinates, straight-line distance. 380 registered projects within 2 km.

Builder: Yog Reality

Yog Reality has 1 registration on MahaRERA, including Bhaveshwar Nagar Building No. 3. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Bhaveshwar Nagar Building No. 3 is delayed beyond 30 Mar 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Bhaveshwar Nagar Building No. 3?

The registered promoter entity is Yog Reality, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Bhaveshwar Nagar Building No. 3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Bhaveshwar Nagar Building No. 3?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Bhaveshwar Nagar Building No. 3?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Bhaveshwar Nagar Building No. 3?

The professionals named in the filing: Architect: Mehul Vaghela of Creative Consultancy; Engineer: Dilip Parekh; Chartered Accountant: KETAN VINODCHANDRA LATHIA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Bhaveshwar Nagar Building No. 3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Bhaveshwar Nagar Building No. 3. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Bhaveshwar Nagar Building No. 3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.