Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2026Possession promisedregistration recorded completed
55 of 55Construction stages doneacross 5 buildings; every applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 75 documents Report an error

Bhanushali Nagar is a Others project by SHREE KUTCHHI BHANUSHALI SEVA SAMAJ TRUST in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800028824 on 30 Mar 2021. The registration is recorded completed; possession was promised by 30 Jun 2026.

At a glance

Project

  • NameBhanushali Nagar
  • TypeOthers
  • Location
    • Tilak Road
    • Ghatkopar Kirol
    • Kurla
    • Mumbai Suburban
    • 400077
  • Pincode400077
  • RERA no.P51800028824
  • ReraGenie IDRG-MH-28299

Builder

  • NameSHREE KUTCHHI BHANUSHALI SEVA SAMAJ TRUST
  • Entity typeTrust
  • TrusteesPratap Chhaganlal Joisher, Dinesh Laxmidas Chandra, Vallabhadas Liladhar Bhadra, Govind Liladhar Bhanushali, Mohan Sunderji Dama, Harish Dhirajlal Bhanushali, Premji Vershi Bhadra

Key dates

this monthRegisteredMar 2021PromisedJun 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on30 Mar 2021
  • Promised completion30 Jun 2026
  • Revised completionNone
  • Buildings5 building records
  • Documents filed75 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A-WINGNA270000
B-WINGNA270000
C-WINGNA260000
D-WINGNA260000
E-WINGNA240000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 8 Aug 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

55 of 55 construction stages are filed complete across 5 buildings.

A-WING100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B-WING100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
C-WING100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
D-WING100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
E-WING100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities17

As on 8 Aug 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%
Fitness CentreYes100%
Society OfficeYes100%

Parking filed331

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots331
Closed/Covered331
BuildingClosed/CoveredTotal
A-WING3131
B-WING6262
C-WING7878
D-WING1818
E-WING142142

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,111 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI24360.0
Proposed, not sanctioned14,315 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKiran Niketantilak Road, Ghatkopar East

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAccess Architects
ArchitectAshish Bhatt
EngineerJ W Consultant
EngineerSK Consultants & Engineers
Chartered AccountantRutuja Narsingh & Associates
PartnerRole in project
SHREE KUTCHHI BHANUSHALI SEVA SAMAJ TRUST-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Mar 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 26 Feb 2024

Documents filed75

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Bhanushali Nagar Form 4_compressed.pdf8 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf17 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 11 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf17 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 12 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf17 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: CC - Bhanushali Nagar.pdf1 Mar 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2410127_OC_signed.pdf26 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Bhanushali Nagar as on Dec 2023.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Bhanushali Nagar as on 31st December 23.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Bhanushali Nagar as on Sep 2023.pdf1 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Bhanushali Nagar as on Sep 2023.pdf1 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Final New Format Form 5 Bhanushali Nagar.pdf30 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Bhanushali Nagar as on June 2023.pdf22 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Bhanushali Nagar as on 30-06-2023.pdf22 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Bhanushali Nagar as on March 2023.pdf15 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Bhanushali Nagar as on 31-03-2023.pdf15 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Bhanushali Nagar as on December 2022.pdf1 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Bhanushali Nagar as on December 2022.pdf1 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Bhanushali Nagar Form 2- September 2022.pdf29 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Bhanushali Nagar as on September 2022.pdf29 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Certificate 231.pdf30 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Bhanushali Nagar Form 2- June 2022.pdf21 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Bhanushali Nagar June 2022.pdf21 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Bhanushali Nagar Form 2- 31 December 2021.pdf20 Jun 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Bhanushali Nagar Form 2- 31 March 2022.pdf20 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Bhanushali Nagar December 2021_compressed.pdf20 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Bhanushali Nagar March 2022_compressed.pdf20 Jun 2022
CERSAI detailsFile: Bhanushali Nagar.pdf10 Mar 2022
Declaration about Commencement CertificateFile: FORMAT D Bhanushali Nagar _07032022__001.pdf9 Mar 2022
Layout approvalFile: Plan Bhanushali Nagar_1-2.pdf1 Mar 2022
Building plan approvalFile: Plan Bhanushali Nagar_3-5_compressed.pdf1 Mar 2022
Building plan approvalFile: Plan Bhanushali Nagar_6-7_11zon (1).pdf1 Mar 2022
Building plan approvalFile: Plan Bhanushali Nagar_8-9.pdf1 Mar 2022
Building plan approvalFile: Plan Bhanushali Nagar_10-end_compressed.pdf1 Mar 2022
Copy of Layout Approval (in case of layout)File: Plan Bhanushali Nagar_1-2.pdf1 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: Plan Bhanushali Nagar_3-5_compressed.pdf1 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: Plan Bhanushali Nagar_6-7_11zon (1).pdf1 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: Plan Bhanushali Nagar_8-9.pdf1 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: Plan Bhanushali Nagar_10-end_compressed.pdf1 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: Further Cc.pdf28 Feb 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Bhanushali Nagar.pdf3 Feb 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Bhanushali Nagar Sept 2021.pdf3 Feb 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Bhanushali Nagar September 2021.pdf3 Feb 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Bhanushali Nagar June 2021.pdf6 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3 Bhanushali Nagar Till June 2021.pdf6 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Certificate 169.pdf6 Oct 2021
Building plan approvalFile: 2288549Amendletter_signed.pdf2 Sep 2021
Building plan approvalFile: 1843702251-19-08-2021 12-23-40_DRAWING issue_compressed-1-4-compressed.pdf2 Sep 2021
Building plan approvalFile: 1843702251-19-08-2021 12-23-40_DRAWING issue_compressed-7-9.pdf2 Sep 2021
Building plan approvalFile: 1843702251-19-08-2021 12-23-40_DRAWING issue_compressed-10-11.pdf2 Sep 2021
Building plan approvalFile: 1843702251-19-08-2021 12-23-40_DRAWING issue_compressed-5-6-1.pdf2 Sep 2021
Building Plan Approval / NA Order for plotted developmentFile: 2288549Amendletter_signed.pdf2 Sep 2021
Building Plan Approval / NA Order for plotted developmentFile: 1843702251-19-08-2021 12-23-40_DRAWING issue_compressed-1-4-compressed.pdf2 Sep 2021
Building Plan Approval / NA Order for plotted developmentFile: 1843702251-19-08-2021 12-23-40_DRAWING issue_compressed-7-9.pdf2 Sep 2021
Building Plan Approval / NA Order for plotted developmentFile: 1843702251-19-08-2021 12-23-40_DRAWING issue_compressed-10-11.pdf2 Sep 2021
Building Plan Approval / NA Order for plotted developmentFile: 1843702251-19-08-2021 12-23-40_DRAWING issue_compressed-5-6-1.pdf2 Sep 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Rera_Certificate_Bhanushaliwadi___compressed.pdf1 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A - Site Supervisor Certificate.pdf1 Sep 2021
Copy of the legal title reportFile: skbsst BWR_Title Report for RERA 28032021_compressed (1).pdf29 Mar 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Bhanuhali Nagar.pdf15 Mar 2021
Layout approvalFile: PLAN_compressed-1-2_rotated.pdf13 Mar 2021
Building plan approvalFile: PLAN_compressed-3-4_rotated.pdf13 Mar 2021
Building plan approvalFile: PLAN_compressed-5.pdf13 Mar 2021
Building plan approvalFile: PLAN_compressed-6 and 7.pdf13 Mar 2021
Building plan approvalFile: PLAN_compressed-8-9.pdf13 Mar 2021
Copy of Layout Approval (in case of layout)File: PLAN_compressed-1-2_rotated.pdf13 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: PLAN_compressed-3-4_rotated.pdf13 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: PLAN_compressed-5.pdf13 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: PLAN_compressed-6 and 7.pdf13 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: PLAN_compressed-8-9.pdf13 Mar 2021
Proforma of Allotment letterFile: Allotment Letter_Bhanushali _kacchi.pdf13 Mar 2021
Proforma of Allotment letterFile: Draft RERA AFS - Bhanushali Wadi.pdf11 Mar 2021
Details of encumbrancesFile: RERA-ENCUMBRANCE No Dues and No Ligitation Letter Signed.pdf22 Feb 2021
Commencement Certificates / NA Order for plotted developmentFile: Further CC.pdf22 Feb 2021
Declaration in FORM BFile: RERA-Affidavit cum Declaration Agreement_compressed.pdf22 Feb 2021
PAN CardFile: pan card kutchhi.pdf8 Jan 2021

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Bhanushali Nagar on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ghatkopar Kirol6,700+ in Mumbai Suburban

Builder: SHREE KUTCHHI BHANUSHALI SEVA SAMAJ TRUST

SHREE KUTCHHI BHANUSHALI SEVA SAMAJ TRUST has 1 registration on MahaRERA, including Bhanushali Nagar. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Bhanushali Nagar is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Bhanushali Nagar?

The registered promoter entity is SHREE KUTCHHI BHANUSHALI SEVA SAMAJ TRUST, a trust as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Bhanushali Nagar?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Bhanushali Nagar?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Bhanushali Nagar?

The professionals named in the filing: Architect: Access Architects; Architect: Ashish Bhatt; Engineer: J W Consultant; Engineer: SK Consultants & Engineers; Chartered Accountant: Rutuja Narsingh & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Bhanushali Nagar?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Bhanushali Nagar. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Bhanushali Nagar to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.