Completed No litigation declared Residential / Group Housing project

BHANDARI CAPITAL

By UDAYSINH SHANTILAL BHANDARI

RG-MH-21479 · RERA P53100029468 · Last updated on MahaRERA portal: 25 Mar 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.
Mar 2025Possession promisedregistration recorded completed
0 of 11Construction stages donefurthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 69 documents Report an error

BHANDARI CAPITAL is a Residential / Group Housing project by UDAYSINH SHANTILAL BHANDARI in Sangli, Maharashtra, registered with MahaRERA as P53100029468 on 29 May 2021. The registration is recorded completed; possession was promised by 31 Mar 2025. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameBHANDARI CAPITAL
  • TypeResidential / Group Housing
  • Location
    • SNO 217/1/2/2/A PLOT NO 1+2 CHINCHNI ROAD TASGAON DIST. SANGLI
    • CHINCHNI ROAD
    • Tasgaon (M Cl)
    • Tasgaon
    • Sangli
    • 416312
  • Pincode416312
  • RERA no.P53100029468
  • ReraGenie IDRG-MH-21479

Builder

  • NameUDAYSINH SHANTILAL BHANDARI
  • Entity typeIndividual

Key dates

this monthRegisteredMay 2021First promiseMar 2024Revised toMar 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on29 May 2021
  • Promised completion31 Mar 2025
  • Revised completionRevised to 31 Mar 2025 (originally 31 Mar 2024)
  • Buildings1 building record
  • Documents filed69 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BHANDARI CAPITALNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

BHANDARI CAPITAL: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 25 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed25

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots25
Closed/Covered15
Open Space10

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area806 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1801.1
Proposed, not sanctioned1,801 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJOSHI GALLI GARIOM BUILDING TASGAON 416312

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRASHANT PATIL
EngineerNANDKUMAR PATIL
Chartered Accountantgopal mundada
Chartered AccountantBhushan Picha
PartnerRole in project
UDAYSINH SHANTILAL BHANDARI-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT53100019611Mar 2024 → Mar 2025

Reason as filed by the promoterLock down during the 1st year of operation

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 May 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 May 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 May 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 May 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 25 Mar 2025

Documents filed69

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- CA certificate Q3 24-25.pdf25 Mar 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate.pdf25 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Architect certificate Q3 24-25.pdf24 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Engineer certificate Q3 24-25.pdf24 Mar 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold-booked inventory Q3 24-25.pdf24 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A- Engineer certificate for Quality 23-24.pdf24 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5- CA Certificate Annual report 23-24.pdf24 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Architect certificate Q1 24-25.pdf26 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Architect certificate Q2 24-25.pdf26 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- CA certificate Q1 24-25.pdf26 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- CA certificate Q2 24-25.pdf26 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Engineer certificate Q1 24-25.pdf26 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Engineer certificate Q2 24-25.pdf26 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold-booked inventory Q1 24-25.pdf26 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold-booked inventory Q2 24-25.pdf26 Feb 2025
Declaration in FORM BFile: Form B.pdf29 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Architect certificate Q4 23-24.pdf12 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Engineer certificate Q4 23-24.pdf12 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold-booked inventory Q4 23-24.pdf12 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- CA certificate Q4 23-24.pdf12 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Architect certificate Q3 23-24.pdf14 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Engineer certificate Q3 23-24.pdf14 Mar 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold-booked inventory Q3 23-24.pdf14 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- CA certificate Q3 23-24.pdf14 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Architect certificate Q2 23-24.pdf18 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Engineer certificate Q2 23-24.pdf18 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold-booked inventory Q2 23-24.pdf18 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- CA certificate Q2 23-24.pdf18 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5- CA Certificate Annual report 22-23.pdf18 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Architect certificate Q1 23-24.pdf12 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Engineer certificate Q1 23-24.pdf12 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A- Engineer certificate for Quality 22-23.pdf12 Aug 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold-booked inventory Q1 23-24.pdf12 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- CA certificate Q1 23-24.pdf12 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- CA Certificate Q4 22-23.pdf21 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Architect certificate Q4 22-23.pdf20 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Engineer certificate Q4 22-23.pdf20 Apr 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold-booked inventory Q4 22-23.pdf20 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Architect certificate Q3 22-23.pdf21 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Engineer certificate Q3 22-23.pdf21 Jan 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold-booked inventory Q3 22-23.pdf21 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- CA Certificate Q3 22-23.pdf21 Jan 2023
Details of encumbrancesFile: Details of encumbrance.pdf12 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Architect certificate Q2 22-23.pdf12 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Engineer certificate Q2 22-23.pdf12 Nov 2022
Disclosure of sold/ booked inventoryFile: Disclosure of sold-booked inventory Q2 22-23.pdf12 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- CA Certificate Q2 22-23.pdf12 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A- Engineer certificate for Quality 21-22.pdf3 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5- CA Certificate Annual report.pdf3 Nov 2022
Declaration about Commencement CertificateFile: Declaration about Commencement certificate.pdf16 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect certificate.pdf16 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Engineer certificate.pdf16 Jul 2022
Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory.pdf16 Jul 2022
CERSAI detailsFile: CREDAI cert.pdf16 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- CA Certificate.pdf16 Jul 2022
Layout approvalFile: BHANDARI LAYOUT.pdf24 May 2021
Building plan approvalFile: DWG BW.pdf24 May 2021
Copy of the legal title reportFile: LEGAL TITLE REPORT.pdf24 May 2021
Details of encumbrancesFile: ENCUMBRANCE CERTIFICATE.pdf24 May 2021
Copy of Layout Approval (in case of layout)File: BHANDARI LAYOUT.pdf24 May 2021
Building Plan Approval / NA Order for plotted developmentFile: DWG BW.pdf24 May 2021
Commencement Certificates / NA Order for plotted developmentFile: prashant patil sanction CERT.pdf24 May 2021
Declaration in FORM BFile: FORM B.pdf24 May 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf24 May 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE.pdf24 May 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf24 May 2021
Proforma of Allotment letterFile: AGREEMENT FORMAT.pdf24 May 2021
Proforma of Allotment letterFile: allotment letter1.pdf24 May 2021
PAN CardFile: PAN.pdf20 May 2021

How this compares with Sangli

11%of Sangli projects moved their completion datethis one moved by 12 months
29%of Sangli registrations have lapsed or been cancelledthis one is completed

Computed across the 790+ Sangli projects on ReraGenie, from their own filings.

Keep BHANDARI CAPITAL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHINCHNI ROAD790+ in Sangli

Builder: UDAYSINH SHANTILAL BHANDARI

UDAYSINH SHANTILAL BHANDARI has 1 registration on MahaRERA, including BHANDARI CAPITAL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sangli district page.

Frequently asked questions

What are my rights if BHANDARI CAPITAL is delayed beyond 31 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BHANDARI CAPITAL?

The registered promoter entity is UDAYSINH SHANTILAL BHANDARI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BHANDARI CAPITAL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BHANDARI CAPITAL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BHANDARI CAPITAL?

The professionals named in the filing: Architect: PRASHANT PATIL; Engineer: NANDKUMAR PATIL; Chartered Accountant: gopal mundada; Chartered Accountant: Bhushan Picha. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BHANDARI CAPITAL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BHANDARI CAPITAL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BHANDARI CAPITAL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.