Home / Browse projects / Bengaluru Urban, Karnataka / Beverly Hills
Beverly Hills
By Sammy’s Dreamland Co., Private Limited
RG-KA-03662 · RERA PRM/KA/RERA/1251/309/PR/181226/002260 · Last updated on RERA Karnataka portal: 25 May 2022
Source: official RERA Karnataka filing
Red flags
- 30 complaints at RERA Karnataka
- Completion date moved by 21 months
- 2 extensions taken
Clear
- Separate project account declared
Saved.
Beverly Hills is a Plotted Development project by Sammy’s Dreamland Co., Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/181226/002260 on 26 Dec 2018. Possession is promised by 27 Jun 2022. The completion date has moved by 21 months from the original filing. 30 complaints are on record with the regulator.
At a glance
Project
- NameBeverly Hills
- TypePlotted Development
- Location
- Bengaluru North
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/309/PR/181226/002260
- ReraGenie IDRG-KA-03662
Builder
- NameSammy’s Dreamland Co., Private Limited
- Entity typeCompany
- CINU85110KA1995PTC017657
- Authorized SignatoryRamesh N Ramnani
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on26 Dec 2018
- Promised completion27 Jun 2022
- Revised completionRevised to 27 Jun 2022 (originally 27 Sep 2020)
- BuildingsNot stated in filing
- Documents filed60 files
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Reason as filed by the promoterAwaiting OC
Complaints filed with RERA Karnataka30
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| 01326/2023 | - | Sammy?s Dreamland Co., Private Limited | 02/09/2023 |
| 00019/2026 | - | Sammy?s Dreamland Co., Private Limited | 06/01/2026 |
| 00276/2026 | - | Sammy?s Dreamland Co., Private Limited | 23/03/2026 |
| 00329/2026 | - | Sammy?s Dreamland Co., Private Limited | 01/04/2026 |
| 00367/2026 | - | Sammy?s Dreamland Co., Private Limited | 08/04/2026 |
| 00388/2026 | - | Sammy?s Dreamland Co., Private Limited | 15/04/2026 |
| 00411/2026 | - | Sammy?s Dreamland Co., Private Limited | 17/04/2026 |
| 00466/2026 | - | Sammy?s Dreamland Co., Private Limited | 04/05/2026 |
| 00467/2026 | - | Sammy?s Dreamland Co., Private Limited | 04/05/2026 |
| 00468/2026 | - | Sammy?s Dreamland Co., Private Limited | 04/05/2026 |
| 00486/2026 | - | Sammy?s Dreamland Co., Private Limited | 07/05/2026 |
| 00487/2026 | - | Sammy?s Dreamland Co., Private Limited | 07/05/2026 |
| 00519/2026 | - | Sammy?s Dreamland Co., Private Limited | 13/05/2026 |
| 00611/2026 | - | Sammy?s Dreamland Co., Private Limited | 29/05/2026 |
| 00679/2026 | - | Sammy?s Dreamland Co., Private Limited | 09/06/2026 |
| 00680/2026 | - | Sammy?s Dreamland Co., Private Limited | 09/06/2026 |
| 00717/2026 | - | Sammy?s Dreamland Co., Private Limited | 23/06/2026 |
| 00783/2026 | - | Sammy?s Dreamland Co., Private Limited | 04/07/2026 |
| 01141/2026 | - | Sammy?s Dreamland Co., Private Limited | 22/09/2026 |
| 01152/2026 | - | Sammy?s Dreamland Co., Private Limited | 25/09/2026 |
| 01154/2026 | - | Sammy?s Dreamland Co., Private Limited | 25/09/2026 |
| 01157/2026 | - | Sammy?s Dreamland Co., Private Limited | 28/09/2026 |
| 01158/2026 | - | Sammy?s Dreamland Co., Private Limited | 28/09/2026 |
| 01159/2026 | - | Sammy?s Dreamland Co., Private Limited | 28/09/2026 |
| 01160/2026 | - | Sammy?s Dreamland Co., Private Limited | 28/09/2026 |
| 01172/2026 | - | Sammy?s Dreamland Co., Private Limited | 01/10/2026 |
| 01176/2026 | - | Sammy?s Dreamland Co., Private Limited | 02/10/2026 |
| 01177/2026 | - | Sammy?s Dreamland Co., Private Limited | 02/10/2026 |
| 01199/2026 | - | Sammy?s Dreamland Co., Private Limited | 07/10/2026 |
| 01200/2026 | - | Sammy?s Dreamland Co., Private Limited | 07/10/2026 |
Documents filed60
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/181226/002260 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Bank Account Change ClarificationFile: Bank Account Change Clarification.pdf | 25 May 2022 |
| Clarification on Project statusFile: Clarification on Project status.pdf | 25 May 2022 |
| Clarification on Affidavit abiding to pay compensation event due to delay as per Section 18File: Clarification on Affidavit abiding to pay compensation event due to delay as per Section 1 | 25 May 2022 |
| Water NOCFile: Water NOC.pdf | 25 May 2022 |
| Clarification on renewed drawing along with renewed plan sanction letter along with final release orFile: Clarification on renewed drawing and renewed plan sanction letter.pdf | 25 May 2022 |
| Proforma AOSFile: Proforma AOS.pdf | 25 May 2022 |
| STP Design and LocationFile: STP Design and Location.pdf | 25 May 2022 |
| Allotee Details as on 5th March 2022File: Allotee Details as on 5th March 2022.xlsx | 25 May 2022 |
| Bank Account change Clarification letterFile: Bank Account Change Clarification.pdf | 11 Apr 2022 |
| CertificateFile: SDL INC.pdf | - |
| Architect Certificate for Work Completion Schedule till DateFile: Arc certificate - work completed.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Engg certificate - work completed.pdf | - |
| CA Certificate for Funds UtilizationFile: CA Certfiicate Funds Utilized.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: Arc certificate - work pending.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Engg certificate - work pending.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: CA Certificate Funds Required.pdf | - |
| AffidavitFile: Extension Affidavit.pdf | - |
| Latest Encumbrance CertificateFile: Latest EC.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: Sold and Unsold Inventory.xlsx | - |
| Document 2File: Form B Affidavit.pdf | - |
| Document 3File: RERA Extension Affidavit.pdf | - |
| BIAAP | - |
| APPROVED PLOTTING PLAN | - |
| APPROVED PLOTTING PLAN | - |
| PROFORMA OF SALE DEED | - |
| Agreement for Sale | - |
| Sale Deed Final- | - |
| SAMMYS_APPROVED_LAYOUT_22Acres-min | - |
| APPROVED PLOTTING PLAN | - |
| Allotment BH | - |
| Beverly Hills Brochure-FINAL | - |
| PROJECT SPECIFICATION | - |
| E C Compressed | - |
| NEW katha | - |
| AGREEMENTS | - |
| Final Sale Deed & RTC | - |
| Conversion Order | - |
| APPROVED PLOTTING PLAN | - |
| APPROVED PLOTTING PLAN | - |
| CHANGE OF LAND USE-FINAL FOR UPLAOD | - |
| Balance Sheet 2017 - 2018File: BALANCE SHEET 2016-17.pdf | - |
| Balance Sheet 2016 - 2017File: BALANCE SHEET 2015-16.pdf | - |
| Balance Sheet 2015 - 2016File: BALANCE SHEET 2014-15.pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: PROFIT AND LOSS 2016-17.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: PROFIT AND LOSS 2015-16.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: PROFIT AND LOSS 2014-15.pdf | - |
| Director's Report 2017 - 2018File: DIRECTORS REPORT 2016-17.pdf | - |
| Director's Report 2016 - 2017File: DIRECTORS REPORT 2015-16.pdf | - |
| Director's Report 2015 - 2016File: DIRECTORS REPORT 2014-15.pdf | - |
| Cash Flow Statement 2017 - 2018File: CASH FLOW STATEMENT 2016-17.pdf | - |
| Cash Flow Statement 2016 - 2017File: CASH FLOW STATEMENT 2015-16.pdf | - |
| Auditor's Report 2017 - 2018File: Audit Report 2016-17.pdf | - |
| Auditor's Report 2016 - 2017File: Audit Report 2015-16.pdf | - |
| Auditor's Report 2015 - 2016File: Audit Report 2014-15.pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: ITR ACK 2017-18 .pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: ITR ACK 2016-17.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ITR ACK 2015-16.pdf | - |
| AFFIDAVIT FINAL | - |
| Prospectus/BrochureFile: Brochure.pdf | - |
| Plot Excel SheetFile: PRM_KA_RERA_1251_309_PR_181226_002260.xlsx | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Beverly Hills on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: Sammy’s Dreamland Co., Private Limited
Sammy’s Dreamland Co., Private Limited has 1 registration on RERA Karnataka, including Beverly Hills. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Beverly Hills is delayed beyond 27 Jun 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Beverly Hills?
The registered promoter entity is Sammy’s Dreamland Co., Private Limited, a company as per the filing. Its CIN U85110KA1995PTC017657 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Beverly Hills?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Beverly Hills?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
What should I check before booking in Beverly Hills?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback