ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / BELVEDERE by UKN AIRPORT DISTRICT -PHASE 1

Registration approved Residential/Group Housing project

BELVEDERE by UKN AIRPORT DISTRICT -PHASE 1

By U.K.N. PROPERTIES PRIVATE LIMITED

RG-KA-10618 · RERA PRM/KA/RERA/1251/309/PR/171014/000527

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka
  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • Separate project account declared
Nov 2023Possession promisedmoved 21 months from the original
1Complaints at RERA Karnatakaon this registration
Jump to the 83 documents Report an error

BELVEDERE by UKN AIRPORT DISTRICT -PHASE 1 is a Residential/Group Housing project by U.K.N. PROPERTIES PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/171014/000527 on 14 Oct 2017. Possession is promised by 2 Nov 2023. The completion date has moved by 21 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameBELVEDERE by UKN AIRPORT DISTRICT -PHASE 1
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/309/PR/171014/000527
  • ReraGenie IDRG-KA-10618

Builder

  • NameU.K.N. PROPERTIES PRIVATE LIMITED
  • Entity typeCompany
  • CINU70102KA1997PTC022387
  • Authorized SignatoryGAUTAM U NAMBISAN
  • DirectorsRAVINDRAN .K, VINUTHA KONDUR
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredOct 2017First promiseFeb 2022Revised toNov 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on14 Oct 2017
  • Promised completion2 Nov 2023
  • Revised completionRevised to 2 Nov 2023 (originally 3 Feb 2022)
  • Buildings3 building records
  • Documents filed83 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block 1---1710171
Block 2---055
Block 3---2490249

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etcNot applicable
Basic work of Water supply, Sanitary and ElectrificationNot applicable
Dadoing, Skirting, Flooring, Tiles work (All types)Not applicable
Railing and Grill fixingNot applicable
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
PaintingNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area18,717 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 125.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVIJAY AND ANJALI YAGNIK ARCHITECTS
EngineerBASE ENGINEERING SERVICES

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionFeb 2022 → Nov 2022

No reason recorded in the filing

EX/PRM/KA/RERA/1251/309/PR/220912/000527Nov 2022 → Nov 2023

Reason as filed by the promoterForce Majeure

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
00736/2025-U.K.N. PROPERTIES PRIVATE LIMITED14/05/2025

Documents filed83

As listed on the registration, under the names the promoter filed them with; the newest 80 of 83 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/171014/000527 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Certificate of Incorporation.pdf-
Architect Certificate for Work Completion Schedule till DateFile: EX 1_Architect Certificate.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: EX-5_Engineer Certificate.pdf-
CA Certificate for Funds UtilizationFile: Ex 3- CA Certificate.pdf-
Architect Certificate for Pending Work Completion Schedule.File: EX 2_Architect Certificate.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: EX-6_Engineer Certificate.pdf-
CA Certificate for Funds required for Project CompletionFile: Ex 4 - CA Certificate.pdf-
AffidavitFile: Affidavit.pdf-
Latest Encumbrance CertificateFile: EC Belvedere.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
Document 1File: Reason for delay.pdf-
COMMENCEMENT AND BUILDING LICENSE-
Sanction plan-
Layout plan-
Belvedere Proforma Sale Deed-
AGREEMENT TO SELL-
Merged JDs-
Section plan(1)-
Development plan-
Allotment Letter Belvedere-
BROCHURE-
NOC-
SPECIFICATION-
EC`s-
Khata-
JDA1-
title-
Convs-
193332-
193332-
193332-
RD-
33 -NOC -Fire-
38 -NOC -Airport Authority of India-
37 -NOC -BESCOM-
32 -NOC - Doddajala Village Panchayat-
34 -CFE KSPCB-
35 -NOC -MOEF-
36 -NOC -BSNL-
193332-
Unnamed document-
193332-
193332-
193332-
193332-
193332-
belvedere_stability-
Section plan1-
Balance Sheet 2015 - 2016File: 15-16 BS.pdf-
Balance Sheet 2014 - 2015File: 14-15 BS.pdf-
Balance Sheet 2013 - 2014File: 2013-14 BS.pdf-
Audited Profit and Loss Statement 2015 - 2016File: 15-16 PL.pdf-
Audited Profit and Loss Statement 2014 - 2015File: 14-15 PL.pdf-
Audited Profit and Loss Statement 2013 - 2014File: 2013-14 PL.pdf-
Director's Report 2015 - 2016File: Directors report -2015-16.pdf-
Director's Report 2014 - 2015File: Directors report -2014-15.pdf-
Director's Report 2013 - 2014File: Directors report -2013-14.pdf-
Cash Flow Statement 2015 - 2016File: 15-16 CFS.pdf-
Cash Flow Statement 2014 - 2015File: 14-15 CFS.pdf-
Auditor's Report 2015 - 2016File: 15-16 AR.pdf-
Auditor's Report 2014 - 2015File: 14-15 AUDITOR'S REPORT.pdf-
Auditor's Report 2013 - 2014File: 2013-14 AUDITORS REPORT.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: 3 -UKN, IT return -2015-16.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: 4 -UKN, IT return -2014-15.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: 2013-14 ITR.pdf-
Affidavit cum declaration-
Prospectus/BrochureFile: The Belvedere by UKn-e-brochure-.pdf-
Advertisement Copy 1File: Belvedere Hoarding.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_309_PR_171014_000527.xlsx-
Loan raised documentFile: Sanction letter - 45 cr.pdf-
Road cutting permission letter issued by the planning Authority for laying Water supply line, sanitary line, UFile: BESCOM NOC for LT Power dated 13 10 2023 for Belvedere Project_compressed.pdf-
NOC issued by the Fire Force department after completion of workFile: FIRE & EMERGENCY -Partial Clearance Certificate dtd -15 09 2023(Belvedere).pdf-
Occupancy CertificateFile: Occupancy Certificate by Doddajala Grama Panchayat dated 18 10 2023 (Belvedere Project).pd-
Consent for operation issued by KSPCBFile: KSPCB -extension of CFE validity dated 15 05 2023(Belvedere).pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: Blank.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: BESCOM NOC for LT Power dated 13 10 2023 for Belvedere Project_compressed.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: Drinking Water NOC from Grama Panchayat dated 15 12 2014.pdf-
Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: Sepecification.pdf-
Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: Completed.pdf-
Architect certificate for having completed the work(in format no 5)File: completion_Form5 Architect certificate.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 21 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep BELVEDERE by UKN AIRPORT DISTRICT -PHASE 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: U.K.N. PROPERTIES PRIVATE LIMITED

U.K.N. PROPERTIES PRIVATE LIMITED has 2 registrations on RERA Karnataka, including BELVEDERE BY UKN AIRPORT DISTRICT -PHASE 2 and BELVEDERE by UKN AIRPORT DISTRICT -PHASE 1. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if BELVEDERE by UKN AIRPORT DISTRICT -PHASE 1 is delayed beyond 2 Nov 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of BELVEDERE by UKN AIRPORT DISTRICT -PHASE 1?

The registered promoter entity is U.K.N. PROPERTIES PRIVATE LIMITED, a company as per the filing. Its CIN U70102KA1997PTC022387 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in BELVEDERE by UKN AIRPORT DISTRICT -PHASE 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against BELVEDERE by UKN AIRPORT DISTRICT -PHASE 1?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at BELVEDERE by UKN AIRPORT DISTRICT -PHASE 1?

The professionals named in the filing: Architect: VIJAY AND ANJALI YAGNIK ARCHITECTS; Engineer: BASE ENGINEERING SERVICES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BELVEDERE by UKN AIRPORT DISTRICT -PHASE 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BELVEDERE by UKN AIRPORT DISTRICT -PHASE 1. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BELVEDERE by UKN AIRPORT DISTRICT -PHASE 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.