Home / Browse projects / Bengaluru Urban, Karnataka / BELLEZEA-PHASE IV

Registration approved No litigation declared Residential/Group Housing project

BELLEZEA-PHASE IV

By M/S NAMBIAR BUILDERS PVT LTD

RG-KA-24076 · RERA PRM/KA/RERA/1251/308/PR/180521/001786 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 45 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Jan 2027Possession promisedmoved 45 months from the original
6 of 15Construction stages donefurthest along: Basic work of Water supply, 98%
20 of 48Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 91 documents Report an error

BELLEZEA-PHASE IV is a Residential/Group Housing project by M/S NAMBIAR BUILDERS PVT LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/180521/001786 on 21 May 2018. Possession is promised by 11 Jan 2027. The completion date has moved by 45 months from the original filing. 28 of the 48 units on this registration are recorded sold or booked, and 6 of 15 construction stages are filed complete.

At a glance

Project

  • NameBELLEZEA-PHASE IV
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/308/PR/180521/001786
  • ReraGenie IDRG-KA-24076

Builder

  • NameM/S NAMBIAR BUILDERS PVT LTD
  • Entity typeCompany
  • CINU45201KA2009PTC050747
  • Authorized SignatoryRamesh Nambiar
  • DirectorsRamesh Nambiar, Ramesh Nambiar, Ratheesh Nambiar
  • Other registrations1 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredMay 2018First promiseApr 2023Revised toJan 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on21 May 2018
  • Promised completion11 Jan 2027
  • Revised completionRevised to 11 Jan 2027 (originally 11 Apr 2023)
  • Buildings5 building records
  • Documents filed91 files

Current status

58%28 of 48 units booked
5.6%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK A---11011
BLOCK B---101
BLOCK C---10010
BLOCK D---303
BLOCK E---23023

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 15 construction stages are filed complete. The stage furthest along is Basic work of Water supply, at 98%.

Building: 96% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)Not applicable
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc85%
Basic work of Water supply, Sanitary and Electrification98%
Dadoing, Skirting, Flooring, Tiles work (All types)85%
Railing and Grill fixing80%
Electrification, Water supply and Sanitary Finishing97%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)97%
Painting97%
Elevation work97%
Internal and External work including landscapes as per santioned drawings97%

Progress on shared amenities41

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes97%
Internal Roads & FootpathsYes100%
Sewage and Drainage SystemYes100%
Parks & Tree plantingYes97%
Street LightingYes98%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes97%
Water conservationYes92%
Energy managementYes90%
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes98%
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes89%
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes91%
ElectricityYes85%
Smart Home AutomationYes0%
CCTV SurveillanceYes0%
Club HouseYes100%
Community HallYes100%
Outdoor Sports facilityYes100%
Indoor Sports facilityYes100%
Swimming PoolYes100%
GymYes100%
ParksYes100%
Power BackupYes94%
GasNoNot applicable
Water and SanitationYes90%
Air Conditioning And incerntionNoNot applicable
StaircasesNoNot applicable
LiftsNoNot applicable
Staircases and Lift lobbies, corridor,lobbies, corridorNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes0%
Outer WallYes90%
Open parking areas and common storage spacesYes80%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area25,495 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 112.48 cr
Cost incurredRs 6.28 cr
Spent of the estimate5.58%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 77.98 crRs 3.90 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 14.68 cr-
On-site expenditure-Site OverheadRs 13.55 crRs 1.13 cr
On-site expenditure-Salaries of workersRs 3.52 crRs 1.00 cr
On-site expenditure-Consultants FeesRs 2.09 crRs 25.00 lakh
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 65.58 lakh-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectC SUNDARAM
EngineerC SUNDARAM

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionApr 2023 → Jan 2024

No reason recorded in the filing

EX/PRM/KA/RERA/1251/308/PR/231204/001786Jan 2024 → Jan 2025

Reason as filed by the promoterothers

ExtensionJan 2025 → Jan 2027

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed91

As listed on the registration, under the names the promoter filed them with; the newest 80 of 91 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/180521/001786 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4_Phase IV FY 26-27 Q2.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5_Phase IV FY 26-27 Q2.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6_Phase IV FY 26-27 Q2.pdf14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4_Phase IV FY 26-27 Q1.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5_Phase IV FY 26-27 Q1.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6_Phase IV FY 26-27 Q1.pdf14 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4_Phase IV FY 25-26 Q4.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5_Phase IV FY 25-26 Q4.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6_Phase IV FY 25-26 Q4.pdf15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4_ BELLEZEA-Phase IV FY 25-26 Q3.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5_Phase IV FY 25-26 Q3.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 - Q3 FY 25-25 Bellezea Ph 4.pdf15 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Jan 2026
CertificateFile: certificate.pdf-
Project Details-
Architect Certificate for Work Completion Schedule till DateFile: Form EX1- Phase 4.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Form EX 5 Phase IV.pdf-
CA Certificate for Funds UtilizationFile: Ex-3.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Form EX2 Bellezea Phase 4E.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Form EX 6 Phase IV.pdf-
CA Certificate for Funds required for Project CompletionFile: Ex-4.pdf-
AffidavitFile: Form EX7.pdf-
Latest Encumbrance CertificateFile: EC merged.pdf-
Consent letter from 2/3rd of AllotteesFile: Consent Letter - Phase4 Compressed.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
Document 1File: Form B.pdf-
BMRDA sanction letter-
BMRDA PLAN-
BMRDA PLAN-
NAMBIAR-
NAMBIAR-
title-
BMRDA PLAN-
BMRDA PLAN-
NAMBIAR PAN latest (1)-
BROUCHURE-
Bellezea Phase 4 Specifications pdf-
ec (1)-
khatha tax paid-
joint development agreement (1)-
title new-
Conversion order-
NAMBIAR-
NAMBIAR-
NAMBIAR-
relinquishment deed ph iv-
NAMBIAR-
NAMBIAR-
NAMBIAR-
NAMBIAR-
NAMBIAR-
NAMBIAR-
NAMBIAR-
NAMBIAR-
Unnamed document-
NAMBIAR-
NAMBIAR-
NAMBIAR-
NAMBIAR-
NAMBIAR-
NAMBIAR-
NAMBIAR-
NAMBIAR-
BMRDA PLAN-
BMRDA PLAN-
NAMBIAR-
D&M COMPRESSED-
Balance Sheet 2016 - 2017File: balance sheet 16-17.pdf-
Balance Sheet 2015 - 2016File: Balance Sheet 2015-16.pdf-
Balance Sheet 2014 - 2015File: Balance Sheet 2014-15.pdf-
Audited Profit and Loss Statement 2016 - 2017File: P & L 16-17.pdf-
Audited Profit and Loss Statement 2015 - 2016File: P & L 2015-16.pdf-
Audited Profit and Loss Statement 2014 - 2015File: P & L 2014-15.pdf-
Director's Report 2016 - 2017File: NAMBIAR.pdf-
Director's Report 2015 - 2016File: Director's Report_2016.pdf-
Director's Report 2014 - 2015File: NAMBIAR.pdf-
Cash Flow Statement 2016 - 2017File: Cashflow 16-17.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
Bellezea Phase III-OngoingApr 2021Not delivered

How this compares with Bengaluru Urban

58%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 45 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep BELLEZEA-PHASE IV on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: M/S NAMBIAR BUILDERS PVT LTD

M/S NAMBIAR BUILDERS PVT LTD has 2 registrations on RERA Karnataka, including BELLEZEA-PHASE IV and ELLEGANZA PHASE I. Its filings declare 2 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if BELLEZEA-PHASE IV is delayed beyond 11 Jan 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of BELLEZEA-PHASE IV?

The registered promoter entity is M/S NAMBIAR BUILDERS PVT LTD, a company as per the filing. Its CIN U45201KA2009PTC050747 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in BELLEZEA-PHASE IV?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at BELLEZEA-PHASE IV?

The professionals named in the filing: Architect: C SUNDARAM; Engineer: C SUNDARAM. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BELLEZEA-PHASE IV?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BELLEZEA-PHASE IV. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BELLEZEA-PHASE IV to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.