ReraGenieLog inGet a buyer report

Home / Browse projects / Nashik, Maharashtra / BAPHANA EMPIRE

Registration lapsed No litigation declared Residential / Group Housing project

BAPHANA EMPIRE

By Baphana Infra

RG-MH-14215 · RERA P51600031444 · Last updated on MahaRERA portal: 19 Jun 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
15 of 55Construction stages doneacross 5 buildings; furthest along: Slabs of Super Structure, 78%
0Complaints at MahaRERAon this registration
Jump to the 75 documents Report an error

BAPHANA EMPIRE is a Residential / Group Housing project by Baphana Infra in Nashik, Maharashtra, registered with MahaRERA as P51600031444 on 23 Oct 2021. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NameBAPHANA EMPIRE
  • TypeResidential / Group Housing
  • Location
    • MAIN ROAD
    • NEAR ASHOK ANNA BANKAR BANK
    • Pimpalgaon Baswant
    • Niphad
    • Nashik
    • 422209
  • Pincode422209
  • RERA no.P51600031444
  • ReraGenie IDRG-MH-14215

Builder

  • NameBaphana Infra
  • Entity typeOthers
  • Named personsVijayraj Lakhichand Baphana, Kiran Vijayraj Baphana

Key dates

4 months past promisethis monthRegisteredOct 2021First promiseJun 2024Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on23 Oct 2021
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2024)
  • Buildings5 building records
  • Documents filed75 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA72000
WING BNA60000
WING CNA60000
WING DNA30000
WING ENA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 19 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Slabs of Super Structure, at 78%.

WING A40%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure78%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises31%
Sanitary Fittings within the flats / premises31%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING B40%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure78%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises31%
Sanitary Fittings within the flats / premises31%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING C40%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure78%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises31%
Sanitary Fittings within the flats / premises31%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING D40%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure78%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises31%
Sanitary Fittings within the flats / premises31%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING E40%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure78%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises31%
Sanitary Fittings within the flats / premises31%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed24

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots24
Closed/Covered24
BuildingClosed/CoveredTotal
WING A77
WING B66
WING C66
WING D33
WING E22

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,315 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityNashik Municipal Corporation
Permissible FSI2604.56
Proposed, not sanctioned2,605 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDHANSHREE BANK STREET PIMPALGAON B NASHIK MAHARASHTRA

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSAGAR KABRE
EngineerMANISH BOTHARA
Chartered AccountantCA Chetan Bumb
Chartered AccountantBHAVANA LOYA
PartnerRole in project
Baphana Infra-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51600024175Jun 2024 → Jun 2026

Reason as filed by the promoterThe project has faced unexpected delays in construction due to factors like labour shortage, inclement weather or logistical challenges etc., therefore I hereby apply for extention.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Oct 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Oct 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Oct 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed75

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1 Q4 24-25.pdf19 Jun 2026
Form 2File: FORM 2 Q4 24-25.pdf19 Jun 2026
Form 3File: Baphana Empire Form 3 Q4_0002.pdf19 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Q4 24-25.pdf19 Jun 2026
Form 1File: FORM 1 Baphana Empire Architect Certificate Q1_0001.pdf19 Jun 2026
Form 2File: FORM 2 baphana Empire Engineers Certificate Q1_0001.pdf19 Jun 2026
Form 3File: Baphana Empire Form 3 Q1_0001.pdf19 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Q1 25-26.pdf19 Jun 2026
Form 1File: Baphana Empire Architect Certificate Q2_0001_0001.pdf19 Jun 2026
Form 2File: baphana Empire Engineers Certificate Q2_0001_0001.pdf19 Jun 2026
Form 3File: Baphana Empire Form 3 Q2_0001_0001.pdf19 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Q2 25-26.pdf19 Jun 2026
Form 1File: Baphana Empire Architect Certificate Q3_0001_0001.pdf19 Jun 2026
Form 2File: baphana Empire Engineers Certificate Q3_0001_0001.pdf19 Jun 2026
Form 3File: Baphana Empire Form 3 Q3_0001.pdf19 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Q3 25-26.pdf19 Jun 2026
Form 1File: Baphana Empire Architect Certificate Q4_0001_0001.pdf19 Jun 2026
Form 2File: baphana Empire Engineers Certificate Q4_0001_0001.pdf19 Jun 2026
Form 3File: Baphana Empire Form 3 Q4_0001.pdf19 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Q4 25-26.pdf19 Jun 2026
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 (2023-24).pdf31 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate - Q1.pdf29 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate - Q2.pdf29 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate - Q3.pdf29 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Baphana Infra Q1 24-25.pdf29 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Baphana Infra Q2 24-25.pdf29 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Baphana Infra Q3 24-25.pdf29 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate_Q1.pdf29 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate _Q2.pdf29 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate _Q3.pdf29 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 21-22.pdf4 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 22-23.pdf4 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 23-24.pdf4 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold and unsold inventory circular 29.pdf4 Jul 2024
Declaration in FORM BFile: Form B Declaration.pdf28 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect q1.pdf28 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: q3.pdf28 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: q 4.pdf28 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q1.pdf28 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q2.pdf28 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q3.pdf28 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q4.pdf28 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q1 Engineer certificate 22-23.pdf28 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q4 engineer certificate 22-23.pdf28 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engenieer certificate Q 1 23-24.pdf28 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engenieer certificate Q 2 23-24.pdf28 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engenieer certificate Q 3 23-24.pdf28 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engenieer certificate Q 4 23-24.pdf28 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1_merged.pdf28 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1_merged.pdf28 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1_merged.pdf28 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1_merged (1).pdf28 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1_merged.pdf28 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1_merged (1).pdf28 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Baphana Infra Rera Form 5.pdf28 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.PDF28 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA Cert.PDF28 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Baphana Infra RERA Audit.PDF30 Sep 2022
Disclosure of sold/ booked inventoryFile: ANNEXURE A.PDF12 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate form3 Bafana.PDF12 Oct 2021
Proforma of Allotment letterFile: PROFORMA OF ALLOTMENT.PDF12 Oct 2021
Proforma of Allotment letterFile: SAMPLE SALE FORMAT Phase 1.pdf12 Oct 2021
OtherFile: LETTER OF AUTHORISATION.pdf12 Oct 2021
Layout approvalFile: Plan Photo.pdf6 Oct 2021
Building plan approvalFile: Plan Photo.pdf6 Oct 2021
Copy of the legal title reportFile: Legal Title Report.pdf6 Oct 2021
Copy of Layout Approval (in case of layout)File: Plan Photo.pdf6 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: Plan Photo.pdf6 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: Development Permission and Commencement Certificate.pdf6 Oct 2021
Declaration in FORM BFile: FORM B (Affidavit cum Declaration).pdf6 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf6 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf6 Oct 2021
PAN CardFile: HUF PAN CARD.PDF5 Oct 2021
Details of encumbrancesFile: Non Encumberance Certificate.PDF5 Oct 2021
Declaration about Commencement CertificateFile: Declaration about Commencement Cert.PDF5 Oct 2021

How this compares with Nashik

10%of Nashik projects moved their completion datethis one moved by 24 months
19%of Nashik registrations have lapsed or been cancelledthis one is among them

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BAPHANA EMPIRE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR ASHOK ANNA BANKAR BANK4,100+ in Nashik

Builder: Baphana Infra

Baphana Infra has 1 registration on MahaRERA, including BAPHANA EMPIRE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What does it mean that BAPHANA EMPIRE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if BAPHANA EMPIRE is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BAPHANA EMPIRE?

The registered promoter entity is Baphana Infra, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BAPHANA EMPIRE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for BAPHANA EMPIRE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BAPHANA EMPIRE?

The professionals named in the filing: Architect: SAGAR KABRE; Engineer: MANISH BOTHARA; Chartered Accountant: CA Chetan Bumb; Chartered Accountant: BHAVANA LOYA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BAPHANA EMPIRE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BAPHANA EMPIRE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BAPHANA EMPIRE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.