Home / Browse projects / Mumbai Suburban, Maharashtra / Avis Residency

Registered No litigation declared Residential / Group Housing project

Avis Residency

By Avi housing Realtors

RG-MH-70984 · RERA P51800012791 · Last updated on MahaRERA portal: 10 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 84 months
  • 5 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 84 months from the original
6 of 11Construction stages donefurthest along: Slabs of Super Structure, 95%
30 of 63Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 67 documents Report an error

Avis Residency is a Residential / Group Housing project by Avi housing Realtors in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800012791 on 7 Sep 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 84 months from the original filing. 33 of the 63 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameAvis Residency
  • TypeResidential / Group Housing
  • Location
    • R N Narkar marg
    • Ghatkopar East
    • Kurla
    • Mumbai Suburban
    • 400077
  • Pincode400077
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800012791
  • ReraGenie IDRG-MH-70984

Builder

  • NameAvi housing Realtors
  • Entity typePartnership
  • GSTIN27AASFA7447B1ZB
  • PartnersParesh Vrajlal Chabhadia, Priyank Chetan Chabhadia

Key dates

this monthRegisteredSep 2017First promiseDec 2019Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on7 Sep 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed67 files

Current status

52%33 of 63 units booked

Figures as on 10 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Avis ResidencyNA181861263

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 95%.

Avis Residency: 93% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%

Progress on shared amenities15

As on 10 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes50%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed80

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots80
Closed/Covered78
Open Space2

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,673 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on24 Jul 2026

Approvals and building plan

Sanctioning authorityBMC
Permissible FSI4293.18
Proposed, not sanctioned4,293 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch177 Ramani Sadan Garodia Nagar Ghatkopar Mumbai 400077

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVC Architects
EngineerNP3 Architects & Consultants
EngineerSankalp Enterprises
EngineerV K DESIGN CONSULTANCY
EngineerVK DESIGN CONSULTANCY
Chartered AccountantDharmesh B. Mehta & Co.
Chartered AccountantDharmesh B. Mehta & Co
Chartered AccountantNehali & Co
PartnerRole in project
Avi housing Realtors-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800010729Dec 2019 → Aug 2022

Reason as filed by the promoterThe Developer were working promptly to complete the project on or before the due line as undertaken before this Hon’ble Authority. In the year 2018-2019 the building’s brick work completed and the finishing work was under process. In the meantime some the person concerned with the said development project with intent to malafied intention lodge some false and frivolious criminal as well as civil prosecution there by the developers were suffered huge mental agony and the development work was substantially affected. During the said period due to said criminal and civil litigation the interse dis

EXT51800019289Dec 2019 → Oct 2024

Reason as filed by the promoterThe primary cause of the project delay stemmed from the process of obtaining permissions from the authorities, which consequently postponed the construction of the building. However, a significant portion of the construction work has been completed, and progress is underway on the parking tower, and it will be finished within the extended deadline.

EXT51800015057Dec 2019 → Feb 2024

Reason as filed by the promoterThe project was delayed due to a number of reason one being the lockdown which slowed down the work, the next reason is that there was delay in getting plans approved from the authorities which caused the project to get delayed

EXT51800025667Dec 2019 → Jun 2025

Reason as filed by the promoter1. Project is nearing to completion 2. Consent of 71.43 % of Allotees uploaded for Extension 3. The Revised Form B is uploaded in Other tab No. 1 and also in the main Application 4. PERT Chart is uploaded in Other Tab No. 2 and also in Other Technical Tab of the Main Application 5. Reasons for Delay in project Completion Uploaded in Other Tab No. 3

EA11082622088Dec 2019 → Dec 2026

Reason as filed by the promoterThe Project is approximately 85% completed. The consent of 54.55% of allottees has been uploaded in support of this extension application. TAB 1 - Format B Uploaded TAB 2 - Form B Uploaded TAB 3 - Declaration for extension TAB 4 - PERT Chart TAB 5 - Notarised Declaration TAB 6 - FORM 2A Uploaded TAB 7 & 8 - FORM 5 Uploaded TAB 9 to 20 - FORM 1,2 & 3 Uploaded The Project got delayed due to following reasons:- The delay in completion of the project is due to the pending Part Occupancy Certificate (OC) from MCGM and certain correction and rectification works required as per the revised sanctioned

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 21 Feb 2023

Documents filed67

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: form 1 march 25.pdf10 Aug 2026
Form 2File: Form 2 31 03 2025.pdf10 Aug 2026
Form 3File: Form 3_March25.pdf10 Aug 2026
Disclosure of Sold and Booked InventoryFile: Form 3_March25_organized.pdf10 Aug 2026
Form 1File: form 1 june 25.pdf10 Aug 2026
Form 2File: Form 2 30 06 2025.pdf10 Aug 2026
Form 3File: Form 3 _June 25.pdf10 Aug 2026
Disclosure of Sold and Booked InventoryFile: Form 3 _June 25_organized.pdf10 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A 25-26.pdf10 Aug 2026
Other - TechnicalFile: pert chart avi (2).pdf31 Mar 2025
Declaration in FORM BFile: avi rera.pdf22 Mar 2025
Declaration in FORM BFile: avi rera.pdf22 Mar 2025
Declaration in FORM BFile: avi rera.pdf22 Mar 2025
Declaration in FORM BFile: avi rera.pdf22 Mar 2025
Disclosure of sold/ booked inventoryFile: sold inventory rera.pdf19 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Adobe Scan 29 Jan 2025.pdf29 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 25.pdf27 Jan 2025
Certificates of CA (Form 3)File: form 3 rera.pdf23 Jan 2025
Certificates of CA (Form 3)File: form 3 rera.pdf23 Jan 2025
Declaration in FORM BFile: rera.pdf27 Dec 2024
Declaration in FORM BFile: rera.pdf27 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf7 May 2024
Disclosure of sold/ booked inventoryFile: 44FA647E.pdf7 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 23-24.pdf7 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf2 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf2 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA renewal-1.pdf25 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA renewal-1.pdf25 Apr 2024
Certificates of CA (Form 3)File: Form 1-compressed.pdf25 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 21-22.pdf19 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 22-23.pdf19 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 23-24.pdf19 Apr 2024
Declaration in FORM BFile: Form B rera.pdf15 Apr 2024
Declaration in FORM BFile: Form B rera.pdf15 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A fy 2021-22.pdf6 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - Fy 2022-23.pdf6 Apr 2024
CERSAI detailsFile: cersai declaration.pdf6 Apr 2024
CERSAI detailsFile: cersai declaration.pdf6 Apr 2024
CERSAI detailsFile: cersai declaration.pdf6 Apr 2024
CERSAI detailsFile: cersai declaration.pdf6 Apr 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2311934_OC_signed.pdf21 Feb 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2322427_OC_signed.pdf21 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: EE(BP)ESII Certificate.pdf9 Sep 2021
Disclosure of sold/ booked inventoryFile: rera disclousre.pdf9 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: oct - dec 2020.pdf6 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: jan - march 2021.pdf6 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: apr- june 2021.pdf6 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: RERA Certificate 17-18.pdf6 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: RERA Certificate 18-19.pdf6 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RERA Certificate 19-20.pdf6 Sep 2021
Declaration about Commencement CertificateFile: declaration of cc.pdf5 Sep 2021
Disclosure of sold/ booked inventoryFile: disclosure of inventory.pdf5 Sep 2021
OtherFile: application of bda.pdf5 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA Certificate.pdf4 Sep 2021
Certificates of CA (Form 3)File: AHR pan card.pdf1 Aug 2017
Building plan approvalFile: AHR-IOD-ilovepdf-compressed.pdf31 Jul 2017
Layout approvalFile: ilovepdf_jpg_to_pdf.pdf31 Jul 2017
PAN CardFile: AHR Pancard.pdf31 Jul 2017
Copy of the legal title reportFile: AHR Tital certificate.pdf31 Jul 2017
Details of encumbrancesFile: new doc.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: ilovepdf_jpg_to_pdf.pdf31 Jul 2017
Building Plan Approval (IOD)File: AHR-IOD-ilovepdf-compressed.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: AHR CC (1)-ilovepdf-compressed.pdf31 Jul 2017
Declaration in FORM BFile: AHR From B.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Certificate of Architect.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf31 Jul 2017
Proforma of Allotment letterFile: Sale Agreemen FINAL DRAFT East (1).pdf31 Jul 2017

How this compares with Mumbai Suburban

52%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 84 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Avis Residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ghatkopar East6,700+ in Mumbai Suburban

2 kmAvis ResidencyCompleted 134Lapsed / revoked 105Other 141Dot size: filed unitsN

Filed coordinates, straight-line distance. 380 registered projects within 2 km.

Builder: Avi housing Realtors

Avi housing Realtors has 1 registration on MahaRERA, including Avis Residency. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Avis Residency is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Avis Residency?

The registered promoter entity is Avi housing Realtors, a partnership as per the filing. Its GSTIN 27AASFA7447B1ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Avis Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Avis Residency?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Avis Residency?

The professionals named in the filing: Architect: VC Architects; Engineer: NP3 Architects & Consultants; Engineer: Sankalp Enterprises; Engineer: V K DESIGN CONSULTANCY; Engineer: VK DESIGN CONSULTANCY; Chartered Accountant: Dharmesh B. Mehta & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Avis Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Avis Residency. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Avis Residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.