AVANTIKAA is a Residential/Group Housing project by s2 homes in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/180120/001239 on 20 Jan 2018. Possession is promised by 10 Aug 2017.
At a glance
Project
- NameAVANTIKAA
- TypeResidential/Group Housing
- Location
- Anekal
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/308/PR/180120/001239
- ReraGenie IDRG-KA-40181
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on20 Jan 2018
- Promised completion10 Aug 2017
- Revised completionNone
- Buildings1 building record
- Documents filed48 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| 2.5 | - | - | - | 90 | 0 | 90 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| COMPLETION | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | - |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | Yes | - |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | UMA NIRMALA P |
| Engineer | UMA NIRMALA P |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed48
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/180120/001239 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: s2 homes registration certificate.pdf | - |
| Commencement Certificate Avantikaa | - |
| Approved Plan Avantikaa | - |
| Approved Plan Avantikaa | - |
| Avantikaa Sale Deed Draft | - |
| Avantikaa Sale Agreement Draft | - |
| S2 Homes Sale Deed - Avantikaa | - |
| Approved Plan Avantikaa | - |
| Avanthikaa 9 floor plan approved | - |
| Flat Allotment Letter Draft | - |
| Avantika - 3 Fold Brochure | - |
| NOC-POLLUTION Avantikaa | - |
| Avantika - 3 Fold Brochure | - |
| EC from 01-04-2004 to 21-05-2016 | - |
| katha-1 | - |
| S2 Homes Sale Deed - Avantikaa | - |
| Conversion order Avantikaa | - |
| Conversion order Avantikaa | - |
| NOC FIRE AVANTIKAA | - |
| NOC-AIRPORT-Avanthikaa | - |
| NOC BESCOM AVANTIKAA | - |
| NOC POLLUTION Avantikaa | - |
| NOC-BSNC-AVANTIKAA | - |
| Balance Sheet 2015 - 2016File: balance sheet.pdf | - |
| Balance Sheet 2014 - 2015File: S2 Homes ITR 20152016 balance sheet.pdf | - |
| Balance Sheet 2013 - 2014File: S2 Homes ITR 20152016 balance sheet.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: p&l.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: S2 Homes ITR 20152016 p&L.pdf | - |
| Audited Profit and Loss Statement 2013 - 2014File: S2 Homes ITR 20152016 p&L.pdf | - |
| Director's Report 2015 - 2016File: director report.pdf | - |
| Director's Report 2014 - 2015File: S2 Homes ITR 20152016 auditor report.pdf | - |
| Director's Report 2013 - 2014File: S2 Homes ITR 20152016 auditor report.pdf | - |
| Cash Flow Statement 2015 - 2016File: cashflow.pdf | - |
| Cash Flow Statement 2014 - 2015File: S2 Homes ITR 20152016 cash flow.pdf | - |
| Auditor's Report 2015 - 2016File: auditor report.pdf | - |
| Auditor's Report 2014 - 2015File: S2 Homes ITR 20152016 auditor report.pdf | - |
| Auditor's Report 2013 - 2014File: S2 Homes ITR 20152016 auditor report.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: itr.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: S2 Homes ITR 20152016.pdf | - |
| Income Tax Return Acknowledgement 2013 - 2014File: S2 Homes ITR 20152016.pdf | - |
| Declaration form B | - |
| Prospectus/BrochureFile: BROCHURE.pdf | - |
| Advertisement Copy 1File: BROCHURE.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1251_308_PR_180120_001239.xlsx | - |
| Occupancy CertificateFile: IMG_20190121_130534.jpg | - |
| Completion certificate issued by the competent authorityFile: IMG_20190121_130534.jpg | - |
| Registered Agreement of SaleFile: IMG_20190121_130534.jpg | - |
| Registered conveyance deed for an individual unitFile: IMG_20190121_130534.jpg | - |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| THE WATERGROVE | - | Ongoing | Aug 2017 | Not delivered |
| AVANTIKAA | - | Ongoing | Aug 2017 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep AVANTIKAA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: s2 homes
s2 homes has 2 registrations on RERA Karnataka, including AVANTIKAA and THE WATERGROVE. Its filings declare 2 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if AVANTIKAA is delayed beyond 10 Aug 2017?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of AVANTIKAA?
The registered promoter entity is s2 homes, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in AVANTIKAA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at AVANTIKAA?
The professionals named in the filing: Architect: UMA NIRMALA P; Engineer: UMA NIRMALA P. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AVANTIKAA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback