ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / AURALIS THE TWINS

Completed No litigation declared Residential / Group Housing project

AURALIS THE TWINS

By DEEP HOMES & CONSTRUCTIONS LLP

RG-MH-27167 · RERA P51700009177 · Last updated on MahaRERA portal: 11 Jul 2022

Source: official MahaRERA filing

Red flags

  • 26 complaints at MahaRERA
  • Completion date moved by 22 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jan 2021Possession promisedregistration recorded completed
33 of 33Construction stages doneacross 3 buildings; every applicable stage filed complete
26Complaints at MahaRERAon this registration
Jump to the 57 documents Report an error

AURALIS THE TWINS is a Residential / Group Housing project by DEEP HOMES & CONSTRUCTIONS LLP in Thane, Maharashtra, registered with MahaRERA as P51700009177 on 19 Aug 2017. The registration is recorded completed; possession was promised by 31 Jan 2021. The completion date has moved by 22 months from the original filing. 26 complaints are on record with the regulator.

At a glance

Project

  • NameAURALIS THE TWINS
  • TypeResidential / Group Housing
  • Location
    • Thane (M Corp.)
    • Thane
    • 400604
  • Pincode400604
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700009177
  • ReraGenie IDRG-MH-27167

Builder

  • NameDEEP HOMES & CONSTRUCTIONS LLP
  • Entity typePartnership
  • PartnersMANOJ VELJI SHAH, RAJU KANAYALAL KHETWANI, UTTAMCHAND UMEDMAL SOLANKI

Key dates

this monthRegisteredAug 2017First promiseMar 2019Revised toJan 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on19 Aug 2017
  • Promised completion31 Jan 2021
  • Revised completionRevised to 31 Jan 2021 (originally 1 Mar 2019)
  • Buildings3 building records
  • Documents filed57 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER-1NA350000
TOWER-2NA310000
RENTALNA210000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 11 Jul 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

33 of 33 construction stages are filed complete across 3 buildings.

TOWER-1100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TOWER-2100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
RENTAL100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 11 Jul 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes95%
Landscaping & Tree PlantingYes45%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes85%
Solid Waste Management And DisposalYes65%
Water conservation /Rain water harvestingYes85%
Energy managemcntYes45%
Fire protection and fire safety requirementsYes60%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed441

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots441
Closed/Covered441
BuildingClosed/CoveredTotal
TOWER-1221221
TOWER-2220220

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,420 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI31997.08
Proposed, not sanctioned31,840 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTHANE WEST , TALAO PALI, MAHARASHTRA, SHARADKUNJ, DR MOOSE ROAD, OPP GADKARI RANGAYTAN THANE 400602

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr.Anil Jagwani
EngineerAjay Mahale
PartnerRole in project
DEEP HOMES & CONSTRUCTIONS LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700001432Mar 2019 → Feb 2020

Reason as filed by the promoterOur Project 'Auralis the Twins' has been allowed to be developed under MMRDA Rental Housing Scheme. TMC issued its IOD vide V.P. No. S03/0030/11 dtd. 12/10/2011. In between, we applied for Environment Clearance to MOEF, with regard to the said project vide our application was granted as late as on 04/09/2014 which is one of the major factor for delaying our project. TMC granted its C.C. on 30/11/2013 vide V.P.No. S03/0030/11 TMC/TDD/1015/13 for 1 F.S.I. with regard to Rental Building/ Sale Buildings & accordingly, we commenced the construction work of all 3 buildings. As per the norms & provis

EXT51700008480Mar 2019 → Jan 2021

Reason as filed by the promoterThe project Auralis The Twins is being constructed by us and have been almost finished and waiting for certain NOC so that we can formally apply for OC. The application for OC is expected to be done by next month. As you know that due to COVID 19, we could have got the construction workers and all our offices were closed / temporary working on alternate days for that reason.

Complaints filed with MahaRERA26

Case no.ComplainantRespondentFiled
CC006000000197106PREETI MANDREKARDEEP HOMES & CONSTRUCTIONS PVT.LTD.31/05/2021
CC006000000090062Vijay Liladhar GosraniDeep Homes and Constructions LLP13/07/2019
CC006000000195131SNEHA SUBHASH MARLEWARDEEP HOMES AND DEVELOPERS LLP03/02/2021
CC006000000195688OMKAR PRAKASH GODBOLE AND ADITI OMKAR GODBOLEDEEP HOMES & CONSTRUCTION LLP20/01/2021
CC006000000197920Meghana Abhishek Lakhotia and Abhishek Omprakash LakhotiaM/s Deep Homes & Constructions LLP, Raju Khetwani, Uttamchand Solanki, Manoj Shah,Pradeep Shah10/08/2021
CC006000000197018AMAR KETKARDeep Home COnstructions LLP18/05/2021
CC006000000197101Vivek IyerDeep Homes LLP30/05/2021
CC006000000197755Deep Homes & Constructions LLPVivek Iyer, Priyanka Iyer and K P Gopalkrishnan29/07/2021
CC006000000197756Deep Homes & Constructions LLPSunil Vishnu Redkar and Megha Sunil Redkar29/07/2021
CC006000000197757Deep Homes & Constructions LLPSunil Maheshwari and Mamata Maheshwari29/07/2021
CC006000000197758Deep Homes & Constructions LLPMrs. Shilpa Joshi29/07/2021
CC006000000197759Deep Homes & Constructions LLPRaghunath Mandrekar and Preeti R. Mandrekar29/07/2021
CC006000000197761Deep Homes & Constructions LLPMr. Omkar Godbole and Mrs. Aditi Godbole29/07/2021
CC006000000197762Deep Homes & Construction LLPMr. Nikhil Narkhede29/07/2021
CC006000000197774Deep Homes & Constructions LLPMr. Amar Ketkar and Mrs. Ketaki Ketkar29/07/2021
CC006000000197775Deep Homes & Constructions LLPMrs. Anju Vishnukumar Ajistaria29/07/2021
CC006000000197776Deep Homes & Constructions LLPMrs. Sneha Subhash Marlewar,Ms.Maitreyi Subhash Marlewar & Mr. Subhash Marlewar29/07/2021
CC006000000198166Deep HomesMrs. Meghana Lakhotia and Mr. Abhishek Lakhotia21/07/2022
CC006000000480276Deep HomesMr. Amar Ketkar06/05/2024
CC006000000480351Deep HomesMrs. Sneha Subhash Marlewar, Mr. Subhash Marlewar & Ms. Maitreyi Subhash Marlewar06/05/2024
CC006000000480354Deep HomesMr. Omkar P Godbole and Mrs. Aditi Omkar Godbole06/05/2024
CC006000000198260Shilpa Mahesh JoshiDeep Homes & Constructions LLP06/09/2021
CC006000000199186RAJESH BAROLIYA & JYOTI BAROLIYADeep Homes & Constructions LLP06/12/2021
CC006000000231147Vaishali Sumant PradhanM/s. Deep Homes & Constructions LLP13/05/2022
CC006000000292536Satyanarayan Meghraj RathiDeep Homes & Constructions LLP05/09/2022
CC006000000292537Kantadevi Satyanarayan RathiDeep Homes & Constructions LLP05/09/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 11 Jul 2022

Documents filed57

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement Certificates / NA Order for plotted developmentFile: 08 CC T2 UP TO 26TH FLOOR 09-09-2020.pdf11 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: 09 CC T2 UP TO 28TH FLORR 25-01-2021.pdf11 Jul 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCCUPATION CERTIFICATE.pdf11 Jul 2022
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4.pdf11 Jul 2022
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4.pdf23 Mar 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCCOPATION CERTIFICATE.pdf22 Mar 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20200925_FORM 1_ARCH CERT.pdf25 Sep 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20200925_FORM 2_ENG CERT.pdf25 Sep 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20191116_ARCH CERTIFICATE_FORM 1.pdf16 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20191116_ENG CERTIFICATE_FORM 2.pdf16 Nov 2019
Certificates of CA (Form 3)File: 20191116_C A CERTIFICATE_FORM 3.pdf16 Nov 2019
Details of encumbrancesFile: 20191115_NO DUE CERTIFICATE.pdf15 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20190520_ARCHITECT CERTIFICATE_FORM 1.pdf20 May 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20190520_ENGINEERS CERTIFICATE_FORM 2.pdf20 May 2019
Certificates of CA (Form 3)File: 20190520_CA CERTIFICATE_FORM 5_Pg 1-3.pdf20 May 2019
Certificates of CA (Form 3)File: 20190520_CA CERTIFICATE_FORM 5_Pg 4-6.pdf20 May 2019
Certificates of CA (Form 3)File: 20190520_CA CERTIFICATE_FORM 5_Pg 7-9.pdf20 May 2019
Certificates of CA (Form 3)File: 20181219_CA CERTIFICATE_FORM 3.pdf19 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20181026_FORM 1.pdf26 Oct 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20181026_FORM 2.pdf26 Oct 2018
Certificates of CA (Form 5)File: 20181012_CA CERTIFICATE_FORM 5.pdf12 Oct 2018
Certificates of CA (Form 3)File: 20180605_CA CERTIFICATE_FORM 3.pdf5 Jun 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20180416_ARCHITECT CERTIFICATE_FORM 1.pdf16 Apr 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20180412_ENGINEERS CERTIFICATE_FORM 2.pdf12 Apr 2018
OtherFile: DECLARATION_SOC FORMATION.pdf31 Mar 2018
Details of encumbrancesFile: ENCUMBRANCES CERTIFICATE.pdf8 Jan 2018
Commencement Certificates / NA Order for plotted developmentFile: CC 2.pdf8 Jan 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf8 Jan 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE 2.pdf8 Jan 2018
Certificates of CA (Form 3)File: C A CERTIFICATE.pdf8 Jan 2018
Details of encumbrancesFile: Scan_20171209_175829.pdf11 Dec 2017
Building plan approvalFile: 2.pdf29 Jul 2017
Building plan approvalFile: 3.pdf29 Jul 2017
Building plan approvalFile: 5.pdf29 Jul 2017
Building plan approvalFile: 4.pdf29 Jul 2017
Building plan approvalFile: 8.pdf29 Jul 2017
Layout approvalFile: Untitled-1.pdf29 Jul 2017
Building plan approvalFile: Untitled-2.pdf29 Jul 2017
Building plan approvalFile: Untitled 3.pdf29 Jul 2017
PAN CardFile: pan card deep homes.pdf29 Jul 2017
Copy of the legal title reportFile: TITLE COMBINED.pdf29 Jul 2017
Details of encumbrancesFile: letter of encumbrance.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Untitled-1.pdf29 Jul 2017
Building Plan Approval (IOD)File: 2.pdf29 Jul 2017
Building Plan Approval (IOD)File: 3.pdf29 Jul 2017
Building Plan Approval (IOD)File: 4.pdf29 Jul 2017
Building Plan Approval (IOD)File: 5.pdf29 Jul 2017
Building Plan Approval (IOD)File: 8.pdf29 Jul 2017
Building Plan Approval (IOD)File: Untitled-2.pdf29 Jul 2017
Building Plan Approval (IOD)File: Untitled 3.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf29 Jul 2017
Declaration in FORM BFile: Affidavit.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AR CERTIFICATE.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG.pdf29 Jul 2017
Certificates of CA (Form 3)File: CA.pdf29 Jul 2017
Proforma of Allotment letterFile: allotment letter formate.pdf29 Jul 2017
Proforma of Allotment letterFile: SALE AGREEMENT.pdf29 Jul 2017

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 22 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AURALIS THE TWINS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Thane (M Corp.)7,600+ in Thane

2 kmAURALIS THE TWINSCompleted 96Lapsed / revoked 71Other 152Dot size: filed unitsN

Filed coordinates, straight-line distance. 319 registered projects within 2 km.

Builder: DEEP HOMES & CONSTRUCTIONS LLP

DEEP HOMES & CONSTRUCTIONS LLP has 1 registration on MahaRERA, including AURALIS THE TWINS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if AURALIS THE TWINS is delayed beyond 31 Jan 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AURALIS THE TWINS?

The registered promoter entity is DEEP HOMES & CONSTRUCTIONS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AURALIS THE TWINS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against AURALIS THE TWINS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for AURALIS THE TWINS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AURALIS THE TWINS?

The professionals named in the filing: Architect: Mr.Anil Jagwani; Engineer: Ajay Mahale. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AURALIS THE TWINS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AURALIS THE TWINS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AURALIS THE TWINS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.