Registration approved Residential/Group Housing project

Astoria Park

By Suvastu Estates Pvt Ltd

RG-KA-25749 · RERA PRM/KA/RERA/1251/310/PR/180516/001696

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Dec 2019Possession promisedmoved 12 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 70 documents Report an error

Astoria Park is a Residential/Group Housing project by Suvastu Estates Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/180516/001696 on 16 May 2018. Possession is promised by 15 Dec 2019. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameAstoria Park
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/180516/001696
  • ReraGenie IDRG-KA-25749

Builder

  • NameSuvastu Estates Pvt Ltd
  • Entity typeCompany
  • CINU70102KA2012PTC067464
  • Authorized SignatoryArjun Kumar
  • Other registrations1 more →

Key dates

this monthRegisteredMay 2018First promiseDec 2018Revised toDec 2019

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on16 May 2018
  • Promised completion15 Dec 2019
  • Revised completionRevised to 15 Dec 2019 (originally 15 Dec 2018)
  • Buildings1 building record
  • Documents filed70 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Astoria Park---64064

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing workNot applicable
Retaining wall (All types)Not applicable
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etcNot applicable
Plastering inside , outside & CeilingNot applicable
Joinery: Doors, Windows, Ventilators etcNot applicable
Basic work of Water supply, Sanitary and ElectrificationNot applicable
Dadoing, Skirting, Flooring, Tiles work (All types)Not applicable
Railing and Grill fixingNot applicable
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
PaintingNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes-
Community HallYes-
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,440 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 14.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBasavaraj
EngineerBasavaraj

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/310/PR/220613/001696Dec 2018 → Dec 2019

Reason as filed by the promoterothers

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed70

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/180516/001696 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Suvastu Estates COI.jpeg-
Already registered project ongoing detailsFile: Under process.pdf-
Modified plan details site plan, floor plans, Plan Licence LetterFile: Under process.pdf-
Elevation, Sections, Specifications ( If changes are there )File: Under process.pdf-
List Of AllotteesFile: Under process.pdf-
List Of ComplaintsFile: Under process.pdf-
Consent LetterFile: Under process.pdf-
List Of Pending LitigationsFile: Under process.pdf-
Chartered Accountant CertificateFile: Under process.pdf-
Notarized AffidavitFile: Under process.pdf-
Engineer CertificateFile: Under process.pdf-
Architect CertificateFile: Under process.pdf-
Structural Engineer Certificate for stability of structureFile: Under process.pdf-
Modification of Plan DetailsFile: Under process.pdf-
Modification of Plan DetailsFile: Under process.pdf-
Modification of Plan DetailsFile: Under process.pdf-
Modification of Plan DetailsFile: Under process.pdf-
Modification of Plan DetailsFile: Under process.pdf-
Document 1File: Under process.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Under Process.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Under Process.pdf-
CA Certificate for Funds UtilizationFile: Under Process.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Under Process.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Under Process.pdf-
CA Certificate for Funds required for Project CompletionFile: Under Process.pdf-
AffidavitFile: Under Process.pdf-
Details Of Sold/ Un-sold UnitsFile: Under Process.pdf-
BBMP Letter-
Astoria sanction plan 1-
Astoria sanction plan 1-
SALE DEED DRAFT -
Draft agreement-
Sale Deeds-
Astoria sanction plan 1-
Astoria sanction plan 1-
Draft agreement-
Astoria Park_brochure-
astoria noc-
Astoria Park_brochure-
astoria EC 14 years-
Khata & Extarct-
astoria JDA-
Sale Deeds-
Conversion order all-
Unnamed document-
Sanction plan-
Under Process-
Under Process-
Under Process-
Astoria legal report-
Balance Sheet 2016 - 2017File: Balance sheet 2.pdf-
Balance Sheet 2015 - 2016File: Balance sheet 1.pdf-
Balance Sheet 2014 - 2015File: Balance sheet 1.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Balance sheet 2.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Balance sheet 1.pdf-
Audited Profit and Loss Statement 2014 - 2015File: Balance sheet 1.pdf-
Director's Report 2016 - 2017File: Estates ROC search report.pdf-
Director's Report 2015 - 2016File: Estates ROC search report.pdf-
Director's Report 2014 - 2015File: Estates ROC search report.pdf-
Cash Flow Statement 2016 - 2017File: Balance sheet 2.pdf-
Cash Flow Statement 2015 - 2016File: Balance sheet 1.pdf-
Auditor's Report 2016 - 2017File: Auditor report 2.pdf-
Auditor's Report 2015 - 2016File: Auditor report 1.pdf-
Auditor's Report 2014 - 2015File: Auditor report 1.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: Estates IT return 2.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: Estates IT return 1.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: Estates IT return 1.pdf-
FORM B-
Prospectus/BrochureFile: Under Process.pdf-
Advertisement Copy 1File: Under Process.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Astoria Park on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmAstoria ParkOther 21Dot size: filed unitsN

Filed coordinates, straight-line distance. 21 registered projects within 2 km.

Builder: Suvastu Estates Pvt Ltd

Suvastu Estates Pvt Ltd has 2 registrations on RERA Karnataka, including Oak Leaf and Astoria Park. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Astoria Park is delayed beyond 15 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Astoria Park?

The registered promoter entity is Suvastu Estates Pvt Ltd, a company as per the filing. Its CIN U70102KA2012PTC067464 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Astoria Park?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Astoria Park?

The professionals named in the filing: Architect: Basavaraj; Engineer: Basavaraj. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Astoria Park?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Astoria Park. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Astoria Park to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.