Assetz Soho & Sky Phase 1B

By APG IMPERIAL HOMES PRIVATE LIMITED

RG-KA-74607 · RERA PRM/KA/RERA/1251/309/PR/200524/006910 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • Litigation declared, 2 cases

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2027Possession promisedno revision filed
14 of 18Construction stages donefurthest along: Painting, 90%
0 of 120Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 209 documents Report an error

Assetz Soho & Sky Phase 1B is a Residential/Group Housing project by APG IMPERIAL HOMES PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/200524/006910 on 20 May 2024. Possession is promised by 31 Dec 2027. 120 of the 120 units on this registration are recorded sold or booked, and 14 of 18 construction stages are filed complete.

At a glance

Project

  • NameAssetz Soho & Sky Phase 1B
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/309/PR/200524/006910
  • ReraGenie IDRG-KA-74607

Builder

  • NameAPG IMPERIAL HOMES PRIVATE LIMITED
  • Entity typeCompany
  • CINU45209KA2015PTC084242
  • GSTIN29AAOCA0369D1ZM
  • Authorized SignatoryAkshay Kishore Dewani
  • CeoAkshay Kishore Dewani
  • DirectorsAkshay Kishore Dewani, Pankaj Kumar Bajaj
  • Project HeadNanda Kumar P S
  • Other registrations1 more →

Key dates

this monthRegisteredMay 2024PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on20 May 2024
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings3 building records
  • Documents filed209 files

Current status

100%120 of 120 units booked
75.0%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING A---24024
WING B---48048
WING C---48048

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 18 construction stages are filed complete. The stage furthest along is Painting, at 90%.

Building: 94% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification80%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing80%
Painting90%
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings50%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes70%
Energy managementYes0%
Fire protection and fire safety requirementsYes100%
Solid waste management and disposalYes100%
Emergency Evacuation servicesYes85%
Internal Roads & FootpathsYes90%
Electricity supply transformer and substationYes10%
Storm water drainsYes80%
Use of renewable energyYes5%
Sewage Treatment Plant (STP)Yes80%
Parks & Tree plantingYes30%
Street LightingYes5%
ElectricityYes50%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes15%
Club HouseYes65%
Community HallYes40%
Outdoor Sports facilityYes30%
Indoor Sports facilityYes30%
Swimming PoolYes50%
GymYes10%
ParksNoNot applicable
Power BackupYes40%
Piped GasNoNot applicable
Water and SanitationYes40%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesYes100%
Common entrance and exit for the building/common portico/foyer/verandahYes50%
BasementYes80%
TerraceYes70%
Outer WallYes60%
Open parking areasYes40%
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyYes70%
Common storage spacesYes0%

Land and ownership10

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners10
LandownerVillageDistrict
Chandra Kumari Raghu Ram Shetty--
Chandra Kumari Raghu Ram Shetty--
Chandra Kumari Raghu Ram Shetty--
Chandra Kumari Raghu Ram Shetty--
Chandra Kumari Raghu Ram Shetty--
Chandra Kumari Raghu Ram Shetty--
Chandra Kumari Raghu Ram Shetty--
Chandra Kumari Raghu Ram Shetty--
Chandra Kumari Raghu Ram Shetty--
Chandra Kumari Raghu Ram Shetty--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 110.51 cr
Cost incurredRs 82.83 cr
Spent of the estimate74.95%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 78.49 crRs 62.44 cr
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 13.19 crRs 12.86 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 10.00 cr-
Approval CostRs 6.69 crRs 2.43 cr
On-site expenditure-Site OverheadRs 2.14 crRs 5.09 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSandeep Rajendran
EngineerB.E Pruthviraja
Chartered AccountantY S Shetty & Company

Litigation declared2

CaseCourtStatus
9863ADDLCITYCIVILANDSESSINSJUDGE-
O.S 830/2019/2019IX ADDL.City civil and SessionsJudge ,Bangalore-

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed209

As listed on the registration, under the names the promoter filed them with; the newest 80 of 209 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/200524/006910 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4, Chartered Accountant (QU) -Soho & Sky Ph 1b.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) soho & Sky Ph 1b.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer (QU) Soho & Sky Phase 1B.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q2 2026-27 Preventive Order (Injunction / Interim Order / Final Order / Stay OrderFile: O.S 830 of 2019 - Judgment.pdf15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4, Chartered Accountant (QU) -Soho & Sky Ph 1b.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) soho & Sky Ph 1b.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer (QU) Soho & Sky Phase 1B.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department15 Jul 2026
Q1 2026-27 Preventive Order (Injunction / Interim Order / Final Order / Stay OrderFile: O.S 830 of 2019 - Judgment.pdf15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form -4, Chartered Accountant (QU) -Soho & Sky Ph 1b.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) soho & Sky Ph 1b.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer (QU) Soho & Sky Phase 1B.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form -4, Chartered Accountant (QU) -Soho & Sky Ph 1b.pdf10 Mar 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) soho & Sky Ph 1b.pdf10 Mar 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 engineering soho & Sky Ph 1b-.pdf10 Mar 2026
Q3 2025-26 Water supply and sewage board10 Mar 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)10 Mar 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)10 Mar 2026
Q3 2025-26 KPTCL- BESCOM10 Mar 2026
Q3 2025-26 Fire and Safety10 Mar 2026
Q3 2025-26 Airport Authority of India10 Mar 2026
Q3 2025-26 BSNL/Telecommunication Department10 Mar 2026
Covering LetterFile: Covering Letter.pdf17 May 2024
Upload quarterly updates for previous projectFile: Annexure 1-Quarterly Update.pdf17 May 2024
Clarification regarding ViolationFile: Annexure 2-Clarification regarding Violation.pdf17 May 2024
Form-1 CA CertificateFile: Annexure 3-Form-1 CA Certificate.pdf17 May 2024
Sources of FundFile: Annexure 4-Sources of Fund.pdf17 May 2024
bank account affidavit in prescribed formatFile: Annexure 5-Bank Affidavit.pdf17 May 2024
Area DetailsFile: Annexure 6-Area Details.pdf17 May 2024
RTC 61/1File: Annexure 7-RTC 61-3.pdf17 May 2024
Conversion order ClarificationFile: Annexure 8-Conversion order Clarification.pdf17 May 2024
ECFile: Annexure 9-EC.pdf17 May 2024
Gift Deed BRS to Chandrakumari BRSFile: Annexure 10-Gift Deed BRS to Chandrakumari BRS.pdf17 May 2024
KR Ramesh DeedFile: Annexure 11-KR Ramesh Deed.pdf17 May 2024
Khata and JDA Clarification Sy no 22-1,2File: Annexure 12-Khata and JDA Clarification Sy no 22-1,2.pdf17 May 2024
JA Cum Declaration JDA land owner Chandrakumari Raghuram Shetty is not Signed.File: Annexure 13-JA Affidavit clarification.pdf17 May 2024
DP clarificationFile: Annexure 14-DP clarification.pdf17 May 2024
Clarification regarding BR shetty GPAFile: Annexure 15-BR shetty GPA in favor C Reddy.pdf17 May 2024
Kharab ClarificationFile: Annexure 16-Kharab Clarification.pdf17 May 2024
Advocate Search reportFile: Annexure 17-Advocate Search report.pdf17 May 2024
Area DetailsFile: Annexure 18-Area Details.pdf17 May 2024
FAR Sanction ClarificationFile: Annexure 19-FAR Sanction Clarification.pdf17 May 2024
Single plot layout.File: Annexure 20-Approved Sanction plan -Lower Basment to Terrace plan.pdf17 May 2024
Single plot layout order.File: Annexure 21-Layout order.pdf17 May 2024
Carpet Area CalculationFile: Annexure 22-Carpet Area Calculation.pdf17 May 2024
CDP MapFile: Annexure 23-CDP Map.pdf17 May 2024
Village MapFile: Annexure 24-Village Map.pdf17 May 2024
CC clarificationFile: Annexure 25-CC clarification.pdf17 May 2024
KSPCB NOCFile: Annexure 26-KSPCB.pdf17 May 2024
Relinquishment DeedFile: Annexure 27-Relinquishment Deed.pdf17 May 2024
Building LicenseFile: Annexure 28-Building License.pdf17 May 2024
Approved Plan SanctionFile: Annexure 29A-Approved Sanction plan -Lower Basment to Terrace plan.pdf17 May 2024
Section & ElevationFile: Annexure 29B-Section & Elevation.pdf17 May 2024
CLUFile: Annexure 30-CLU Clarification.pdf17 May 2024
Self Attested Engineer licence CertificateFile: Annexure 31-Self Attested Engineer licence Certificate.pdf17 May 2024
Certified Amenties & Common AreaFile: Annexure 32-Certified Amenties & Common Area.pdf17 May 2024
engineer certificateFile: Annexure 33-engineer certificate.pdf17 May 2024
STP DetailsFile: Annexure 34-STP Details.pdf17 May 2024
BWSSB NOC and Paid receiptFile: Annexure 35A-BWSSB NOC and Paid receipt.pdf17 May 2024
Becom NOC and Paid receiptFile: Annexure 35B-Becom NOC and Paid receipt.pdf17 May 2024
JAKKUR NOC-Airodrum 1File: Annexure 36-JAKKUR NOC-Airodrum 1.pdf17 May 2024

How this compares with Bengaluru Urban

100%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Assetz Soho & Sky Phase 1B on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: APG IMPERIAL HOMES PRIVATE LIMITED

APG IMPERIAL HOMES PRIVATE LIMITED has 2 registrations on RERA Karnataka, including Assetz Soho & Sky Phase 1B and Assetz Soho & Sky. Its filings disclose no earlier RERA Karnataka projects. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Assetz Soho & Sky Phase 1B is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Assetz Soho & Sky Phase 1B?

The registered promoter entity is APG IMPERIAL HOMES PRIVATE LIMITED, a company as per the filing. Its CIN U45209KA2015PTC084242 and GSTIN 29AAOCA0369D1ZM can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Assetz Soho & Sky Phase 1B?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Assetz Soho & Sky Phase 1B?

The professionals named in the filing: Architect: Sandeep Rajendran; Engineer: B.E Pruthviraja; Chartered Accountant: Y S Shetty & Company. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Assetz Soho & Sky Phase 1B?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Assetz Soho & Sky Phase 1B. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Assetz Soho & Sky Phase 1B to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.