Home / Browse projects / Bengaluru Urban, Karnataka / Assetz 22 & Crest

Registration transferred Residential/Group Housing project

Assetz 22 & Crest

By Jain Heights and Structures Pvt Ltd

RG-KA-35243 · RERA PRM/KA/RERA/1251/309/PR/170915/000219 · Last updated on RERA Karnataka portal: 30 Aug 2021

Source: official RERA Karnataka filing

Red flags

  • Registration transferred
  • 6 complaints at RERA Karnataka
  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • Separate project account declared
Mar 2022Possession promisedmoved 21 months from the original
6Complaints at RERA Karnatakaon this registration
Jump to the 93 documents Report an error

Assetz 22 & Crest is a Residential/Group Housing project by Jain Heights and Structures Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/170915/000219 on 15 Sep 2017. Possession is promised by 30 Mar 2022. The completion date has moved by 21 months from the original filing. 6 complaints are on record with the regulator.

At a glance

Project

  • NameAssetz 22 & Crest
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/170915/000219
  • ReraGenie IDRG-KA-35243

Builder

  • NameJain Heights and Structures Pvt Ltd
  • Entity typeCompany
  • CINU70200KA2005PTC036013
  • Authorized SignatoryGururaj K
  • OthersPrakash H.N
  • Declared earlier projects5 →

Key dates

this monthRegisteredSep 2017First promiseJun 2020Revised toMar 2022

Key facts

Registration and timeline

  • StatusRegistration transferred
  • Registered on15 Sep 2017
  • Promised completion30 Mar 2022
  • Revised completionRevised to 30 Mar 2022 (originally 30 Jun 2020)
  • Buildings2 building records
  • Documents filed93 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 1---63063
Tower 2---50050

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 30 Aug 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 30 Aug 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,275 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 72.73 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKhan Global Engineering consultants Pvt Ltd
EngineerInnotech Engineerng consultants Pvt Ltd

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJun 2020 → Mar 2021

No reason recorded in the filing

ExtensionMar 2021 → Mar 2022

Reason as filed by the promoterothers

Complaints filed with RERA Karnataka6

Case no.ComplainantRespondentFiled
CMP/200112/0005197-Jain Heights and Structures Pvt Ltd12/01/2020
CMP/200926/0006604-Jain Heights and Structures Pvt Ltd26/09/2020
CMP/210305/0007749-Jain Heights and Structures Pvt Ltd05/03/2021
CMP/210418/0007907-Jain Heights and Structures Pvt Ltd18/04/2021
CMP/210803/0008205-Jain Heights and Structures Pvt Ltd03/08/2021
CMP/210803/0008206-Jain Heights and Structures Pvt Ltd03/08/2021

Documents filed93

As listed on the registration, under the names the promoter filed them with; the newest 80 of 93 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/170915/000219 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CA CERTIFICATE FUNA UTILIZEDFile: CERTIFICATE FOR FUNDS UTILIZATION.pdf30 Aug 2021
CA CERTIFICATE FUND REQUIREDFile: CERTIFICATE FOR FUNDS REQUIRED.pdf30 Aug 2021
QUERY CLARIFICATION LETTER DATED 210830File: CLARIFICATION LETTER 210830.pdf30 Aug 2021
QUERY CLARIFICATION LETTER DATED 210816File: CLARIFICATION LETTER 210819.pdf19 Aug 2021
MODIFIED SITE PLANFile: ANNEXURE 1 1 SITE PLAN .pdf19 Aug 2021
ELEVATION PLANFile: ANNEXURE 1 2 Modified Plan Sanction Elevation plan.pdf19 Aug 2021
LOWER BASEMENT PLANFile: ANNEXURE 1 3 Lower Basement Floor.pdf19 Aug 2021
UPPER BASEMENT PLANFile: ANNEXURE 1 4 Upper Basement.pdf19 Aug 2021
GROUND FLOOR PLANFile: ANNEXURE 1 5 Ground Floor.pdf19 Aug 2021
FIRST AND SECOND FLOOR PLANFile: ANNEXURE 1 6 First Second Floor Plan .pdf19 Aug 2021
TYPICAL AND TERRACE FLOOR PLANFile: ANNEXURE 1 7 Typical Floor and Terrace Floor Plan.pdf19 Aug 2021
CA FUNDS UTILIZED CERTIFICATEFile: ANNEXURE 2 1 CA CERTIFICATE FUNDS UTILIZED.pdf19 Aug 2021
CA FUNDS REQUIRED CERTIFICATEFile: ANNEXURE 2 2 CA CERTIFICATE FUNDS REQUIRED.pdf19 Aug 2021
ENGINEER WORK PENDING CERTIFICATEFile: ANNEXURE 3 1 ENGINEER CERTIFICATE WORK PENDING.pdf19 Aug 2021
ENGINEER WORK DONE CERTIFICATEFile: ANNEXURE 3 2 ENGINEER CERTIFICATE WORK DONE.pdf19 Aug 2021
ARCHITECT WORK DONE CERTIFICATEFile: ANNEXURE 4 1 ARC CERTIFICATE WORK COMPLETED.pdf19 Aug 2021
ARCHITECT WORK PENDING CERTIFICATEFile: ANNEXURE 4 2 ARC CERTIFICATE WORK PENDING.pdf19 Aug 2021
AFFIDAVIT FROM OUTGOING PROMOTERFile: ANNEXURE 5 -AFFIDAVIT FROM OUTGOING PROMOTER.pdf19 Aug 2021
AFFIDAVIT FROM INCOMING PROMOTERFile: ANNEXURE 6 -AFFIDAVIT FROM INCOMING PROMOTER.pdf19 Aug 2021
COMPENSATION AFFIDAVITFile: ANNEXURE 7 COMPENSATION AFFIDAVIT.pdf19 Aug 2021
CertificateFile: Registration Certificate- JHSPL.pdf-
Architect Certificate for Work Completion Schedule till DateFile: ANNEXURE 2 ARCHITECT WORK COMPLETED .pdf-
Engineer Certificate for Work Completion Schedule till DateFile: ANNEXURE 3 ENGINEER CERTIFICATE.pdf-
CA Certificate for Funds UtilizationFile: ANNEXURE 4 CA FUND UTILIZED.pdf-
Architect Certificate for Pending Work Completion Schedule.File: ANNEXURE 6 ARCHITECT WORK PENDING.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: ANNEXURE 3 ENGINEER CERTIFICATE.pdf-
CA Certificate for Funds required for Project CompletionFile: ANNEXURE 7 CA FUNDS REQUIRED.pdf-
AffidavitFile: ANNEXURE 8 AFFIDAVIT.pdf-
Latest Encumbrance CertificateFile: ANNEXURE 9 ENCUMBRANCE CERTIFICATE.pdf-
Consent letter from 2/3rd of AllotteesFile: CONSENT LETTER.pdf-
Details Of Sold/ Un-sold UnitsFile: ANNEXURE 10 SOLD AND UNSOLD DETAILS.xlsx-
Document 1File: ANNEXURE 13 2:3RD CONSENT LETTERS.pdf-
Document 2File: Affidavit Form-B.pdf-
G W - Commencement Certificate dt 09-02-2017-
G W - Approved Building Plan-
G W - Proform of Sale deed-
G W - Proforma Agreement of Sale-
Existing Layout Plan-
Existing Sectional Plan and Specification-
Title Deed-
G W - Approved Section of buildingInfrastructure Plan of Plotting-
G W - Area Development Plan-
G W - Proforma of Allotment Letter-
G W - Brochure-
G W - All NOC's from all the Authorities-
G W - Project Specifications-
G W - Encumbrance Certificates-
Doc No 14 Katha Certificate & Extract dt 13-04-2017-
Joint Development Agreement-
Other title document1-
Section 95 of KLR Act-
CLU-
Utilization Certificate-
TDR Certificate-
Relinquishment Deed-
Doc No 08 Revised Fire NOC-
Doc No 01 Revised -AAI-AIRPORT NOC-
Doc No 04 BESCOM NOC-
Doc No 05 BWSSB-NOC-
KSPCB NOC-
Doc No 09 MOEF-
Doc No 03 BSNL NOC-
NOC from abutting lands-
Unnamed document-
Urban Land Ceiling-
BMRCL-
Urban Arts Commission-
Inspector of factories-
District Magistrate-
Coastal regulation-
Structural Stability Certificate-
Sectional Drawing-
Title Report-Tatva-
Balance Sheet 2015 - 2016File: JHSPL Balance Sheet 15-16.pdf-
Balance Sheet 2014 - 2015File: JHSPL Balance Sheet 14-15.pdf-
Balance Sheet 2013 - 2014File: JHSPL Balance Sheet 13-14.pdf-
Audited Profit and Loss Statement 2015 - 2016File: JHSPL Profit & Loss 15-16.pdf-
Audited Profit and Loss Statement 2014 - 2015File: JHSPL Profit & Loss 14-15.pdf-
Audited Profit and Loss Statement 2013 - 2014File: JHSPL Audited Profit & Loss 13-14.pdf-
Director's Report 2015 - 2016File: JHSPL Director Report 15-16.pdf-

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 not delivered by the promised date3 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Solus2 Phase I-OngoingAug 2019Not delivered
Jain Heights East Parade Phase II-OngoingJan 2019Not delivered
Solus-Completed-No date filed
Jain Heights East Parade Phase I-Completed-No date filed
Jain Heights Corona-Completed-No date filed

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 21 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Assetz 22 & Crest on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmAssetz 22 & CrestOther 18Dot size: filed unitsN

Filed coordinates, straight-line distance. 18 registered projects within 2 km.

Builder: Jain Heights and Structures Pvt Ltd

Jain Heights and Structures Pvt Ltd has 1 registration on RERA Karnataka, including Assetz 22 & Crest. Its filings declare 5 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Assetz 22 & Crest is delayed beyond 30 Mar 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Assetz 22 & Crest?

The registered promoter entity is Jain Heights and Structures Pvt Ltd, a company as per the filing. Its CIN U70200KA2005PTC036013 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Assetz 22 & Crest?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Assetz 22 & Crest?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Assetz 22 & Crest?

The professionals named in the filing: Architect: Khan Global Engineering consultants Pvt Ltd; Engineer: Innotech Engineerng consultants Pvt Ltd. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Assetz 22 & Crest?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Assetz 22 & Crest. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Assetz 22 & Crest to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.