ASR OCTAVE
RG-KA-57482 · RERA PRM/KA/RERA/1251/446/PR/180130/002203
Source: official RERA Karnataka filing
Red flags
- 5 complaints at RERA Karnataka
- Completion date moved by 12 months
- 1 extension taken
Clear
- Separate project account declared
Saved.
ASR OCTAVE is a Residential/Group Housing project by ASR CONSTRUCTIONS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/180130/002203 on 30 Jan 2018. Possession is promised by 31 Dec 2018. The completion date has moved by 12 months from the original filing. 5 complaints are on record with the regulator.
At a glance
Project
- NameASR OCTAVE
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/446/PR/180130/002203
- ReraGenie IDRG-KA-57482
Builder
- NameASR CONSTRUCTIONS
- Entity typeProprietorship Firm
- Authorized SignatoryAS RAMESH KUMAR
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on30 Jan 2018
- Promised completion31 Dec 2018
- Revised completionRevised to 31 Dec 2018 (originally 31 Dec 2017)
- BuildingsNot stated in filing
- Documents filed45 files
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterShortage of Labour
Complaints filed with RERA Karnataka5
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CMP/220817/0009902 | - | ASR CONSTRUCTIONS | 17/08/2022 |
| 00696/2023 | - | ASR CONSTRUCTIONS | 06/05/2023 |
| 00697/2023 | - | ASR CONSTRUCTIONS | 06/05/2023 |
| 00698/2023 | - | ASR CONSTRUCTIONS | 06/05/2023 |
| 00699/2023 | - | ASR CONSTRUCTIONS | 06/05/2023 |
Documents filed45
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/180130/002203 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: VAT.pdf | - |
| Architect Certificate for Work Completion Schedule till DateFile: Architech certificate_completed.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Engineer certificate.pdf | - |
| CA Certificate for Funds UtilizationFile: CA certificate.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: Architech certificate work pending.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Engineer certificate pending.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: CA certificate.pdf | - |
| AffidavitFile: affidavit.pdf | - |
| Latest Encumbrance CertificateFile: EC 15-17.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: sole and unsoled.xlsx | - |
| Plans | - |
| Plans (2) | - |
| 18Proforma sale deed | - |
| 19Proforma Of Agreement of Sale | - |
| Sale deed | - |
| Plans (2) | - |
| Plans (2) | - |
| 13Allotment Letter | - |
| 14Brochure | - |
| 16Project Specifications | - |
| 5EC | - |
| Khatha merged | - |
| JDA | - |
| Conversion order | - |
| 7Approved Plan 1 | - |
| 11Approved Plan - Elevetion | - |
| Khatha 117 | - |
| Balance Sheet 2016 - 2017File: 3Financial-Not Filed.pdf | - |
| Balance Sheet 2015 - 2016File: 3Financial-Not Filed.pdf | - |
| Balance Sheet 2014 - 2015File: 3Financial-Not Filed.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: 3Financial-Not Filed.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: 3Financial-Not Filed.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: 3Financial-Not Filed.pdf | - |
| Director's Report 2016 - 2017File: 3Financial-Not Filed.pdf | - |
| Director's Report 2015 - 2016File: 3Financial-Not Filed.pdf | - |
| Director's Report 2014 - 2015File: 3Financial-Not Filed.pdf | - |
| Cash Flow Statement 2016 - 2017File: 3Financial-Not Filed.pdf | - |
| Cash Flow Statement 2015 - 2016File: 3Financial-Not Filed.pdf | - |
| Auditor's Report 2016 - 2017File: 3Financial-Not Filed.pdf | - |
| Auditor's Report 2015 - 2016File: 3Financial-Not Filed.pdf | - |
| Auditor's Report 2014 - 2015File: 3Financial-Not Filed.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: 3Financial-Not Filed.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: 3Financial-Not Filed.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: 3Financial-Not Filed.pdf | - |
| 17Declaration Form-B | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep ASR OCTAVE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 67 registered projects within 2 km.
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: ASR CONSTRUCTIONS
ASR CONSTRUCTIONS has 1 registration on RERA Karnataka, including ASR OCTAVE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if ASR OCTAVE is delayed beyond 31 Dec 2018?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of ASR OCTAVE?
The registered promoter entity is ASR CONSTRUCTIONS, a proprietorship firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in ASR OCTAVE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ASR OCTAVE?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
What should I check before booking in ASR OCTAVE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.