Home / Browse projects / Bengaluru Urban, Karnataka / ASN SRIKARAM

Registration approved Residential/Group Housing project

ASN SRIKARAM

By M/s.Ankuraa Sai Nitya Ventures

RG-KA-54584 · RERA PRM/KA/RERA/1251/446/PR/190829/002840

Source: official RERA Karnataka filing

Red flags

  • 2 complaints at RERA Karnataka
  • Completion date moved by 29 months
  • 3 extensions taken

Clear

  • Separate project account declared
Dec 2024Possession promisedmoved 29 months from the original
2Complaints at RERA Karnatakaon this registration
Jump to the 74 documents Report an error

ASN SRIKARAM is a Residential/Group Housing project by M/s.Ankuraa Sai Nitya Ventures in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/190829/002840 on 29 Aug 2019. Possession is promised by 31 Dec 2024. The completion date has moved by 29 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameASN SRIKARAM
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/190829/002840
  • ReraGenie IDRG-KA-54584

Builder

  • NameM/s.Ankuraa Sai Nitya Ventures
  • Entity typePartnership Firm
  • Authorized SignatoryMADHUKAR GADDAM
  • OthersBalasubramanyam Perumal

Key dates

this monthRegisteredAug 2019First promiseJul 2022Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on29 Aug 2019
  • Promised completion31 Dec 2024
  • Revised completionRevised to 31 Dec 2024 (originally 29 Jul 2022)
  • Buildings4 building records
  • Documents filed74 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing 1---56056
Wing 2---70070
Wing 3---56056
Wing 4---24024

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemNoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,983 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 57.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSrinivas & Khan Architects
EngineerSterling

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJul 2022 → not stated

No reason recorded in the filing

EX/PRM/KA/RERA/1251/446/PR/230627/002840not stated → Apr 2024

Reason as filed by the promoterShortage of Building Materials, Concrete, Jalli etc

ExtensionApr 2024 → Dec 2024

No reason recorded in the filing

Complaints filed with RERA Karnataka2

Case no.ComplainantRespondentFiled
00259/2024-M/s.Ankuraa Sai Nitya Ventures11/03/2024
00684/2026-M/s.Ankuraa Sai Nitya Ventures09/06/2026

Documents filed74

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/190829/002840 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: ASN Ventures-RC.pdf-
Project Details-
Modified plan details site plan, floor plans, Plan Licence LetterFile: Building License.pdf-
Elevation, Sections, Specifications ( If changes are there )File: 5 Section & Elevation Plan BBMP.pdf-
List Of AllotteesFile: List of Allottees.xlsx-
Chartered Accountant CertificateFile: Form 4 Modification CA Certificate.pdf-
Notarized AffidavitFile: Modification Affidavit.pdf-
Engineer CertificateFile: Form 6 Engineer Certificate Modified.pdf-
Architect CertificateFile: Form-5 -Architect Certificate-Modified.pdf-
Structural Engineer Certificate for stability of structureFile: STABILITY CERTIFICATE ASN SRIKARAM.pdf-
Modification of Plan DetailsFile: GROUND FLOOR_compressed.pdf-
Modification of Plan DetailsFile: Modified Plan.pdf-
Modification of Plan DetailsFile: Commencement Certificate.pdf-
Modification of Plan DetailsFile: Commencement Certificate.pdf-
Modification of Plan DetailsFile: Sold and Unsold.xlsx-
Modification of Plan DetailsFile: Sold and Unsold.xlsx-
Document 1File: 1 FIRE NOC.pdf-
Document 2File: 3 AAI NOC.pdf-
Document 3File: 7 Bescom NOC.pdf-
Document 4File: 5 BWSSB - NOC.pdf-
Document 5File: 4 KSPCB NOC.pdf-
Document 6File: 2 MOEF Corrigendum.pdf-
Document 7File: 8 BSNL NOC.pdf-
Consent Letters-1-75File: Consent Letters-1-75.pdf-
Consent Letters-76-153File: Consent Letters-76-153.pdf-
Approved Plan OldFile: Approved Plan Old.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Architect Work Completed.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer Work Completed.pdf-
CA Certificate for Funds UtilizationFile: CA Funds Utilized.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Architect Work Pending.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer Work Pending.pdf-
CA Certificate for Funds required for Project CompletionFile: CA Funds Required.pdf-
AffidavitFile: Form B Affidavit.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
Document 1File: 1 FIRE NOC.pdf-
Document 2File: 2 MOEF Corrigendum.pdf-
Document 3File: 3 AAI NOC.pdf-
Document 4File: 4 KSPCB NOC.pdf-
Document 5File: 5 BWSSB - NOC.pdf-
Document 6File: 6 HAL.pdf-
LetterASN-
SD_compressed-
GROUND FLOOR_compressed-
specification_compressed-
Sreekaram ECs-
Affidavit-3(1)-
Affidavit Cum Declaration 3 in 1-
Khata and Khata Extract-
Srikaram JD-
Plan Sanction-Srikaram new-
Conversion Certificate-
Bescom NOC-
BWSSB srikaram-
K S P C B srikaram-
GROUND FLOOR_compressed-
Change in Land Use-
Balance Sheet 2017 - 2018File: 2017-18 BS.pdf-
Balance Sheet 2016 - 2017File: 2016-17 BS.pdf-
Balance Sheet 2015 - 2016File: 2015-16 BS.pdf-
Audited Profit and Loss Statement 2017 - 2018File: 2017-18 PL.pdf-
Audited Profit and Loss Statement 2016 - 2017File: 2016-17 PL.pdf-
Audited Profit and Loss Statement 2015 - 2016File: 2015-16 PL.pdf-
Cash Flow Statement 2017 - 2018File: ASNV Cash Flow 2017-18.pdf-
Cash Flow Statement 2016 - 2017File: ASNV Cash Flow 2016-17.pdf-
Auditor's Report 2017 - 2018File: AUDIT REPORT 17-18.pdf-
Auditor's Report 2016 - 2017File: AUDIT REPORT 16-17.pdf-
Auditor's Report 2015 - 2016File: AUDIT REPORT 15-16.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: 2017-18 Ack.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: 2016-17 Ack.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: 2015-16 Ack.pdf-
Form-B-
Prospectus/BrochureFile: ASN Srikaram Brochure.pdf-
Advertisement Copy 1File: Advertisement copy.pdf-
Tower Excel SheetFile: PRMKARERA1251446PR190829002840.xlsx-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 29 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep ASN SRIKARAM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmASN SRIKARAMOther 44Dot size: filed unitsN

Filed coordinates, straight-line distance. 44 registered projects within 2 km.

Builder: M/s.Ankuraa Sai Nitya Ventures

M/s.Ankuraa Sai Nitya Ventures has 1 registration on RERA Karnataka, including ASN SRIKARAM. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if ASN SRIKARAM is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ASN SRIKARAM?

The registered promoter entity is M/s.Ankuraa Sai Nitya Ventures, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ASN SRIKARAM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ASN SRIKARAM?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at ASN SRIKARAM?

The professionals named in the filing: Architect: Srinivas & Khan Architects; Engineer: Sterling. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ASN SRIKARAM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ASN SRIKARAM. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ASN SRIKARAM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.